Home / Browse projects / Udupi, Karnataka / MOOKAMBIKA SUKHATVA
MOOKAMBIKA SUKHATVA
RG-KA-50006 · RERA PRM/KA/RERA/1273/487/PR/200908/003589 · Last updated on RERA Karnataka portal: 27 Aug 2020
Source: official RERA Karnataka filing
Red flags
- No red flags in this filing
Clear
- No complaints on record
- Completion date never moved
- Separate project account declared
Saved.
MOOKAMBIKA SUKHATVA is a Residential/Group Housing project by KODACHADRI ASSOCIATES in Udupi, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1273/487/PR/200908/003589 on 8 Sep 2020. Possession is promised by 31 Dec 2023. 0 of the 182 units on this registration are recorded sold or booked, and 0 of 18 construction stages are filed complete.
At a glance
Project
- NameMOOKAMBIKA SUKHATVA
- TypeResidential/Group Housing
- Location
- Byndoor
- Udupi
- PincodeNot stated
- MapView location on Google Maps (as filed on RERA)
- RERA no.PRM/KA/RERA/1273/487/PR/200908/003589
- ReraGenie IDRG-KA-50006
Builder
- NameKODACHADRI ASSOCIATES
- Entity typePartnership Firm
- Authorized SignatoryK VENKATESH KINI
- OthersNAYANA V KINI, K VENKATESH KINI
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on8 Sep 2020
- Promised completion31 Dec 2023
- Revised completionNone
- Buildings1 building record
- Documents filed73 files
Current status
Figures as on 27 Aug 2020, this project's latest RERA Karnataka filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| MOOKAMBIKA SUKHATVA | - | - | - | - | - | 182 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
As on 27 Aug 2020, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
0 of 18 construction stages are filed complete. The stage furthest along is Earth work and other leveling preparation work, at 0%.
Building: 0% average across the applicable activities
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | - |
| Foundation footing work | - |
| Retaining wall (All types) | - |
| Plinth level Beam | - |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | - |
| RCC or MS Framed structure | - |
| Masonry construction: Bricks, Concrete blocks etc | - |
| Plastering inside , outside & Ceiling | - |
| Joinery: Doors, Windows, Ventilators etc | - |
| Basic work of Water supply, Sanitary and Electrification | - |
| Dadoing, Skirting, Flooring, Tiles work (All types) | - |
| Railing and Grill fixing | - |
| Electrification, Water supply and Sanitary Finishing | - |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | Not applicable |
| Fire prevention and fire fighting fitting and fixture with network | - |
| Weather Proof work(tile,concrete) | - |
| Painting | - |
| Elevation work | - |
| Internal and External work including landscapes as per santioned drawings | - |
Progress on shared amenities41
As on 27 Aug 2020, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | - |
| Internal Roads & Footpaths | No | Not applicable |
| Sewage and Drainage System | No | Not applicable |
| Parks & Tree planting | No | Not applicable |
| Street Lighting | Yes | - |
| Provision for community buildings and for treatment and disposal of sewage and sullage water | No | Not applicable |
| Solid waste management and disposal | Yes | - |
| Water conservation | No | Not applicable |
| Energy management | Yes | - |
| Fire protection and fire safety requirements | No | Not applicable |
| Education/Health/Other public amenities | Yes | - |
| Electricity supply transformer and substation | Yes | - |
| Emergency Evacuation services | No | Not applicable |
| Storm water drains | No | Not applicable |
| Use of renewable energy | No | Not applicable |
| Water conservation/rain water harvesting/recharge of ground water | Yes | - |
| Electricity | Yes | - |
| Smart Home Automation | Yes | - |
| CCTV Surveillance | Yes | - |
| Club House | No | Not applicable |
| Community Hall | Yes | - |
| Outdoor Sports facility | No | Not applicable |
| Indoor Sports facility | No | Not applicable |
| Swimming Pool | Yes | - |
| Gym | Yes | - |
| Parks | No | Not applicable |
| Power Backup | Yes | - |
| Gas | No | Not applicable |
| Water and Sanitation | No | Not applicable |
| Air Conditioning And incerntion | Yes | - |
| Staircases | Yes | - |
| Lifts | Yes | - |
| Staircases and Lift lobbies, corridor,lobbies, corridor | Yes | - |
| Fire escapes | Yes | - |
| Common entrance and exit for the building / common portico/foyer/verandah | Yes | - |
| Basement | Yes | - |
| Terrace | Yes | - |
| Outer Wall | Yes | - |
| Open parking areas and common storage spaces | Yes | - |
| Provision for lodging of management staff and security staff | Yes | - |
| Water conservation and renewable energy | Yes | - |
Land and ownership1
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| K VENKATESH KINI | - | - |
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners2
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | MAHIMA SRINIVAS PAI(B.ARCH) |
| Engineer | MR. VASUDEVAN T S |
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed73
As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1273/487/PR/200908/003589 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| BANK ACCOUNTFile: bank account.pdf | 27 Aug 2020 |
| PAYMENT CHALLANFile: PAYMENT CHALLAN.pdf | 27 Aug 2020 |
| ITR 2019File: AUDIT REPORT 2019.pdf | 27 Aug 2020 |
| bank pass bookFile: BANK PASS BOOK.jpg | 4 Jul 2020 |
| ITR 2019-20File: AY 2019-20.pdf | 4 Jul 2020 |
| balance sheet 2019-20File: BALANCE SHEET 2019.jpg | 4 Jul 2020 |
| Audit report 2019-20File: AUDIT REPORT 2019.jpg | 4 Jul 2020 |
| cash Flow 2019-20File: CASH FLOW 2019.jpg | 4 Jul 2020 |
| profit and Loss account 2019-20File: PROFIT AND LOSS ACCOUNT 2019.jpg | 4 Jul 2020 |
| Brochure and SpecificationFile: Brochure of Current.pdf | 4 Jul 2020 |
| Fire Force Dept NOCFile: FIRE CERTIFICATE.pdf | 4 Jul 2020 |
| water Supply NOCFile: WATER SUPPLY NOC.pdf | 4 Jul 2020 |
| CertificateFile: FIRM REGISRATION CERTIFICATE.jpg | - |
| COMMENCEMENT CERTIFICATE | - |
| GF Plan | - |
| APPROVAL SANCATION PLAN-HIGH | - |
| PROFORMA OF - DEED OF SALE | - |
| PROFORMA OF AGREEMENT FOR SALE | - |
| SALE DEED | - |
| Section | - |
| SINGLE LAYOUT PLAN-merged | - |
| Allotment Letter | - |
| Brochure of Current | - |
| SPECIFICATION | - |
| EC 2005 TO 2020_compressed | - |
| Notarized Affidavit for 3(1) Voliation 1 | - |
| FIRE CERTIFICATE | - |
| E KATHA | - |
| MOTHER DEED | - |
| REGISTARED PARTNER SHIP DEED_compressed_compressed | - |
| CONVERSTION ORDER_compressed | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| FIRE CERTIFICATE-page-001 | - |
| Unnamed document | - |
| MESCOM NOC | - |
| WATER SUPPLY NOC | - |
| KPCB_compressed (1) | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| REGISTARED PARTNER SHIP DEED | - |
| Site Plan | - |
| FIRE CERTIFICATE | - |
| CONVERSTION ORDER_compressed | - |
| Unnamed document | - |
| Balance Sheet 2018 - 2019File: BALANCE SHEET 2019.jpg | - |
| Balance Sheet 2017 - 2018File: BALANCE SHEET 2018.jpg | - |
| Balance Sheet 2016 - 2017File: BALANCE SHEET 2017.jpg | - |
| Audited Profit and Loss Statement 2018 - 2019File: PROFIT AND LOSS ACCOUNT 2019.jpg | - |
| Audited Profit and Loss Statement 2017 - 2018File: PROFIT AND LOSS ACCOUNT 2018.jpg | - |
| Audited Profit and Loss Statement 2016 - 2017File: PROFIT AND LOSS ACCOUNT 2017.jpg | - |
| Director's Report 2018 - 2019File: DIRECTOR REPORT 2019.jpg | - |
| Director's Report 2017 - 2018File: DIRECTOR REPORT 2018.jpg | - |
| Cash Flow Statement 2018 - 2019File: CASH FLOW 2019.jpg | - |
| Cash Flow Statement 2017 - 2018File: BALANCE SHEET 2018.jpg | - |
| Auditor's Report 2018 - 2019File: AUDIT REPORT 2019.jpg | - |
| Auditor's Report 2017 - 2018File: AUDIT REPORT 2018.jpg | - |
| Income Tax Return Acknowledgement 2018 - 2019File: AY 2019-20.pdf | - |
| Income Tax Return Acknowledgement 2017 - 2018File: AY 2018-19.pdf | - |
| Income Tax Return Acknowledgement 2016 - 2017File: AY 2017-18.pdf | - |
| FORM B | - |
| Prospectus/BrochureFile: Brochure of Current.pdf | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Udupi
Computed across the 260+ Udupi projects on ReraGenie, from their own filings.
Keep MOOKAMBIKA SUKHATVA on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Udupi260+ in Udupi
GRASSLANDS - LAKESIDE
GRAZLANZ PROPERTIES LLP
MANDAVI DOWNTOWN
MANDAVI CONSTRUCTIONS
KIRTHI PALMVILLE PHASE II
KIRTHI CONSTRUCTION
RAINTREE
VINIT S AMIN
MANDAVI ROYAL GARDEN
MANDAVI INFRASTRUCTURES
Mandavi Casa Grande
J J Builders and Developers
See every Udupi project, with the district possession charts
Builder: KODACHADRI ASSOCIATES
KODACHADRI ASSOCIATES has 1 registration on RERA Karnataka, including MOOKAMBIKA SUKHATVA. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Udupi district page.
Frequently asked questions
What are my rights if MOOKAMBIKA SUKHATVA is delayed beyond 31 Dec 2023?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of MOOKAMBIKA SUKHATVA?
The registered promoter entity is KODACHADRI ASSOCIATES, a partnership firm as per the filing. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in MOOKAMBIKA SUKHATVA?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at MOOKAMBIKA SUKHATVA?
The professionals named in the filing: Architect: MAHIMA SRINIVAS PAI(B.ARCH); Engineer: MR. VASUDEVAN T S. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in MOOKAMBIKA SUKHATVA?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.
Report an error Share feedback