Home / Browse projects / Mumbai Suburban, Maharashtra / MONIZ SHRADDHA HEIGHTS
MONIZ SHRADDHA HEIGHTS
By K K KRISHNAN CONSTRUCTION COMPANY PVT LTD
RG-MH-24229 · RERA P51800009326 · Last updated on MahaRERA portal: 8 May 2025
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 10 months past the filed date
- 4 complaints at MahaRERA
- Completion date moved by 33 months
- 2 extensions taken
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
- All 1 earlier projects delivered on promise
5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
MONIZ SHRADDHA HEIGHTS is a Residential / Group Housing project by K K KRISHNAN CONSTRUCTION COMPANY PVT LTD in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800009326 on 22 Aug 2017. Possession was promised by 31 Dec 2025 and is now 10 months past that date. The completion date has moved by 33 months from the original filing. 4 complaints are on record with the regulator.
At a glance
Project
- NameMONIZ SHRADDHA HEIGHTS
- TypeResidential / Group Housing
- Location
- VAKOLA
- SANTACRUZ
- Andheri
- Mumbai Suburban
- 400055
- Pincode400055
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51800009326
- ReraGenie IDRG-MH-24229
Builder
- NameK K KRISHNAN CONSTRUCTION COMPANY PVT LTD
- Entity typeCompany
- CINU70101MH1984PTC031742
- GSTIN27AAACK2885L2Z3
- CIN and GSTIN are from this promoter's other MahaRERA registrations. This project's own filing does not repeat them.
- ChairpersonsSHEEJA SURESH KRISHNAN, SULOCHANA KRISHNAN
- Managing DirectorSURESH KRISHNAN
- Other registrations3 more →
- No longer live4 lapsed, de-registered or revoked
- Declared earlier projects1 →
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on22 Aug 2017
- Promised completion31 Dec 2025
- Revised completionRevised to 31 Dec 2025 (originally 30 Mar 2023)
- Buildings2 building records
- Documents filed62 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| MONIZ SHRADDHA HEIGHTS WING-A | NA | 13 | 0 | 0 | 0 | 0 |
| MONIZ SHRADDHA HEIGHTS WING-B | NA | 12 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building2
As on 8 May 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
14 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Slabs of Super Structure, at 81%.
MONIZ SHRADDHA HEIGHTS WING-A59%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 81% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 32% |
| Sanitary Fittings within the flats / premises | 35% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 51% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 45% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 2% |
MONIZ SHRADDHA HEIGHTS WING-B91%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 8 May 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 15% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 90% |
| Storm Water Drains | Yes | 90% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 33% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | Yes | 0% |
Parking filed11
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Open Space | Total |
|---|---|---|---|
| MONIZ SHRADDHA HEIGHTS WING-A | 7 | 1 | 8 |
| MONIZ SHRADDHA HEIGHTS WING-B | 1 | 2 | 3 |
Land and ownership2
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| Ms Shraddha Enterprises | Andheri | Mumbai Suburban |
| Shraddha Enterprises | Andheri | Mumbai Suburban |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners6
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | MS SURESH KRISHNAN & ASSOCIATES |
| Engineer | BHUSHAN N SANGHAVI |
| Engineer | Sandeep Sakpal |
| Engineer | Destech Designs |
| Chartered Accountant | Neeta Chaudhry & Co |
| Chartered Accountant | G C Patel & Co |
| Partner | Role in project |
|---|---|
| K K KRISHNAN CONSTRUCTION COMPANY PVT LTD | - |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterIt is a redevelopment project. Due to pandemic, the financial condition to conduct the construction and fulfill the rentals to tenants and other expenses was not suitable, hence we were negotiating with several financial institutions and inventors. From which, we have introduced an investor as a co-promoter and resumed the construction activity in full threshold recently. We have received consent from existing allottees and seeking extension to complete the construction with complete willingness. Kindly grant us the extension
