Home / Browse projects / Mumbai Suburban, Maharashtra / Navrang Atlantis

Registered No litigation declared Others project

Navrang Atlantis

By Oxford Worldone Realty LLP

RG-MH-31839 · RERA P51800080163 · Last updated on MahaRERA portal: 20 Apr 2026

Source: official MahaRERA filing

Red flags

  • Rs 55.00 crore secured on the land, in favour of A U SMALL FINANCE BANK LIMITED

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Jan 2029Possession promisedno revision filed
3 of 11Construction stages donefurthest along: Basement (if any), 80%
113 of 120Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 75 documents Report an error

Navrang Atlantis is a Others project by Oxford Worldone Realty LLP in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800080163 on 2 May 2025. Possession is promised by 31 Jan 2029. 7 of the 120 units on this registration are recorded sold or booked, and 3 of 11 construction stages are filed complete.

At a glance

Project

  • NameNavrang Atlantis
  • TypeOthers
  • Location
    • Oshiwara Godavari CHSL
    • Building no. 1
    • C St No
    • 2/B
    • Adarsh Nagar
    • Mhada Layout
    • Village Oshiwara
    • Jogeshwari West
    • Mumbai
    • Oshiwara
    • Andheri
    • Mumbai...
  • Pincode400102
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800080163
  • ReraGenie IDRG-MH-31839

Builder

  • NameOxford Worldone Realty LLP
  • Entity typePartnership

Key dates

this monthRegisteredMay 2025PromisedJan 2029

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on2 May 2025
  • Promised completion31 Jan 2029
  • Revised completionNone
  • Buildings1 building record
  • Documents filed75 files

Current status

6%7 of 120 units booked
40.3%Work done, per cost certificate

Figures as on 20 Apr 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Navrang AtlantisNA33321164120

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 20 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

3 of 11 construction stages are filed complete. The stage furthest along is Basement (if any), at 80%.

Navrang Atlantis: 36% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)80%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure6%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks6%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 20 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed135

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots135
Closed/Covered134
Open Space1

Land and ownership1

MahaRERA does not publish landowner contact details. A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area972 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
Encumbrance on the landDeclared present
Charge in favour ofA U SMALL FINANCE BANK LIMITED
Secured amountRs 55.00 crore
CERSAI search filedYes
Declared on23 Sep 2025
LandownerVillageDistrict
Oshiwara Godavari Co-operative Housing Society LTDOshiwaraMumbai Suburban

Approvals and building plan

Sanctioning authorityMHADA
Permissible FSI7683.87
Proposed, not sanctioned7,684 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchShop No 16, Ground Floor, Kanakia Zillion, LBS-CST Road, Junction,BKC Annexe, Kurla(W),Mumbai,Maharashtra-400070
Estimated costRs 105.64 cr
Cost incurredRs 42.60 cr
Work done40.33%
BuildingWingEstimatedIncurred
Navrang AtlantisNARs 97.46 crRs 41.63 cr
-NARs 8.18 crRs 97.01 lakh

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSPACE MOULDERS
EngineerOm Gurudatta Contractor
Chartered AccountantR D LUKAD & CO
Chartered AccountantM N N Y & Associates LLP
PartnerRole in project
Oxford Worldone Realty LLP-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 23 Apr 2025
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 23 Apr 2025
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 23 Apr 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 20 Apr 2026Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Jan 2029

Documents filed75

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Commencement certificateFile: Further CC.pdf20 Apr 2026
Withdrawal Update Form 1File: Form-1 Q4.pdf20 Apr 2026
Withdrawal Update Form 2File: Form-2 Q4.pdf20 Apr 2026
Withdrawal Update Form 3File: Form-3 Q4.pdf20 Apr 2026
Withdrawal Update Form 1File: form 1 Q3.pdf20 Jan 2026
Withdrawal Update Form 2File: FORM 2.pdf20 Jan 2026
Withdrawal Update Form 3File: Final Form-3 Q3_compressed.pdf20 Jan 2026
Withdrawal Update Form 1File: FORM 1 Q2.pdf4 Nov 2025
Withdrawal Update Form 2File: FORM 2 Q2.pdf4 Nov 2025
Withdrawal Update Form 3File: Final Form-3 Q2_compressed.pdf4 Nov 2025
Withdrawal Update Form 1File: FORM 1.pdf22 Jul 2025
Withdrawal Update Form 2File: FORM-2.pdf22 Jul 2025
Withdrawal Update Form 3File: Form 3_compressed.pdf22 Jul 2025
Withdrawal Update Form 1File: FORM 1.pdf21 Jul 2025
Withdrawal Update Form 1File: FORM 1.pdf21 Jul 2025
Withdrawal Update Form 1File: FORM 1.pdf21 Jul 2025
Withdrawal Update Form 2File: FORM-2.pdf21 Jul 2025
Withdrawal Update Form 2File: FORM-2.pdf21 Jul 2025
Withdrawal Update Form 2File: FORM-2.pdf21 Jul 2025
Withdrawal Update Form 3File: Form 3_compressed.pdf21 Jul 2025
Withdrawal Update Form 3File: Form 3_compressed.pdf21 Jul 2025
Withdrawal Update Form 3File: Form 3_compressed.pdf21 Jul 2025
Withdrawal Update Form 1File: 1 Architect’s Certificate of Percentage of Completion of Work (Form 1).pdf19 Jul 2025
Withdrawal Update Form 2File: 1 Engineer’s Certificate on Cost Incurred on Project (Form 2).pdf19 Jul 2025
Withdrawal Update Form 3File: Form 3_compressed.pdf19 Jul 2025
Layout approvalFile: 1 Copy of Layout Approval (in case of layout).pdf23 Apr 2025
Building plan approvalFile: 1 Building Plan Approval _ NA Order for plotted development.pdf23 Apr 2025
Building plan approvalFile: 2 Building Plan Approval _ NA Order for plotted development.pdf23 Apr 2025
Building plan approvalFile: 3 Building Plan Approval _ NA Order for plotted development.pdf23 Apr 2025
Building plan approvalFile: 4 Building Plan Approval _ NA Order for plotted development.pdf23 Apr 2025
Building plan approvalFile: 5 Building Plan Approval _ NA Order for plotted development.pdf23 Apr 2025
Building plan approvalFile: 6 Building Plan Approval _ NA Order for plotted development.pdf23 Apr 2025
Building plan approvalFile: 7 Building Plan Approval _ NA Order for plotted development.pdf23 Apr 2025
Building plan approvalFile: 8 Building Plan Approval _ NA Order for plotted development.pdf23 Apr 2025
Building plan approvalFile: 9 Building Plan Approval _ NA Order for plotted development.pdf23 Apr 2025
Building plan approvalFile: 10 Building Plan Approval _ NA Order for plotted development.pdf23 Apr 2025
PAN CardFile: 1 PAN Card.pdf23 Apr 2025
Copy of the legal title reportFile: 1 Copy of the legal title report.pdf23 Apr 2025
Details of encumbrances concerned to FinanceFile: 1 b Details of encumbrances concerned to Legal.pdf23 Apr 2025
Details of encumbrances concerned to FinanceFile: 2 a Details of encumbrances concerned to Finance.pdf23 Apr 2025
Copy of Layout Approval (in case of layout)File: 1 Copy of Layout Approval (in case of layout).pdf23 Apr 2025
Proforma of Allotment letterFile: 1 Proforma of Allotment letter.pdf23 Apr 2025
Declaration in FORM BFile: 1 Declaration in FORM B.pdf23 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1 Architect’s Certificate of Percentage of Completion of Work (Form 1).pdf23 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 1 CA Certificate on Project Cost Fund withdrawal Form 3.pdf23 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 1 Engineer’s Certificate on Cost Incurred on Project (Form 2).pdf23 Apr 2025
Commencement Certificates / NA Order for plotted developmentFile: 1 Commencement Certificates _ NA Order for plotted development.pdf23 Apr 2025
Building Plan Approval / NA Order for plotted developmentFile: 9 Building Plan Approval _ NA Order for plotted development.pdf23 Apr 2025
Building Plan Approval / NA Order for plotted developmentFile: 10 Building Plan Approval _ NA Order for plotted development.pdf23 Apr 2025
Building Plan Approval / NA Order for plotted developmentFile: 8 Building Plan Approval _ NA Order for plotted development.pdf23 Apr 2025
Building Plan Approval / NA Order for plotted developmentFile: 7 Building Plan Approval _ NA Order for plotted development.pdf23 Apr 2025
Building Plan Approval / NA Order for plotted developmentFile: 6 Building Plan Approval _ NA Order for plotted development.pdf23 Apr 2025
Building Plan Approval / NA Order for plotted developmentFile: 4 Building Plan Approval _ NA Order for plotted development.pdf23 Apr 2025
Building Plan Approval / NA Order for plotted developmentFile: 3 Building Plan Approval _ NA Order for plotted development.pdf23 Apr 2025
Building Plan Approval / NA Order for plotted developmentFile: 2 Building Plan Approval _ NA Order for plotted development.pdf23 Apr 2025
Building Plan Approval / NA Order for plotted developmentFile: 1 Building Plan Approval _ NA Order for plotted development.pdf23 Apr 2025
Building Plan Approval / NA Order for plotted developmentFile: 5 Building Plan Approval _ NA Order for plotted development.pdf23 Apr 2025
Other - LegalFile: 1 Other - Legal.pdf23 Apr 2025
Other - LegalFile: 2 Other - Legal.pdf23 Apr 2025
Declaration about Commencement CertificateFile: 1 Declaration about Commencement Certificate.pdf23 Apr 2025
CERSAI detailsFile: 1 CERSAI details.pdf23 Apr 2025
Declaration about all RERA Designated Bank Accounts (Format A)File: 1 Declaration about all RERA Designated Bank Accounts (Format A).pdf23 Apr 2025
Deviation Report with respect to Allotment letterFile: 1 Deviation Report with respect to Allotment letter.pdf23 Apr 2025
Details of encumbrances concerned to LegalFile: 1 b Details of encumbrances concerned to Legal.pdf23 Apr 2025
Details of encumbrances concerned to LegalFile: 2 a Details of encumbrances concerned to Finance.pdf23 Apr 2025
Other - TechnicalFile: 1 Other - Technical.pdf23 Apr 2025
Other - TechnicalFile: 2 Other - Technical.pdf23 Apr 2025
Deviation Report with respect to model copy of AgreementFile: 1 Deviation Report with respect to model copy of Agreement.pdf23 Apr 2025
Proforma of Agreement for saleFile: 1 Proforma of Agreement for sale.pdf23 Apr 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: 1 Disclosure of Interest in Other Real Estate Organizations.pdf23 Apr 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: 2 Disclosure of Interest in Other Real Estate Organizations.pdf23 Apr 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: 3 Disclosure of Interest in Other Real Estate Organizations.pdf23 Apr 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: 4 Disclosure of Interest in Other Real Estate Organizations.pdf23 Apr 2025
Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: 1 Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B).p23 Apr 2025
Disclosure for secured/unsecured finance availed for the projectFile: 1 Disclosure for secured_unsecured finance availed for the project.pdf23 Apr 2025

How this compares with Mumbai Suburban

6%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one has not
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is on the register

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Navrang Atlantis on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Village Oshiwara, Jogeshwari West , Mumbai6,700+ in Mumbai Suburban

2 kmNavrang AtlantisCompleted 124Lapsed / revoked 71Abeyance 1Other 136Dot size: filed unitsN

Filed coordinates, straight-line distance. 332 registered projects within 2 km.

Builder: Oxford Worldone Realty LLP

Oxford Worldone Realty LLP has 1 registration on MahaRERA, including Navrang Atlantis. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if Navrang Atlantis is delayed beyond 31 Jan 2029?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Navrang Atlantis?

The registered promoter entity is Oxford Worldone Realty LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Navrang Atlantis?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Navrang Atlantis?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Navrang Atlantis?

The professionals named in the filing: Architect: SPACE MOULDERS; Engineer: Om Gurudatta Contractor; Chartered Accountant: R D LUKAD & CO; Chartered Accountant: M N N Y & Associates LLP. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Navrang Atlantis?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Navrang Atlantis. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Navrang Atlantis to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.