ReraGenieLog inGet a buyer report

Home / Browse projects / Nagpur, Maharashtra / NEEL CITY

Registration lapsed No litigation declared Residential / Group Housing project

NEEL CITY

By RAJAT DEVELOPERS & BUILDERS

RG-MH-07911 · RERA P50500014354 · Last updated on MahaRERA portal: 10 May 2026

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 10 months past the filed date
  • Completion date moved by 25 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Nagpur registration emailed to you, free during the pilot beta.
Dec 2025Possession promised10 months past this date
72 of 297Construction stages doneacross 27 buildings; furthest along: Staircases, 80%
146 of 146Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 159 documents Report an error

NEEL CITY is a Residential / Group Housing project by RAJAT DEVELOPERS & BUILDERS in Nagpur, Maharashtra, registered with MahaRERA as P50500014354 on 24 Nov 2017. Possession was promised by 19 Dec 2025 and is now 10 months past that date. The completion date has moved by 25 months from the original filing. 0 of the 146 units on this registration are recorded sold or booked, and 72 of 297 construction stages are filed complete.

At a glance

Project

  • NameNEEL CITY
  • TypeResidential / Group Housing
  • Location
    • MAHARASHTRA
    • NAGPUR
    • Hingna
    • 441110
  • Pincode441110
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P50500014354
  • ReraGenie IDRG-MH-07911

Builder

  • NameRAJAT DEVELOPERS & BUILDERS
  • Entity typePartnership
  • GSTIN27AATFR2584B1ZX
  • PartnerSHEVANTI SHALIKRAM ASHTIKAR

Key dates

10 months past promisethis monthRegisteredNov 2017First promiseNov 2023Revised toDec 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on24 Nov 2017
  • Promised completion19 Dec 2025
  • Revised completionRevised to 19 Dec 2025 (originally 28 Nov 2023)
  • Buildings27 building records
  • Documents filed159 files

Current status

0%0 of 146 units booked

Figures as on 10 May 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Twin Bunglow 23NA33101
Duplex 2NA33101
TOWER 1NA74521365
TOWER 2NA7456056
Duplex 1NA33101
Twin Bunglow 1NA33101
Twin Bunglow 2NA33101
Twin Bunglow 3NA33101
Twin Bunglow 4NA33101
Twin Bunglow 5NA33101
Twin Bunglow 6NA33101
Twin Bunglow 7NA33101
Twin Bunglow 8NA33101
Twin Bunglow 9NA33101
Twin Bunglow 10NA33101
Twin Bunglow 11NA33101
Twin Bunglow 12NA33101
Twin Bunglow 13NA33101
Twin Bunglow 14NA33101
Twin Bunglow 15NA33101
Twin Bunglow 16NA33101
Twin Bunglow 17NA33101
Twin Bunglow 18NA33101
Twin Bunglow 19NA33101
Twin Bunglow 20NA33101
Twin Bunglow 21NA33101
Twin Bunglow 22NA33101

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building20

As on 10 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection. The count above covers all 27 buildings; the table lists the first 20.

72 of 297 construction stages are filed complete across 27 buildings. The stage furthest along is Staircases, at 80%.

Twin Bunglow 230%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Duplex 20%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
TOWER 155%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises20%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
TOWER 20%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Duplex 10%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Twin Bunglow 10%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Twin Bunglow 20%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Twin Bunglow 327%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Twin Bunglow 427%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Twin Bunglow 556%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.20%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Twin Bunglow 656%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.20%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Twin Bunglow 756%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.20%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Twin Bunglow 856%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.20%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Twin Bunglow 927%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Twin Bunglow 1027%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Twin Bunglow 1173%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Twin Bunglow 1273%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Twin Bunglow 130%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Twin Bunglow 140%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Twin Bunglow 150%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 10 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes95%
Water SupplyYes80%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes65%
Landscaping & Tree PlantingYes30%
Street LightingYes100%
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntYes0%
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes71%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed114

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots114
Open Space114
BuildingOpen SpaceTotal
Twin Bunglow 2311
Duplex 211
TOWER 14343
TOWER 24646
Duplex 111
Twin Bunglow 111
Twin Bunglow 211
Twin Bunglow 311
Twin Bunglow 411
Twin Bunglow 511
Twin Bunglow 611
Twin Bunglow 711
Twin Bunglow 811
Twin Bunglow 911
Twin Bunglow 1011
Twin Bunglow 1111
Twin Bunglow 1211
Twin Bunglow 1311
Twin Bunglow 1411
Twin Bunglow 1511
Twin Bunglow 1611
Twin Bunglow 1711
Twin Bunglow 1811
Twin Bunglow 1911
Twin Bunglow 2011
Twin Bunglow 2111
Twin Bunglow 2211

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area6,877 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on13 Apr 2026

Approvals and building plan

Sanctioning authoritynagar panchayat hingna nagpur
Permissible FSI11532.3
Proposed, not sanctioned8,832 sq m
Buildings approved27
Buildings sanctioned27

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchTELECOM NAGAR NERA Pratap Nagpur 440025

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectPRAVIN DHONE
EngineerAMIR DILIP THAKRE
Chartered AccountantRAM BONDE
PartnerRole in project
RAJAT DEVELOPERS & BUILDERS-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT50500018050Nov 2023 → Dec 2024

Reason as filed by the promoterDue to COVID-19, projects have been delayed, and the promoters have decided to prioritize completing the sections of the project for which bookings were received first. Currently, the promoters have successfully completed the booked units, obtaining the occupancy certificate for them. Construction has now commenced for the remaining unbooked units. In Tower 1, there are 52 flats and 13 shops, all sold and occupancy certificate received.25 bungalows, for 18 occupancy received. Rest 7 bungalow under construction70% work done and 5 booked. As for Tower 2, construction work has begun and 25% work

EXT50500027525Nov 2023 → Dec 2025

Reason as filed by the promoter1. DUE TO COVID THE WORK WAS DELAYED AND ALSO BOOKING WERE DELAYED . 2 SANCTION MAP WAS REVISED DUE TO INCREASE IN UNITS.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 17 Nov 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 17 Nov 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 16 Feb 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 17 Nov 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed159

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 159 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 2A (FY 2024-2025)File: 2a march 25.pdf10 May 2026
Form 5 (FY 2024-2025)File: form 5 march 25.pdf6 Feb 2026
Disclosure of Sold and Booked InventoryFile: ilovepdf_merged (1).pdf5 Feb 2026
Form 1File: FORM 1 SEP 2025.pdf5 Feb 2026
Form 2File: sep 25 engineer certificate.pdf5 Feb 2026
Form 3File: FORM 3 SEP 25.pdf5 Feb 2026
Form 3File: FORM 3 DEC 25.pdf3 Feb 2026
Form 1File: FORM 1 DEC 2025.pdf3 Feb 2026
Form 2File: dec 25 engineer certificate.pdf3 Feb 2026
Disclosure of Sold and Booked InventoryFile: ilovepdf_merged.pdf3 Feb 2026
Form 1File: FORM 1_JUNE 2025.pdf23 Aug 2025
Form 2File: FORM 2_JUNE 2025.pdf23 Aug 2025
Form 3File: _RAJAT DEV FORM 3_JUNE 2025.pdf23 Aug 2025
Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF INVENTORY JUNE 2025.pdf23 Aug 2025
Form 1File: FORM 1_MARCH 2025.pdf13 Aug 2025
Form 2File: FORM 2_MARCH 2025.pdf13 Aug 2025
Form 3File: rajat dev form 3 march 25.pdf13 Aug 2025
Disclosure of Sold and Booked InventoryFile: sold unsold inventory march 2025.pdf13 Aug 2025
OtherFile: ROW HOUSE DUPLEX.pdf17 Mar 2025
OtherFile: TOWER 1.pdf17 Mar 2025
OtherFile: TOWER 2.pdf17 Mar 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: form 5.pdf19 Feb 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: MARCH24.pdf29 Jan 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: JUNE24.pdf29 Jan 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: SEP24.pdf29 Jan 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: DEC24.pdf29 Jan 2025
Certificates of CA (Form 3)File: MARCH 24.pdf29 Jan 2025
Certificates of CA (Form 3)File: JUNE 24.pdf29 Jan 2025
Certificates of CA (Form 3)File: SEP 24.pdf29 Jan 2025
Certificates of CA (Form 3)File: DEC 24.pdf29 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: MARCH24.pdf29 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: JUNE24.pdf29 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: SEP24.pdf29 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: DEC24.pdf29 Jan 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: form2A.pdf29 Jan 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT.pdf7 Feb 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER.pdf7 Feb 2024
Declaration about Commencement CertificateFile: declaration about commencement certificate.pdf6 Feb 2024
CERSAI detailsFile: cersai_CERSAI(2)_merged.pdf6 Feb 2024
Disclosure of sold/ booked inventoryFile: sold unsold.pdf6 Feb 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: MANISHA interest in other real estate.pdf6 Feb 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: SHEVANTI interest in other real estate.pdf6 Feb 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: separate bank account.pdf6 Feb 2024
Certificates of CA (Form 3)File: RAJAT FORM 3 DEC - 2023.pdf30 Jan 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 31-3-23.pdf2 Jan 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 30-6-23.pdf2 Jan 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 30-9-23.pdf2 Jan 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 31-3-23.pdf2 Jan 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 30-6-23.pdf2 Jan 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 30-9-23.pdf2 Jan 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A.pdf2 Jan 2024
Certificates of CA (Form 3)File: FORM 3(31ST MARCH).pdf2 Jan 2024
Certificates of CA (Form 3)File: FORM 3 (30TH JUN).pdf2 Jan 2024
Certificates of CA (Form 3)File: FORM 3(30 SEPT).pdf2 Jan 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5 (RAJAT).pdf2 Jan 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: form 2A.pdf22 Feb 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 1 30-9-21.pdf21 Feb 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 2 31-12-21.pdf21 Feb 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 3 31-3-22.pdf21 Feb 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 4 30-6-22.pdf21 Feb 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 5 30-9-22.pdf21 Feb 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 6 31-12-22.pdf21 Feb 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 1 30-9-21.pdf21 Feb 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 2 31-12-21.pdf21 Feb 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 3 31-3-22.pdf21 Feb 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 4 30-6-22.pdf21 Feb 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 5 30-9-22.pdf21 Feb 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 6 31-12-22.pdf21 Feb 2023
Building plan approvalFile: 616.pdf16 Feb 2023
Building plan approvalFile: 617.pdf16 Feb 2023
Building plan approvalFile: 618.pdf16 Feb 2023
Building Plan Approval (IOD)File: 616.pdf16 Feb 2023
Building Plan Approval (IOD)File: 617.pdf16 Feb 2023
Building Plan Approval (IOD)File: 618.pdf16 Feb 2023
Certificates of CA (Form 3)File: 1 SEPT 21.pdf16 Feb 2023
Certificates of CA (Form 3)File: 2 DEC 21.pdf16 Feb 2023
Certificates of CA (Form 3)File: 3 MARCH 22.pdf16 Feb 2023
Certificates of CA (Form 3)File: 4 JUNE 22.pdf16 Feb 2023
Certificates of CA (Form 3)File: 5 SEPT 22.pdf16 Feb 2023
Certificates of CA (Form 3)File: 6 DEC 22.pdf16 Feb 2023

How this compares with Nagpur

0%of this project is bookeddistrict median 35%
13%of Nagpur projects moved their completion datethis one moved by 25 months
22%of Nagpur registrations have lapsed or been cancelledthis one is among them

Computed across the 2,800+ Nagpur projects on ReraGenie, from their own filings.

Free monthly report: Nagpur on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep NEEL CITY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near NAGPUR2,800+ in Nagpur

2 kmNEEL CITYCompleted 15Lapsed / revoked 7Other 16Dot size: filed unitsN

Filed coordinates, straight-line distance. 38 registered projects within 2 km.

Builder: RAJAT DEVELOPERS & BUILDERS

RAJAT DEVELOPERS & BUILDERS has 1 registration on MahaRERA, including NEEL CITY. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Nagpur district page.

Frequently asked questions

What does it mean that NEEL CITY shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if NEEL CITY is delayed beyond 19 Dec 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of NEEL CITY?

The registered promoter entity is RAJAT DEVELOPERS & BUILDERS, a partnership as per the filing. Its GSTIN 27AATFR2584B1ZX can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in NEEL CITY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for NEEL CITY?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at NEEL CITY?

The professionals named in the filing: Architect: PRAVIN DHONE; Engineer: AMIR DILIP THAKRE; Chartered Accountant: RAM BONDE. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in NEEL CITY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About NEEL CITY. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save NEEL CITY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.