NATURE PARADISE
RG-MH-11502 · RERA P52000001604 · Last updated on MahaRERA portal: 16 Jun 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Completion date moved by 102 months
- 2 extensions taken
Clear
- No litigation declared
- No complaints on record
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
NATURE PARADISE is a Mixed project by VISHWA REAL ESTATE CO in Raigarh, Maharashtra, registered with MahaRERA as P52000001604 on 29 Jul 2017. Possession is promised by 31 Dec 2029. The completion date has moved by 102 months from the original filing. 121 of the 234 units on this registration are recorded sold or booked, and 493 of 1287 construction stages are filed complete.
At a glance
Project
- NameNATURE PARADISE
- TypeMixed
- Location
- Alibagh
- Mulgaon T. Wasare
- Karjat
- Raigarh
- 410201
- Pincode410201
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52000001604
- ReraGenie IDRG-MH-11502
Builder
- NameVISHWA REAL ESTATE CO
- Entity typePartnership
- PartnersARCHANA RAVINDRA POTDAR, AAKASH RAVINDRA POTDAR, SHRIRAM BHASKAR VIBHANDIK, PRAVIN RAMDAS KUNJIWAL, SUREKHA PRAVIN KUNJIWAL, SUNIL EKNATHRAO PANDIT, MANISHA SUNIL PANDIT
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on29 Jul 2017
- Promised completion31 Dec 2029
- Revised completionRevised to 31 Dec 2029 (originally 30 Jun 2021)
- Buildings117 building records
- Documents filed108 files
Current status
Figures as on 16 Jun 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| LIG E TYPE PLOT NO 48 | NA | 2 | 2 | 2 | 0 | 2 |
| LIG E TYPE PLOT NO 49 | NA | 2 | 2 | 2 | 0 | 2 |
| LIG E TYPE PLOT NO 50 | NA | 2 | 2 | 2 | 0 | 2 |
| MIG D TYPE PLOT NO 51 | NA | 2 | 2 | 2 | 0 | 2 |
| MIG D TYPE PLOT NO 52 | NA | 2 | 2 | 2 | 0 | 2 |
| LIG E TYPE PLOT NO 53 | NA | 2 | 2 | 2 | 0 | 2 |
| LIG E TYPE PLOT NO 54 | NA | 2 | 2 | 2 | 0 | 2 |
| LIG E TYPE PLOT NO 55 | NA | 2 | 2 | 2 | 0 | 2 |
| LIG E TYPE PLOT NO 56 | NA | 2 | 2 | 2 | 0 | 2 |
| LIG E TYPE PLOT NO 57 | NA | 2 | 2 | 2 | 0 | 2 |
| LIG E TYPE PLOT NO 58 | NA | 2 | 2 | 2 | 0 | 2 |
| MIG D TYPE PLOT NO 59 | NA | 2 | 2 | 2 | 0 | 2 |
| MIG D TYPE PLOT NO 60 | NA | 2 | 2 | 2 | 0 | 2 |
| LIG E TYPE PLOT NO 61 | NA | 2 | 2 | 2 | 0 | 2 |
| LIG E TYPE PLOT NO 62 | NA | 2 | 2 | 2 | 0 | 2 |
| LIG E TYPE PLOT NO 63 | NA | 2 | 2 | 2 | 0 | 2 |
| LIG E TYPE PLOT NO 64 | NA | 2 | 2 | 2 | 0 | 2 |
| LIG E TYPE PLOT NO 65 | NA | 2 | 2 | 2 | 0 | 2 |
| LIG E TYPE PLOT NO 66 | NA | 2 | 2 | 2 | 0 | 2 |
| MIG D TYPE PLOT NO 67 | NA | 2 | 2 | 2 | 0 | 2 |
| MIG D TYPE PLOT NO 68 | NA | 2 | 2 | 2 | 0 | 2 |
| LIG E TYPE PLOT NO 69 | NA | 2 | 2 | 2 | 0 | 2 |
| LIG E TYPE PLOT NO 70 | NA | 2 | 2 | 2 | 0 | 2 |
| LIG E TYPE PLOT NO 71 | NA | 2 | 2 | 2 | 0 | 2 |
| LIG E TYPE PLOT NO 72 | NA | 2 | 2 | 2 | 0 | 2 |
