Home / Browse projects / Mumbai Suburban, Maharashtra / NEW FRIENDS SRA CHS LTD
NEW FRIENDS SRA CHS LTD
RG-MH-11660 · RERA P51800008637 · Last updated on MahaRERA portal: 18 Aug 2025
Source: official MahaRERA filing
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against every project registered within 2 km.
See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
NEW FRIENDS SRA CHS LTD is a Others project by M/S. VIRAJ ENTERPRIES in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800008637 on 19 Aug 2017. The registration is recorded completed; possession was promised by 30 Oct 2023. 7 of the 7 units on this registration are recorded sold or booked, and 15 of 22 construction stages are filed complete.
At a glance
Project
- NameNEW FRIENDS SRA CHS LTD
- TypeOthers
- Location
- K C ROAD
- Andheri
- Mumbai Suburban
- 400050
- Pincode400050
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51800008637
- ReraGenie IDRG-MH-11660
Builder
- NameM/S. VIRAJ ENTERPRIES
- Entity typePartnership
- PartnerVIVEK SHANKAR JADHAV
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on19 Aug 2017
- Promised completion30 Oct 2023
- Revised completionNone
- Buildings2 building records
- Documents filed24 files
Current status
Figures as on 18 Aug 2025, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| NEW FRIENDS SRA CHS LTD | NA | 7 | 7 | 0 | 0 | 0 |
| ICONIC TOWER | NA | 26 | 26 | 7 | 0 | 7 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building2
As on 18 Aug 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
15 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Slabs of Super Structure, at 66%.
NEW FRIENDS SRA CHS LTD91%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
ICONIC TOWER53%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 66% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 10% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 10% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 18 Aug 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | No | Not applicable |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | No | Not applicable |
Parking filed25
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | AR JAYANT VAIDYA |
| Engineer | SATISH HANDE |
| Chartered Accountant | VDH AND CO |
| Partner | Role in project |
|---|---|
| M/S. VIRAJ ENTERPRIES | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 20 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 28 Jul 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 20 Jul 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 21 Feb 2019Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed24
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Occupational CertificateFile: Final Plan.pdf | 18 Aug 2025 |
| Occupational CertificateFile: OC Covering Letter Sale Bldg. Dt.- 18-10-2023..pdf | 4 Aug 2025 |
| Occupational CertificateFile: REHAB FULL OC Lette.pdf | 4 Aug 2025 |
| Occupational CertificateFile: Form 4.pdf | 4 Aug 2025 |
| Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate Sale Building.pdf | 21 Feb 2019 |
| OtherFile: Occupation Certificate of Rehab Building.pdf | 21 Feb 2019 |
| Certificates of CA (Form 5)File: 20181031160522.pdf | 31 Oct 2018 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER CERTIFICATE FORM 2 (SH).pdf | 1 Aug 2017 |
| Certificates of CA (Form 3)File: CA CERTIFICATE FORM NO 3.pdf | 1 Aug 2017 |
| Details of encumbrancesFile: ENCUMBRANCES.pdf | 31 Jul 2017 |
| Declaration in FORM BFile: Form B.pdf | 31 Jul 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE FORM 1.pdf | 31 Jul 2017 |
| Proforma of Allotment letterFile: Allotment Letter.pdf | 31 Jul 2017 |
| Layout approvalFile: Layout Plan.pdf | 28 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: Layout Plan.pdf | 28 Jul 2017 |
| Building plan approvalFile: PLAN 03 .pdf | 20 Jul 2017 |
| Copy of the legal title reportFile: Title Certificate report.pdf | 20 Jul 2017 |
| Building Plan Approval (IOD)File: PLAN 03 .pdf | 20 Jul 2017 |
| Building plan approvalFile: PLAN 1.pdf | 19 Jul 2017 |
| Building plan approvalFile: Plan 2.pdf | 19 Jul 2017 |
| PAN CardFile: VIRAJ ENTERPRISES PAN CARD.pdf | 19 Jul 2017 |
| Building Plan Approval (IOD)File: PLAN 1.pdf | 19 Jul 2017 |
| Building Plan Approval (IOD)File: Plan 2.pdf | 19 Jul 2017 |
| Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificates.pdf | 19 Jul 2017 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai Suburban
Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- Red flags and clear checks, the possession story, sanctions and sales, land and title, who you are dealing with
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 24 filed documents as one ZIP, foldered, with a manifest
Keep NEW FRIENDS SRA CHS LTD on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Andheri6,700+ in Mumbai Suburban
Filed coordinates, straight-line distance. 226 registered projects within 2 km.
Godrej Bandra Bay Phase 1
Godrej Properties Limited Roshni Developer
INSPIRA ONE
INSPIRA BUILDCON PRIVATE LIMITED
7 ELEMENTS
M&K Elements Realty LLP
The Waterfront
M/s Orbit Developers
Bay Heights
EXCEL ENTERPRISES INDIA PRIVATE LIMITED
33FIFTEEN
AJMERA LUXE REALTY PRIVATE LIMITED
See every Mumbai Suburban project, with the district possession charts
Builder: M/S. VIRAJ ENTERPRIES
M/S. VIRAJ ENTERPRIES has 1 registration on MahaRERA, including NEW FRIENDS SRA CHS LTD. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.
Frequently asked questions
What are my rights if NEW FRIENDS SRA CHS LTD is delayed beyond 30 Oct 2023?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of NEW FRIENDS SRA CHS LTD?
The registered promoter entity is M/S. VIRAJ ENTERPRIES, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in NEW FRIENDS SRA CHS LTD?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for NEW FRIENDS SRA CHS LTD?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at NEW FRIENDS SRA CHS LTD?
The professionals named in the filing: Architect: AR JAYANT VAIDYA; Engineer: SATISH HANDE; Chartered Accountant: VDH AND CO. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in NEW FRIENDS SRA CHS LTD?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback