Home / Browse projects / Sangli, Maharashtra / NIRMITI ELITE 14
NIRMITI ELITE 14
RG-MH-22350 · RERA P53100031761 · Last updated on MahaRERA portal: 2 Mar 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 13 months past the filed date
- Rs 1.00 crore secured on the land, in favour of Veeracharya Babasaheb Kuchnure Jilha Nagari Sahakari Patsanstha Maryadit
- The declared charge does not appear in the CERSAI report on the filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Sangli registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
NIRMITI ELITE 14 is a Residential / Group Housing project by SWASTIVASTU DEVELOPERS LLP in Sangli, Maharashtra, registered with MahaRERA as P53100031761 on 8 Nov 2021. Possession was promised by 9 Sep 2025 and is now 13 months past that date. 12 of the 14 units on this registration are recorded sold or booked, and 11 of 11 construction stages are filed complete.
At a glance
Project
- NameNIRMITI ELITE 14
- TypeResidential / Group Housing
- Location
- S T COLONY
- NEAR SAI MANDIR
- Sangli Miraj Kupwad (M Corp.)
- Miraj
- Sangli
- 416415
- Pincode416415
- MapView location on Google Maps (as filed on RERA)
- RERA no.P53100031761
- ReraGenie IDRG-MH-22350
Builder
- NameSWASTIVASTU DEVELOPERS LLP
- Entity typePartnership
- Other registrations4 more →
- Completed1 of 5
- No longer live3 lapsed, de-registered or revoked
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on8 Nov 2021
- Promised completion9 Sep 2025
- Revised completionNone
- Buildings1 building record
- Documents filed48 files
Current status
Figures as on 2 Mar 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| NIRMITI ELITE 14 | NA | 6 | 5 | 14 | 0 | 14 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 2 Mar 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
11 of 11 construction stages are filed complete.
NIRMITI ELITE 14: 100% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 2 Mar 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | No | Not applicable |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed10
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| NIRMITI ELITE 14 | NA | Rs 3.47 cr | Rs 3.47 cr |
Certifying professionals and partners5
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | MAHESH R PATIL |
| Engineer | A B KULKARNI |
| Engineer | VRUSHABH B BARGALE |
| Chartered Accountant | SURAJ R NILKANT |
| Chartered Accountant | DNYANESHWAR R AROTE |
| Partner | Role in project |
|---|---|
| SWASTIVASTU DEVELOPERS LLP | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 13 Oct 2021 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 15 Sep 2021 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 15 Sep 2021 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 15 Sep 2021Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed48
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: FORM-1 30-06-2025 .pdf | 2 Mar 2026 |
| Withdrawal Update Form 1File: FORM-1 30-09-2025 .pdf | 2 Mar 2026 |
| Withdrawal Update Form 2File: FORM-2 30-06-2025 .pdf | 2 Mar 2026 |
| Withdrawal Update Form 2File: FORM-2 30-09-2025.pdf | 2 Mar 2026 |
| Withdrawal Update Form 3File: FORM-3 30-06-25 .pdf | 2 Mar 2026 |
| Withdrawal Update Form 3File: FORM-3 30-09-25 .pdf | 2 Mar 2026 |
| Form 1File: FORM-1 30-06-24.pdf | 13 Jan 2026 |
| Form 2File: FORM-2 30-6-24.pdf | 13 Jan 2026 |
| Form 3File: FORM-3 30-6-24.pdf | 13 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD 30-6-24.pdf | 13 Jan 2026 |
| Form 1File: FORM-1 30-9-24.pdf | 13 Jan 2026 |
| Form 2File: FORM-2 30-9-24.pdf | 13 Jan 2026 |
| Form 3File: FORM-3 30-9-24.pdf | 13 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD 30-9-24.pdf | 13 Jan 2026 |
| Form 1File: FORM-1 31-12-24.pdf | 13 Jan 2026 |
| Form 2File: FORM-2 31-12-24.pdf | 13 Jan 2026 |
| Form 3File: FORM-3 31-12-24.pdf | 13 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD 31-12-24.pdf | 13 Jan 2026 |
| Form 1File: FORM-1 31-3-25.pdf | 13 Jan 2026 |
| Form 2File: FORM-2 31-3-25.pdf | 13 Jan 2026 |
| Form 3File: FORM-3 31-3-25.pdf | 13 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD 31-03-25.pdf | 13 Jan 2026 |
| Form 5 (FY 2024-2025)File: Form 5 2024-2025.pdf | 13 Jan 2026 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5 - NIRMITEE ELITE.pdf | 11 Jan 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 arch cer elite 3rd quat.pdf | 27 May 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2 engg cert Nirmiti Elite 14 3rd quater.pdf | 27 May 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3 Nirmiti elite 14 3rd quater.pdf | 27 May 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 Nirmiti Elite 14 for 21-22.pdf | 27 May 2023 |
| Disclosure of sold/ booked inventoryFile: Elte 14 3rd quat Sold Inventory as on 31march23.pdf | 24 Apr 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: architect certificate 2.pdf | 7 Feb 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: engineers certificate 2.pdf | 7 Feb 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: c a certificate 2.pdf | 7 Feb 2022 |
| Copy of the legal title reportFile: legal title report.pdf | 13 Oct 2021 |
| Layout approvalFile: MOJNI NAKASHA.pdf | 15 Sep 2021 |
| Building plan approvalFile: DWG SHEET 1.pdf | 15 Sep 2021 |
| Building plan approvalFile: DWG SHEET 2.pdf | 15 Sep 2021 |
| PAN CardFile: pan card firm-min.pdf | 15 Sep 2021 |
| Details of encumbrancesFile: NON-INCUMBRNCE.pdf | 15 Sep 2021 |
| Copy of Layout Approval (in case of layout)File: MOJNI NAKASHA.pdf | 15 Sep 2021 |
| Building Plan Approval / NA Order for plotted developmentFile: DWG SHEET 1.pdf | 15 Sep 2021 |
| Building Plan Approval / NA Order for plotted developmentFile: DWG SHEET 2.pdf | 15 Sep 2021 |
| Commencement Certificates / NA Order for plotted developmentFile: BANDHKAM PARWANA.pdf | 15 Sep 2021 |
| Declaration about Commencement CertificateFile: FORM D.pdf | 15 Sep 2021 |
| Declaration in FORM BFile: FORM B.pdf | 15 Sep 2021 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT CERTIFICATE.pdf | 15 Sep 2021 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEERS CERTIFICATE.pdf | 15 Sep 2021 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate.pdf | 15 Sep 2021 |
| Proforma of Allotment letterFile: Proforma of the allotment.pdf | 15 Sep 2021 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Sangli
Computed across the 790+ Sangli projects on ReraGenie, from their own filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 4 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 4 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 48 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep NIRMITI ELITE 14 on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near NEAR SAI MANDIR790+ in Sangli
Filed coordinates, straight-line distance. 31 registered projects within 2 km.
SHIV SAI VANDANA
S P BUILDER
Purva Heights
Kotibhaskar Builders
SHRI KRUPA ICON
TATYASAHEB SAMBHAJI KHOT
VAJE BUSINESS SQAURE
V D VAJE DEVELOPERS
KALESHWAR PRIDE
PRADEEP SHRIDHAR PHADKE
SAICHARAN HEIGHTS
ASHTANG DEVELOPERS
See every Sangli project, with the district possession charts
Builder: SWASTIVASTU DEVELOPERS LLP
SWASTIVASTU DEVELOPERS LLP has 5 registrations on MahaRERA, including NIRMITI RESIDENCY WING C AND D and NIRMITI ELITE 14. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Sangli district page.
Frequently asked questions
What does it mean that NIRMITI ELITE 14 shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if NIRMITI ELITE 14 is delayed beyond 9 Sep 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of NIRMITI ELITE 14?
The registered promoter entity is SWASTIVASTU DEVELOPERS LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in NIRMITI ELITE 14?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for NIRMITI ELITE 14?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at NIRMITI ELITE 14?
The professionals named in the filing: Architect: MAHESH R PATIL; Engineer: A B KULKARNI; Engineer: VRUSHABH B BARGALE; Chartered Accountant: SURAJ R NILKANT; Chartered Accountant: DNYANESHWAR R AROTE. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in NIRMITI ELITE 14?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.