| LIG E TYPE PLOT NO 73 | NA | 2 | 2 | 2 | 0 | 2 |
| LIG E TYPE PLOT NO 74 | NA | 2 | 2 | 2 | 0 | 2 |
| MIG D TYPE PLOT NO 75 | NA | 2 | 2 | 2 | 0 | 2 |
| MIG D TYPE PLOT NO 76 | NA | 2 | 2 | 2 | 0 | 2 |
| LIG E TYPE PLOT NO 77 | NA | 2 | 2 | 2 | 0 | 2 |
| C TYPE PLOT NO 1 | NA | 2 | 2 | 2 | 0 | 2 |
| A1 TYPE PLOT NO 2 | NA | 2 | 2 | 2 | 0 | 2 |
| A1 TYPE PLOT NO 03 | NA | 2 | 2 | 2 | 0 | 2 |
| A1 TYPE PLOT NO 04 | NA | 2 | 2 | 2 | 0 | 2 |
| D TYPE PLOT NO 05 | NA | 2 | 2 | 2 | 0 | 2 |
| MIG D TYPE PLOT NO 06 | NA | 2 | 2 | 2 | 0 | 2 |
| MIG D TYPE PLOT NO 07 | NA | 2 | 2 | 2 | 0 | 2 |
| B1 TYPE PLOT NO 08 | NA | 2 | 2 | 2 | 0 | 2 |
| B1 TYPE PLOT NO 09 | NA | 2 | 2 | 2 | 0 | 2 |
| LIG E TYPE PLOT NO 15 | NA | 2 | 2 | 2 | 0 | 2 |
| LIG E TYPE PLOT NO 16 | NA | 2 | 2 | 2 | 0 | 2 |
| LIG E TYPE PLOT NO 17 | NA | 2 | 2 | 2 | 0 | 2 |
| LIG E TYPE PLOT NO 18 | NA | 2 | 2 | 2 | 0 | 2 |
| MIG D TYPE PLOT NO 19 | NA | 2 | 2 | 2 | 0 | 2 |
| MIG D TYPE PLOT NO 20 | NA | 2 | 2 | 2 | 0 | 2 |
| LIG E TYPE PLOT NO 21 | NA | 2 | 2 | 2 | 0 | 2 |
| LIG E TYPE PLOT NO 22 | NA | 2 | 2 | 2 | 0 | 2 |
| LIG E TYPE PLOT NO 23 | NA | 2 | 2 | 2 | 0 | 2 |
| LIG E TYPE PLOT NO 24 | NA | 2 | 2 | 2 | 0 | 2 |
| LIG E TYPE PLOT NO 25 | NA | 2 | 2 | 2 | 0 | 2 |
| LIG E TYPE PLOT NO 26 | NA | 2 | 2 | 2 | 0 | 2 |
| MIG D TYPE PLOT NO 27 | NA | 2 | 2 | 2 | 0 | 2 |
| MIG D TYPE PLOT NO 28 | NA | 2 | 2 | 2 | 0 | 2 |
| LIG E TYPE PLOT NO 29 | NA | 2 | 2 | 2 | 0 | 2 |
| LIG E TYPE PLOT NO 30 | NA | 2 | 2 | 2 | 0 | 2 |
| LIG E TYPE PLOT NO 31 | NA | 2 | 2 | 2 | 0 | 2 |
| LIG E TYPE PLOT NO 32 | NA | 2 | 2 | 2 | 0 | 2 |
| LIG E TYPE PLOT NO 33 | NA | 2 | 2 | 2 | 0 | 2 |
| LIG E TYPE PLOT NO 34 | NA | 2 | 2 | 1 | 0 | 1 |
| MIG D TYPE PLOT NO 35 | NA | 2 | 2 | 0 | 0 | 0 |
| MIG D TYPE PLOT NO 36 | NA | 2 | 2 | 0 | 0 | 0 |
| LIG E TYPE PLOT NO 37 | NA | 2 | 2 | 0 | 0 | 0 |
| LIG E TYPE PLOT NO 38 | NA | 2 | 2 | 0 | 0 | 0 |
| LIG E TYPE PLOT NO 39 | NA | 2 | 2 | 0 | 0 | 0 |
| LIG E TYPE PLOT NO 40 | NA | 2 | 2 | 0 | 0 | 0 |
| LIG E TYPE PLOT NO 41 | NA | 2 | 2 | 0 | 0 | 0 |
| LIG E TYPE PLOT NO 42 | NA | 2 | 2 | 0 | 0 | 0 |
| MIG D TYPE PLOT NO 43 | NA | 2 | 2 | 0 | 0 | 0 |
| MIG D TYPE PLOT NO 44 | NA | 2 | 2 | 0 | 0 | 0 |
| LIG E TYPE PLOT NO 45 | NA | 2 | 2 | 0 | 0 | 0 |
| LIG E TYPE PLOT NO 46 | NA | 2 | 2 | 0 | 0 | 0 |
| LIG E TYPE PLOT NO 47 | NA | 2 | 2 | 0 | 0 | 0 |
| LIG E TYPE PLOT NO 78 | NA | 2 | 2 | 0 | 0 | 0 |
| LIG E TYPE PLOT NO 79 | NA | 2 | 2 | 0 | 0 | 0 |
| LIG E TYPE PLOT NO 80 | NA | 2 | 2 | 0 | 0 | 0 |
| LIG E TYPE PLOT NO 81 | NA | 2 | 2 | 0 | 0 | 0 |
| LIG E TYPE PLOT NO 82 | NA | 2 | 2 | 0 | 0 | 0 |
| MIG D TYPE PLOT NO 83 | NA | 2 | 2 | 0 | 0 | 0 |
| MIG D TYPE PLOT NO 84 | NA | 2 | 2 | 0 | 0 | 0 |
| LIG E TYPE PLOT NO 85 | NA | 2 | 2 | 0 | 0 | 0 |
| LIG E TYPE PLOT NO 86 | NA | 2 | 2 | 0 | 0 | 0 |
| LIG E TYPE PLOT NO 87 | NA | 2 | 2 | 0 | 0 | 0 |
| LIG E TYPE PLOT NO 88 | NA | 2 | 2 | 0 | 0 | 0 |
| LIG E TYPE PLOT NO 89 | NA | 2 | 2 | 0 | 0 | 0 |
| LIG E TYPE PLOT NO 90 | NA | 2 | 2 | 0 | 0 | 0 |
| MIG D TYPE PLOT NO 91 | NA | 2 | 2 | 0 | 0 | 0 |
| MIG D TYPE PLOT NO 92 | NA | 2 | 2 | 0 | 0 | 0 |
| LIG E TYPE PLOT NO 93 | NA | 2 | 2 | 0 | 0 | 0 |
| LIG E TYPE PLOT NO 94 | NA | 2 | 2 | 0 | 0 | 0 |
| LIG E TYPE PLOT NO 95 | NA | 2 | 2 | 0 | 0 | 0 |
| LIG E TYPE PLOT NO 96 | NA | 2 | 2 | 0 | 0 | 0 |
| LIG E TYPE PLOT NO 97 | NA | 2 | 2 | 0 | 0 | 0 |
| LIG E TYPE PLOT NO 98 | NA | 2 | 2 | 0 | 0 | 0 |
| MIG D TYPE PLOT NO 99 | NA | 2 | 2 | 0 | 0 | 0 |
| C TYPE PLOT NO 10 | NA | 2 | 2 | 0 | 0 | 0 |
| A1 TYPE PLOT NO 11 | NA | 2 | 2 | 0 | 0 | 0 |
| A1 TYPE PLOT NO 100 | NA | 2 | 2 | 0 | 0 | 0 |
| C TYPE PLOT NO 101 | NA | 2 | 2 | 0 | 0 | 0 |
| A2 TYPE PLOT NO 102 | NA | 2 | 2 | 0 | 0 | 0 |
| A1 TYPE PLOT NO 103 | NA | 2 | 2 | 0 | 0 | 0 |
| B2 TYPE PLOT NO 104 | NA | 2 | 2 | 0 | 0 | 0 |
| B2 TYPE PLOT NO 105 | NA | 2 | 2 | 0 | 0 | 0 |
| B2 TYPE PLOT NO 106 | NA | 2 | 2 | 0 | 0 | 0 |
| B2 TYPE PLOT NO 107 | NA | 2 | 2 | 0 | 0 | 0 |
| B2 TYPE PLOT NO 108 | NA | 2 | 2 | 0 | 0 | 0 |
| B2 TYPE PLOT NO 109 | NA | 2 | 2 | 0 | 0 | 0 |
| B1 TYPE PLOT NO 110 | NA | 2 | 2 | 0 | 0 | 0 |
| B1 TYPE PLOT NO 111 | NA | 2 | 2 | 0 | 0 | 0 |
| A2 TYPE PLOT NO 112 | NA | 2 | 2 | 0 | 0 | 0 |
| B1 TYPE PLOT NO 113 | NA | 2 | 2 | 0 | 0 | 0 |
| C TYPE PLOT NO 114 | NA | 2 | 2 | 0 | 0 | 0 |
| A2 TYPE PLOT NO 115 | NA | 2 | 2 | 0 | 0 | 0 |
| A2 TYPE PLOT NO 116 | NA | 2 | 2 | 0 | 0 | 0 |
| A2 TYPE PLOT NO 117 | NA | 2 | 2 | 0 | 0 | 0 |
| MIG D TYPE PLOT NO 12 | NA | 2 | 2 | 0 | 0 | 0 |
| LIG E TYPE PLOT NO 13 | NA | 2 | 2 | 0 | 0 | 0 |
| LIG E TYPE PLOT NO 14 | NA | 2 | 2 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building20
As on 16 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection. The count above covers all 118 buildings; the table lists the first 20.
493 of 1287 construction stages are filed complete across 118 buildings. The stage furthest along is Slabs of Super Structure, at 98%.
LIG E TYPE PLOT NO 480%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
LIG E TYPE PLOT NO 4982%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
LIG E TYPE PLOT NO 500%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
MIG D TYPE PLOT NO 5182%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
MIG D TYPE PLOT NO 5282%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
LIG E TYPE PLOT NO 5382%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
LIG E TYPE PLOT NO 5482%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