Reason as filed by the promoterThe project faced delays due to the COVID-19 recession, leading to a joint venture with Shraddha Enterprises. Construction resumed in 2021, completing Moniz Shraddha Heights Wing B up to the 7th floor. Challenges, including the removal of an existing structure, were managed, and mechanical parking was added. Work on Wing A progressed to the 3rd floor, and further approvals were secured in February 2025 to continue construction up to the 4th floor, which is currently ongoing. Our existing buyers are aware of the situation and are supporting us to get the further approvals. Hence, they provided
Complaints filed with MahaRERA4
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000194978 | Mrs. Leona Martin | KK Krishnan | 21/11/2020 |
| CC006000000199333 | Vivian Menezes | Mr Suresh Krishnan | 07/12/2021 |
| CC12401170 | Mrs Mirgaelina Fernandes | K K KRISHNAN CONSTRUCTION COMPANY PVT LTD | 18/12/2024 |
| CC12600338 | Jimmy George | K K KRISHNAN CONSTRUCTION COMPANY PVT LTD | 17/01/2026 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 27 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 16 Jun 2018 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 27 Jul 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 8 May 2025Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed62
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Declaration in FORM BFile: FORM B_KKK.pdf | 8 May 2025 |
| Declaration in FORM BFile: FORM B_SHRADDHA ENT.pdf | 8 May 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 OF MSH.pdf | 8 May 2025 |
| Certificates of CA (Form 3)File: Form 3_March 2024_C.pdf | 8 May 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf | 8 May 2025 |
| Commencement Certificates / NA Order for plotted developmentFile: Part Occupation Certificate of Moniz Shraddha Heights.pdf | 8 May 2025 |
| OtherFile: Part Occupation Certificate of Moniz Shraddha Heights.pdf | 8 May 2025 |
| Disclosure of sold/ booked inventoryFile: Sold n unsold inventory of MSH MARCH 24.pdf | 8 May 2025 |
| Disclosure of sold/ booked inventoryFile: SOLD N UNSOLD inventory of MSH JUNE 24.pdf | 8 May 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A_2023_Corrected.pdf | 8 May 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5_2022-23_Corrected.pdf | 8 May 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A_2024_Corrected.pdf | 8 May 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5_2023-24_Corrected.pdf | 8 May 2025 |
| Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: Format B from Canara bank for MSH.pdf | 8 May 2025 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of interest in other projects _ KK Krishnan.pdf | 1 Apr 2023 |
| Certificates of CA (Form 3)File: Form-3_Moniz Complex_Shraddha_17 March 2023 BY G C PATEL.pdf | 31 Mar 2023 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: 1 Disclosure of Interest in Other Real Estate Organizations.pdf | 31 Mar 2023 |
| Disclosure of sold/ booked inventoryFile: Disclosure of sold flats in Moniz Complex 28-3-23.pdf | 28 Mar 2023 |
| Certificates of CA (Form 3)File: Form 3 Moniz Complex 17 March 2023 BY G C PATEL.pdf | 28 Mar 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5 2018-2019 of Moniz Complex.pdf | 28 Mar 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 2019-2020 of Moniz Complex.pdf | 28 Mar 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 2020-2021 of Moniz Complex.pdf | 28 Mar 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 2021-2022 of Moniz Complex.pdf | 28 Mar 2023 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Format A Declaration of bank ac2.pdf | 23 Mar 2023 |
| Details of encumbrances concerned to FinanceFile: Encumbrances_Legal_Moniz.pdf | 5 Mar 2023 |
| Details of encumbrances concerned to LegalFile: Encumbrances_Legal_Moniz.pdf | 5 Mar 2023 |
| Declaration about Commencement CertificateFile: Form D Declaration about CC OF Moniz Complex.pdf | 5 Mar 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form-1 Architect Certificate of percentage completion - Moniz Complex.pdf | 5 Mar 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form-2 Engineer Certificate cost incurred- Moniz Tower-min.pdf | 5 Mar 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form-2A Quality Certificate for Moniz Complex 2020-min.pdf | 5 Mar 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form-2A Quality Certificate for Moniz Complex 2021-min.pdf | 5 Mar 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form-2A Quality certificate for Moniz 2022-min.pdf | 5 Mar 2023 |
| CERSAI detailsFile: CERSAI_Search_Report Moniz Complex.pdf | 5 Mar 2023 |
| Proforma of Agreement for saleFile: Proforma AFS.pdf | 5 Mar 2023 |
| Proforma of Allotment letterFile: Proforma of allotment letter-min.pdf | 5 Mar 2023 |
| Deviation Report with respect to Allotment letterFile: Deviation Report with Allotment letter in respect of Moniz Complex.pdf | 5 Mar 2023 |
| Deviation Report with respect to model copy of AgreementFile: Deviation Report with Agreemetn for sale Moniz Complex.pdf | 5 Mar 2023 |
| Details of Restarting of Construction work post lockdownFile: moniz final plan amended bmc signed 19082021 (1).pdf | 4 Sep 2021 |
| Details of Restarting of Construction work post lockdownFile: 0702092063310_signed (1).pdf | 4 Sep 2021 |
| Details of Restarting of Construction work post lockdownFile: ammend plan approval letter.pdf | 4 Sep 2021 |
| OtherFile: MCHI PDF RESIZER.pdf | 12 Nov 2019 |
| OtherFile: MCHI PDF RESIZER.pdf | 11 Nov 2019 |
| Layout approvalFile: MONIZ MCGM APPROVAL SIGNED DOC.pdf | 16 Jun 2018 |
| Copy of Layout Approval (in case of layout)File: MONIZ MCGM APPROVAL SIGNED DOC.pdf | 16 Jun 2018 |
| Certificates of CA (Form 5)File: Moniz Tower - RERA Updation (28-11-17).pdf | 29 Nov 2017 |
| Certificates of CA (Form 3)File: C A certificatem.pdf | 28 Jul 2017 |
| Layout approvalFile: MOniz Layout plan with letter 1 mb PDF.pdf | 27 Jul 2017 |
| Building plan approvalFile: IOD.pdf | 27 Jul 2017 |
| Layout approvalFile: Moniz Fire layout.pdf | 27 Jul 2017 |
| PAN CardFile: pan card.pdf | 27 Jul 2017 |
| Copy of the legal title reportFile: Title certificate.pdf | 27 Jul 2017 |
| Details of encumbrancesFile: Non encumbrance Letter Moniz PDF.pdf | 27 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: MOniz Layout plan with letter 1 mb PDF.pdf | 27 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: Moniz Fire layout.pdf | 27 Jul 2017 |
| Building Plan Approval (IOD)File: IOD.pdf | 27 Jul 2017 |
| Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate Moniz and Aniketh.pdf | 27 Jul 2017 |
| Declaration in FORM BFile: Form B.pdf | 27 Jul 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect certificate Moniz.pdf | 27 Jul 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Moniz Eng.pdf | 27 Jul 2017 |
| Proforma of Allotment letterFile: Allottment letter and Agreement for sale.pdf | 27 Jul 2017 |
| OtherFile: Fire Approval.pdf | 27 Jul 2017 |
| OtherFile: MCGM Approval Moniz.pdf | 27 Jul 2017 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| Aksh Darshan | Mumbai 400098 | 55 | Completed | Jun 2017 | Jun 2017 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai Suburban
Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 5 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 3 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 62 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep MONIZ SHRADDHA HEIGHTS on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near SANTACRUZ6,700+ in Mumbai Suburban
Filed coordinates, straight-line distance. 341 registered projects within 2 km.
ATMIYA CENTRIA
UPTURN PROPERTIES LLP
NINE ARCS
ARIHANT CONSTRUCTION CO
Trinity Towers
Jet Speed Realtors Private Limited
Bluemoon Annexe
MUDASSAR BUILDERS & DEVELOPERS
W55
DVASUYASH CONSTRUCTION 1 LLP
Sumit Bhakti
Sumit Pragati Ventures LLP
See every Mumbai Suburban project, with the district possession charts
Builder: K K KRISHNAN CONSTRUCTION COMPANY PVT LTD
K K KRISHNAN CONSTRUCTION COMPANY PVT LTD has 4 registrations on MahaRERA, including VINAYAK SHRADDHA TOWER and MONIZ SHRADDHA HEIGHTS. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Mumbai Suburban district page.
Frequently asked questions
What does it mean that MONIZ SHRADDHA HEIGHTS shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if MONIZ SHRADDHA HEIGHTS is delayed beyond 31 Dec 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of MONIZ SHRADDHA HEIGHTS?
The registered promoter entity is K K KRISHNAN CONSTRUCTION COMPANY PVT LTD, a company as per the filing. Its CIN U70101MH1984PTC031742 and GSTIN 27AAACK2885L2Z3 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in MONIZ SHRADDHA HEIGHTS?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against MONIZ SHRADDHA HEIGHTS?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for MONIZ SHRADDHA HEIGHTS?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at MONIZ SHRADDHA HEIGHTS?
The professionals named in the filing: Architect: MS SURESH KRISHNAN & ASSOCIATES; Engineer: BHUSHAN N SANGHAVI; Engineer: Sandeep Sakpal; Engineer: Destech Designs; Chartered Accountant: Neeta Chaudhry & Co; Chartered Accountant: G C Patel & Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in MONIZ SHRADDHA HEIGHTS?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback