Home / Browse projects / Raigarh, Maharashtra / NEELKANTH RESIDENCY

Registration lapsed No litigation declared Residential / Group Housing project

NEELKANTH RESIDENCY

By DEEPJYOTI INFRA DEVELOPERS

RG-MH-24878 · RERA P52000005307 · Last updated on MahaRERA portal: 5 Feb 2024

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 22 months past the filed date
  • 2 complaints at MahaRERA
  • Completion date moved by 72 months
  • 4 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.
Dec 2024Possession promised22 months past this date
27 of 66Construction stages doneacross 6 buildings; furthest along: Slabs of Super Structure, 50%
2Complaints at MahaRERAon this registration
Jump to the 105 documents Report an error

NEELKANTH RESIDENCY is a Residential / Group Housing project by DEEPJYOTI INFRA DEVELOPERS in Raigarh, Maharashtra, registered with MahaRERA as P52000005307 on 11 Aug 2017. Possession was promised by 25 Dec 2024 and is now 22 months past that date. The completion date has moved by 72 months from the original filing. 2 complaints are on record with the regulator.

At a glance

Project

  • NameNEELKANTH RESIDENCY
  • TypeResidential / Group Housing
  • Location
    • Bardi
    • Karjat
    • Raigarh
    • 410201
  • Pincode410201
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52000005307
  • ReraGenie IDRG-MH-24878

Builder

  • NameDEEPJYOTI INFRA DEVELOPERS
  • Entity typePartnership
  • PartnerRAMAKANT PRATAP KALSEKAR
  • Other registrations1 more →
  • No longer live2 lapsed, de-registered or revoked
  • Declared earlier projects1 →

Key dates

22 months past promisethis monthRegisteredAug 2017First promiseDec 2018Revised toDec 2024

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on11 Aug 2017
  • Promised completion25 Dec 2024
  • Revised completionRevised to 25 Dec 2024 (originally 31 Dec 2018)
  • Buildings6 building records
  • Documents filed105 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A BuildingNA50000
B BuildingNA50000
C BuildingNA50000
D BuildingNA50000
E BuildingNA50000
F BuildingNA50000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building6

As on 5 Feb 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

27 of 66 construction stages are filed complete across 6 buildings. The stage furthest along is Slabs of Super Structure, at 50%.

A Building27%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
B Building41%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure50%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
C Building47%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises20%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
D Building47%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises20%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
E Building55%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises40%
Sanitary Fittings within the flats / premises30%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.40%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
F Building51%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises20%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.40%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 5 Feb 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)NoNot applicable
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes50%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed1704

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots1,704
Open Space1,704
BuildingOpen SpaceTotal
A Building284284
B Building284284
C Building284284
D Building284284
E Building284284
F Building284284

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area7,300 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI6950.99
Proposed, not sanctioned6,951 sq m
Buildings approved6
Buildings sanctioned6

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchLOUISWADI THANE WEST

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSTRUCTILIS CONSULTANTS PVT LTD
EngineerADHARSHILA CONSULTANTS
Chartered AccountantSANTOSH SHIGVAN CO
PartnerRole in project
DEEPJYOTI INFRA DEVELOPERS-

Extensions applied for4

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52000013045Dec 2018 → Jun 2023

Reason as filed by the promoterTo, The Secretary, Maharashtra Real Estate Regulatory Authority 6th & 7th Floor, Housefin Bhavan, Plot No: C - 21, E - Block, Bandra Kurla Complex, Bandra (E), Mumbai 400051 Sub: (Extension of our Project “NEELKANTH RESIDENCY”) Dear Sir/Ma’am, There is some delay in completion of our project due to harsh impact of Covid 19 on real estate sector. Second wave has caused a lot of stress and trouble as our labour left for their hometown. We are expecting things to regain momentum in the upcoming months. We need more time to complete our project. It is kindly requested to accord extension of one ye

EXT52000005525Dec 2018 → Dec 2021

Reason as filed by the promoterThere are total 232 Units in our Neelkanth Residency Project and so far (as on 31/12/2019) 161 Units have been booked. We have obtained consent of 101 customers for extending the registration of Neelkanth Residency Project. It means 63% customers have No Objection / Consented for RERA Registration Extension for the period of 2 years from 31/12/2019. A copy of the same is attached herewith. Some customers have conveyed their consent through email, if required we can produce copies of said emails for your perusal. As regards project work, around seventy five percent work of the project is alread

EXT52000001252Dec 2018 → Dec 2021

Reason as filed by the promoteri) 70% work of the project is already completed and striving for completion of remaining work as fast as possible. ii) Though demonetization took place in the year 2016 and GST was unveiled in 2017, the real effects were felt in 2018. The 12% GST is a dampener as it tends to spoil the entire budget of the homebuyer. Many customers who had booked residential units withdrawn after GST implementation. iii) As on date we have completed 70% work of the project and have contributed much more own fund in the project than amount collected from the customers. Although 45% inventory of the project is st

EXT52000018639Dec 2018 → Dec 2024

Reason as filed by the promoterDue to medical reason

Complaints filed with MahaRERA2

Case no.ComplainantRespondentFiled
CC006000000193769Baburao ChouguleRAJENDRA S UTEKAR19/08/2020
CC006000000198286Ajit Vishwanath TaralkarM/s Deepjyoti Infra Developers11/10/2021

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 28 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 28 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 28 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 31 Mar 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed105

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 105 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Declaration in FORM BFile: Format B.pdf5 Feb 2024
Declaration in FORM BFile: Format B-1-1-3.pdf2 Feb 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: fORM 2A 19-20.pdf1 Feb 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FORM 2A 20-21.pdf1 Feb 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FORM 2A 21-22.pdf1 Feb 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A 22-23.pdf1 Feb 2024
Disclosure of sold/ booked inventoryFile: Sold and unsold inventory.pdf1 Feb 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: FORM 5 18-19.pdf1 Feb 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: fORM 2A 19-20.pdf1 Feb 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM 5 20-21.pdf1 Feb 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: fORM 5 2021-22.pdf1 Feb 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 2022-23.pdf1 Feb 2024
Details of encumbrances concerned to FinanceFile: DETAILS OF ENCUM.pdf31 Jan 2024
Details of encumbrances concerned to LegalFile: DETAILS OF ENCUM.pdf31 Jan 2024
Declaration about Commencement CertificateFile: NA (1).pdf31 Jan 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: fORM 2A 19-20.pdf31 Jan 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FORM 2A 20-21.pdf31 Jan 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FORM 2A 21-22.pdf31 Jan 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A 22-23.pdf31 Jan 2024
Disclosure of sold/ booked inventoryFile: Sold and unsold inventory.pdf31 Jan 2024
CERSAI detailsFile: CERSAI DETAILS.pdf31 Jan 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: ANNEXURE A.pdf31 Jan 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: fORM 5 2021-22.pdf31 Jan 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 2022-23.pdf31 Jan 2024
Proforma of Agreement for saleFile: Sample_Agreement for Sale_NR_compressed.pdf31 Jan 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Format A.pdf31 Jan 2024
Deviation Report with respect to Allotment letterFile: aLLOTTMENT LETTER.pdf31 Jan 2024
Deviation Report with respect to model copy of AgreementFile: Sample_Agreement for Sale_NR_compressed.pdf31 Jan 2024
Declaration in FORM BFile: Form B.pdf25 Jan 2024
Declaration in FORM BFile: Format B.pdf25 Jan 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf25 Jan 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf25 Jan 2024
Certificates of CA (Form 3)File: Form 3.pdf25 Jan 2024
Certificates of CA (Form 5)File: Form 5.pdf25 Jan 2024
Certificates of CA (Form 5)File: from5.pdf25 Jan 2024
Other - LegalFile: Request to Maharera_deletion of name_NR-merged_11zon_11zon.pdf30 May 2023
Other - TechnicalFile: Request to Maharera_deletion of name_NR-merged_11zon_11zon.pdf30 May 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Annual Report 2018-2019.pdf11 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Annual Report 2019-2020.pdf11 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Annual Report 2020-2021.pdf11 Feb 2023
Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD BOOKED INVENTORY for MahaRERA.pdf3 May 2021
Certificates of CA (Form 5)File: Form 5_NR.pdf1 Jan 2019
Commencement Certificates / NA Order for plotted developmentFile: NA Copy_1.pdf31 Mar 2018
Commencement Certificates / NA Order for plotted developmentFile: NA Copy_2.pdf31 Mar 2018
Commencement Certificates / NA Order for plotted developmentFile: NA Copy_3.pdf31 Mar 2018
Commencement Certificates / NA Order for plotted developmentFile: NA Copy_4.pdf31 Mar 2018
Commencement Certificates / NA Order for plotted developmentFile: NA Copy_5.pdf31 Mar 2018
Commencement Certificates / NA Order for plotted developmentFile: NA Copy_6.pdf31 Mar 2018
Commencement Certificates / NA Order for plotted developmentFile: NA Copy_7.pdf31 Mar 2018
Commencement Certificates / NA Order for plotted developmentFile: NA Copy_8.pdf31 Mar 2018
Proforma of Allotment letterFile: Allotment Letter_Sample.pdf29 Jul 2017
Proforma of Allotment letterFile: draft copy of sale agreement_NR.pdf29 Jul 2017
Layout approvalFile: Type-5.pdf28 Jul 2017
Layout approvalFile: Type-1.pdf28 Jul 2017
Layout approvalFile: Type-3-4-6.pdf28 Jul 2017
Layout approvalFile: Type-2.pdf28 Jul 2017
Building plan approvalFile: NA Copy_5.pdf28 Jul 2017
Building plan approvalFile: NA Copy_6.pdf28 Jul 2017
Building plan approvalFile: NA Copy_8.pdf28 Jul 2017
Building plan approvalFile: NA Copy_1.pdf28 Jul 2017
Building plan approvalFile: NA Copy_2.pdf28 Jul 2017
Building plan approvalFile: NA Copy_3.pdf28 Jul 2017
Building plan approvalFile: NA Copy_4.pdf28 Jul 2017
Building plan approvalFile: NA Copy_7.pdf28 Jul 2017
PAN CardFile: Deepjyoti Infra Developers Pan card Copy.pdf28 Jul 2017
Copy of the legal title reportFile: scan0454.pdf28 Jul 2017
Copy of the legal title reportFile: scan0455.pdf28 Jul 2017
Copy of the legal title reportFile: scan0456.pdf28 Jul 2017
Copy of the legal title reportFile: scan0457.pdf28 Jul 2017
Copy of the legal title reportFile: scan0458.pdf28 Jul 2017
Copy of the legal title reportFile: scan0459.pdf28 Jul 2017
Copy of the legal title reportFile: scan0460.pdf28 Jul 2017
Copy of the legal title reportFile: scan0461.pdf28 Jul 2017
Copy of the legal title reportFile: scan0462.pdf28 Jul 2017
Copy of the legal title reportFile: scan0463.pdf28 Jul 2017
Details of encumbrancesFile: encumbrances certificate_NR.pdf28 Jul 2017
Copy of Layout Approval (in case of layout)File: Type-1.pdf28 Jul 2017
Copy of Layout Approval (in case of layout)File: Type-2.pdf28 Jul 2017
Copy of Layout Approval (in case of layout)File: Type-3-4-6.pdf28 Jul 2017
Copy of Layout Approval (in case of layout)File: Type-5.pdf28 Jul 2017

How this compares with Raigarh

20%of Raigarh projects moved their completion datethis one moved by 72 months
26%of Raigarh registrations have lapsed or been cancelledthis one is among them

Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.

Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep NEELKANTH RESIDENCY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Bardi5,900+ in Raigarh

2 kmNEELKANTH RESIDENCYCompleted 59Lapsed / revoked 42Other 50Dot size: filed unitsN

Filed coordinates, straight-line distance. 151 registered projects within 2 km.

Builder: DEEPJYOTI INFRA DEVELOPERS

DEEPJYOTI INFRA DEVELOPERS has 2 registrations on MahaRERA, including NEELKANTH RESIDENCY and PLATINUM RESIDENCY. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Raigarh district page.

Frequently asked questions

What does it mean that NEELKANTH RESIDENCY shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if NEELKANTH RESIDENCY is delayed beyond 25 Dec 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of NEELKANTH RESIDENCY?

The registered promoter entity is DEEPJYOTI INFRA DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in NEELKANTH RESIDENCY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against NEELKANTH RESIDENCY?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for NEELKANTH RESIDENCY?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at NEELKANTH RESIDENCY?

The professionals named in the filing: Architect: STRUCTILIS CONSULTANTS PVT LTD; Engineer: ADHARSHILA CONSULTANTS; Chartered Accountant: SANTOSH SHIGVAN CO. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in NEELKANTH RESIDENCY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About NEELKANTH RESIDENCY. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save NEELKANTH RESIDENCY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.