LIG E TYPE PLOT NO 5582%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
LIG E TYPE PLOT NO 5682%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
LIG E TYPE PLOT NO 5782%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
LIG E TYPE PLOT NO 580%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
MIG D TYPE PLOT NO 5982%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
MIG D TYPE PLOT NO 6082%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
LIG E TYPE PLOT NO 610%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
LIG E TYPE PLOT NO 620%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
LIG E TYPE PLOT NO 6382%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
LIG E TYPE PLOT NO 640%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
LIG E TYPE PLOT NO 6568%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 98% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 94% |
| Sanitary Fittings within the flats / premises | 90% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 92% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 89% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 90% |
LIG E TYPE PLOT NO 660%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
MIG D TYPE PLOT NO 6782%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 16 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 100% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | Yes | 100% |
| Community Buildings | Yes | 100% |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | No | Not applicable |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | Yes | 100% |
| Open Parking | No | Not applicable |
Land and ownership
Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| C TYPE PLOT NO 1 | NA | Rs 63.39 lakh | - |
| C TYPE PLOT NO 10 | NA | Rs 63.39 lakh | - |
| C TYPE PLOT NO 101 | NA | Rs 63.39 lakh | - |
| C TYPE PLOT NO 114 | NA | Rs 63.39 lakh | - |
| B2 TYPE PLOT NO 104 | NA | Rs 39.10 lakh | - |
| B2 TYPE PLOT NO 105 | NA | Rs 39.10 lakh | - |
| B2 TYPE PLOT NO 106 | NA | Rs 39.10 lakh | - |
| B2 TYPE PLOT NO 107 | NA | Rs 39.10 lakh | - |
| B2 TYPE PLOT NO 108 | NA | Rs 39.10 lakh | - |
| B2 TYPE PLOT NO 109 | NA | Rs 39.10 lakh | - |
| B1 TYPE PLOT NO 08 | NA | Rs 38.04 lakh | - |
| B1 TYPE PLOT NO 09 | NA | Rs 38.04 lakh | - |
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | MUKESH MORE |
| Engineer | MR BHANGALE |
| Chartered Accountant | Badale Mahale and CO Chartered Accountants |
| Chartered Accountant | Sonawane Mor And Co Charterred Accountant |
| Partner | Role in project |
|---|---|
| VISHWA REAL ESTATE CO | - |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterWorst market scenario and sluggish sales due to many factors ...Also there is a corona since 2020 and lockdown .
Reason as filed by the promoterAs per attachment
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 26 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 28 Jul 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 18 Jul 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 18 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 11 Aug 2021
Documents filed108
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 108 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Architect certificate from 01st Jul25 to 30th Sep25_compres.pdf | 16 Jun 2026 |
| Withdrawal Update Form 1File: Architect form 01st Oct25 to 31st dec25.pdf | 16 Jun 2026 |
| Withdrawal Update Form 1File: Architect form from 01st Jan 26 to 31st Mar26.pdf | 16 Jun 2026 |
| Withdrawal Update Form 2File: Form 2 June 24.pdf | 16 Jun 2026 |
| Withdrawal Update Form 2File: form 2 - Engineer form 01st Oct25 to 31st Dec25.pdf | 16 Jun 2026 |
| Withdrawal Update Form 2File: Form 2 - Engineer Certificate from 01st Jan26 to 31st Mar26.pdf | 16 Jun 2026 |
| Withdrawal Update Form 3File: Form 3 01st Jul25 to 30th Sep25.pdf | 16 Jun 2026 |
| Withdrawal Update Form 3File: Form 3 01st Oct25 to 31st Dec25.pdf | 16 Jun 2026 |
| Withdrawal Update Form 3File: Form 3 - From 01st Jan26 to 31st Mar26.pdf | 16 Jun 2026 |
| Form 5 (FY 2024-2025)File: Form 5 01st Apr 24 to 31st Mar25.pdf | 3 Apr 2026 |
| Form 1File: Architect form 1st Apr25 to 30th Jun25_compressed.pdf | 21 Jul 2025 |
| Form 2File: Form 2 Engineer form 01st Apr25 to 30th Jun25.pdf | 21 Jul 2025 |
| Form 3File: Form 3 01st Apr25 to 30th Jun25.pdf | 21 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of Booked and sold Inventory 01st Apr25 to 30th Jun 2025_compressed.pdf | 21 Jul 2025 |
| Form 1File: Architect form for 1st Jan25 to 31st Mar25_compressed.pdf | 4 Jul 2025 |
| Form 2File: Form 2.pdf | 4 Jul 2025 |
| Form 3File: Form 3.pdf | 4 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of sold & Booked Inventory_compressed.pdf | 4 Jul 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect form for 1st Jan25 to 31st Mar25_compressed.pdf | 24 Apr 2025 |
| Certificates of CA (Form 3)File: Form 3.pdf | 24 Apr 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf | 24 Apr 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1_compressed.pdf | 19 Jan 2025 |
| Certificates of CA (Form 3)File: Form 3.pdf | 19 Jan 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FOrm 2.pdf | 19 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Sold Booked Inventory till 31st Dec24_compressed.pdf | 19 Jan 2025 |
| Certificates of CA (Form 3)File: Form 3 Jul24 to Sep24.pdf | 26 Nov 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer form.pdf | 26 Nov 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure of sold booked - 300623.pdf | 31 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure of sold booked - 300923.pdf | 31 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure of sold booked - 311223.pdf | 31 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure of sold booked - 310324.pdf | 31 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure of sold booked - 300624.pdf | 31 Jul 2024 |
| Declaration in FORM BFile: Form B.pdf | 30 Jul 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate - March 2018.pdf | 30 Jul 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate - March 2019.pdf | 30 Jul 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate - March 2020.pdf | 30 Jul 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate - March 2021.pdf | 30 Jul 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate - March 2022.pdf | 30 Jul 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate - March 2023.pdf | 30 Jul 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate - March 2024.pdf | 30 Jul 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Mar 22.pdf | 30 Jul 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Mar 23.pdf | 30 Jul 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 June 23.pdf | 30 Jul 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Sep 23.pdf | 30 Jul 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Dec 23.pdf | 30 Jul 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - Mar 24.pdf | 30 Jul 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 June 24.pdf | 30 Jul 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A 2022.pdf | 30 Jul 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A 2023.pdf | 30 Jul 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A 2024.pdf | 30 Jul 2024 |
| CERSAI detailsFile: Declaration for CERSAI.pdf | 30 Jul 2024 |
| Certificates of CA (Form 3)File: Form 3 Jun 23.pdf | 30 Jul 2024 |
| Certificates of CA (Form 3)File: Form 3 Sep 23.pdf | 30 Jul 2024 |
| Certificates of CA (Form 3)File: Form 3 March 22.pdf | 30 Jul 2024 |
| Certificates of CA (Form 3)File: Form 3 March 23.pdf | 30 Jul 2024 |
| Certificates of CA (Form 3)File: Form 3 Jun 23.pdf | 30 Jul 2024 |
| Certificates of CA (Form 3)File: Form 3 Sep 23.pdf | 30 Jul 2024 |
| Certificates of CA (Form 3)File: Form 3 Dec 23.pdf | 30 Jul 2024 |
| Certificates of CA (Form 3)File: Form 3 March 24.pdf | 30 Jul 2024 |
| Certificates of CA (Form 3)File: Form 3 Jun 24.pdf | 30 Jul 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Declaration of other interest.pdf | 30 Jul 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 21-22.pdf | 30 Jul 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FOrm 5 22-23.pdf | 30 Jul 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 23-24.pdf | 30 Jul 2024 |
| Declaration about all RERA Designated Bank Accounts (Format A)File: Bank Declaration.pdf | 30 Jul 2024 |
| Declaration about Commencement CertificateFile: Revised Declaration about commencement certificate stamped.pdf | 9 Sep 2021 |
| Declaration about Commencement CertificateFile: Declaration of CC under circular32 on letter head.pdf | 7 Sep 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Quality assurance certificate1_compressed.pdf | 12 Aug 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Quality assurance certificate_compressed.pdf | 12 Aug 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Quality assurance certificate1_compressed.pdf | 12 Aug 2021 |
| Details of Restarting of Construction work post lockdownFile: Details of Restarting of Construction work post lockdown.pdf | 12 Aug 2021 |
| OtherFile: Declaration of CC under circular32 on letter head.pdf | 12 Aug 2021 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Architect form 4_compressed.pdf | 11 Aug 2021 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Architect form 4 additional_compressed.pdf | 11 Aug 2021 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Architect form 4 additionals_compressed.pdf | 11 Aug 2021 |
| Status of Formation of Legal Entity (Society/Co Op etc.)File: Status of formation of Legal Entity Society Co Op etc.pdf | 6 Aug 2021 |
| Status of ConveyanceFile: Status of conveyeance.pdf | 6 Aug 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: RERA Annual Report AY 2020 To 2021.pdf | 4 Aug 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: RERA Annual Report AY 2021 To 2022.pdf | 4 Aug 2021 |
| Declaration about Commencement CertificateFile: NA order small file size.pdf | 20 Jul 2021 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Raigarh
Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.
Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 108 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep NATURE PARADISE on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Alibagh5,900+ in Raigarh
Filed coordinates, straight-line distance. 104 registered projects within 2 km.
Bellezza Woods
DOTOM BUILD SQUARE
Winds of Calm
Eiffel Lifespaces Pvt Ltd
PURANIK CITY SECTOR 2
Puranik Builders Limited
Foothills of Matheran P - 2
HOABL Impactum Land Private Limited
FLORENCE TOWN
BRIGHT DEVELOPERS
The Destination
DOVE BUILDMART PRIVATE LIMITED
See every Raigarh project, with the district possession charts
Builder: VISHWA REAL ESTATE CO
VISHWA REAL ESTATE CO has 1 registration on MahaRERA, including NATURE PARADISE. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Raigarh district page.
Frequently asked questions
What are my rights if NATURE PARADISE is delayed beyond 31 Dec 2029?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of NATURE PARADISE?
The registered promoter entity is VISHWA REAL ESTATE CO, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in NATURE PARADISE?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for NATURE PARADISE?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at NATURE PARADISE?
The professionals named in the filing: Architect: MUKESH MORE; Engineer: MR BHANGALE; Chartered Accountant: Badale Mahale and CO Chartered Accountants; Chartered Accountant: Sonawane Mor And Co Charterred Accountant. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in NATURE PARADISE?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback