Home / Browse projects / Mumbai Suburban, Maharashtra / MIRABILIS

Registration lapsed No litigation declared Residential / Group Housing project

MIRABILIS

By SKYLINK HOSPITALITY LLP

RG-MH-02544 · RERA P51800000370 · Last updated on MahaRERA portal: 14 Mar 2023

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 34 months past the filed date
  • 48 complaints at MahaRERA
  • Completion date moved by 30 months
  • 1 extension taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Dec 2023Possession promised34 months past this date
1 of 11Construction stages donefurthest along: Basement (if any), 70%
48Complaints at MahaRERAon this registration
Jump to the 103 documents Report an error

MIRABILIS is a Residential / Group Housing project by SKYLINK HOSPITALITY LLP in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800000370 on 15 Jul 2017. Possession was promised by 30 Dec 2023 and is now 34 months past that date. The completion date has moved by 30 months from the original filing. 48 complaints are on record with the regulator.

At a glance

Project

  • NameMIRABILIS
  • TypeResidential / Group Housing
  • Location
    • NA
    • Greater Mumbai (M Corp.) (Part) (802794)
    • Mumbai
    • Mumbai Suburban
    • 400055
  • Pincode400055
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800000370
  • ReraGenie IDRG-MH-02544

Builder

  • NameSKYLINK HOSPITALITY LLP
  • Entity typePartnership
  • PartnerKUMAR KANAYALAL MORDANI

Key dates

34 months past promisethis monthRegisteredJul 2017First promiseJun 2021Revised toDec 2023

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on15 Jul 2017
  • Promised completion30 Dec 2023
  • Revised completionRevised to 30 Dec 2023 (originally 30 Jun 2021)
  • Buildings1 building record
  • Documents filed103 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
MIRABILISNA150000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 14 Mar 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

1 of 11 construction stages are filed complete. The stage furthest along is Basement (if any), at 70%.

MIRABILIS: 22% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)70%
Podiums (if any)0%
Plinth70%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities25

As on 14 Mar 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable
Indoor GamesNoNot applicable
GymasiumNoNot applicable
Entrance Lobby& Lift lobbyNoNot applicable
Business CenterNoNot applicable
Virtual GamesNoNot applicable
Swimming Pool and JacuzziNoNot applicable
Steam Room & changing roomNoNot applicable
Society roomNoNot applicable
Pool changing rooms with shower areaNoNot applicable
Kids Play area, Activity areaNoNot applicable

Parking filed140

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots140
Closed/Covered140

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,874 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI7567.39
Proposed, not sanctioned5,496 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchCFS 1 - FORT, MUMBAI 400001

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectM/s Dot Architects Pvt Ltd as L.S. / Architect
EngineerGlobal Engineering Services
PartnerRole in project
SKYLINK HOSPITALITY LLP-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800009117Jun 2021 → Jun 2023

Reason as filed by the promoterOwing to disputes and litigation with the members of the Samrat Ashok SRA CHSL, which is the slum society that has appointed us to implement the said Project; plans had to be revised and amended, the project completion timelines, as a result, are also required to revise. We have already obtained 31 of allottees to revise the completion date to December, 2022 through emails (not including extension of six months given by RERA Authority due to Pandemic) and 8 consents through registered agreement for sale to revise the completion date to June, 2023 aggregating to 39 total number of consents. In

Litigation declared9

CaseCourtStatus
64 to 72/2015Court of small CausesPleadings are being completed
11/2017Court of small CausesCondonation of delay applications are pending for hearing
12/2017Court of Small CausesCondonation of delay applications are pending for hearing
13/2017Court of small causesCondonation of delay applications are pending for hearing
23/2016Slum Tribunal BandraPending admission and hearing
28/2010Slum Tribunal BandraReserved for orders
25/2016Slum Tribunal BandraReserved for orders
38/2013Slum Tribunal BandraPending admission and hearing
1003/2016High Court BombayDismissed

Complaints filed with MahaRERA48

Case no.ComplainantRespondentFiled
CC006000000000640Samarat Ashok SRA Co-operative Housing SocietySkylink Developer16/09/2017
CC006000000199043Reshma BhatiaSkylink Hospitality LLP16/11/2021
CC006000000210442skylink hospitality LLPmr.dhanraj mani and mrs.lakshmipriya dhanraj28/03/2022
CC006000000197109DR ARIVAZHAGAN VELUSAMY AND MRS. THENMOZHI KULANDAISAMYSKYLINK HOSPITALITY LLP10/06/2021
CC006000000197192Mr. Dhanaraj Mani & Mrs. Lakshmipriya DhanrajSKYLINK HOSPITALITY LLP12/06/2021
CC006000000197216Dr Ramanathan Elayaperumal and Mrs. Rajalakshmi VairavanSkyLink Hospitality LLP19/06/2021
CC006000000197250Dr Krishna Dass Lakshmanan Nair Siva DassSKYLINK HOSPITALITY LLP16/06/2021
CC006000000197335Subhabrata GhoshSkylink Hospitality LLP10/07/2021
CC006000000197558Arcot Arumugam MaheshwarSkylink Hospitality LLP15/07/2021
CC006000000197561Arcot Arumugam MaheshwarSkylink Hospitality LLP15/07/2021
CC006000000197334MR DAKSHINAMOORTHY MUTHUKUMARSKYLINK HOSPITALITY LLP22/06/2021
CC006000000197386Mr. Rajesh Narayanan Rama IyerSKYLINK HOSPITALITY LLP02/07/2021
CC006000000209715Dr. Sudha Sudesh Sundar & Dr. Sampath Sudesh SundarSkylink Hospitality LLP31/01/2022
CC006000000220680Samir ShahSkylink Hospitality LLP07/04/2022
CC006000000303379Skylink Hospitality LLP PartnershipArcot Maheshwar19/11/2022
CC006000000303380Skylink Hospitality LLP PartnershipKirtikumar Shriyan22/11/2022
CC006000000303403Skylink Hospitality LLP PartnershipDr. Arivazhagan Velusamy22/11/2022
CC006000000303406Skylink Hospitality LLP PartnershipDakshinamoorthy Muthukumar22/11/2022
CC006000000303407Skylink Hospitality LLP PartnershipDhanaraj Mani22/11/2022
CC006000000303410Skylink Hospitality LLP PartnershipKrishna Dass22/11/2022
CC006000000303411Skylink Hospitality LLP PartnershipRajesh Iyer22/11/2022
CC006000000303412Skylink Hospitality LLP PartnershipRamanathan E22/11/2022
CC006000000303413Skylink Hospitality LLP PartnershipReshma Bhatia22/11/2022
CC006000000303414Skylink Hospitality LLP PartnershipSiddharth Ankathil22/11/2022
CC006000000303415Skylink Hospitality LLP PartnershipSubharata Ghosh22/11/2022
CC006000000364583SKYLINK HOSPITALITY LLPSudha Sudesh Sundar02/03/2023
CC006000000364584SKYLINK HOSPITALITY LLPSAMIR SHAH02/03/2023
CC006000000408452PUSHPA RAJSHI ODEDRAM/s. Skylink Hospitality LLP11/12/2023
CC006000000397883Ashish Harikant RaiM/s SKYLINK HOSPITALITY LLP AND ORS17/10/2023
CC006000000408639Pradeep Kumar PremjaniSKYLINK HOSPITALITY LLP26/12/2023
CC006000000428881Sunil Balkrishna KaleSkylink Hospitality LLP17/01/2024
CC006000000429028Shahrukh Adi KhanSkylink Hospitality LLP02/02/2024
CC006000000429037SHANA SINGHSKYLINK HOSPITALITY07/02/2024
CC006000000197617Mr. Siddharth Ankathil & Ms. kivya GuptaSkylink Hospitality LLP31/07/2021
CC006000000198098Kirtikumar ShriyanSkylink Hospitality LLP07/09/2021
CC006000000540756LINUS DIAGO DCOSTASkylink Hospitality LLP12/06/2024
CC006000000591221SAMMAAN CAPITAL LTDSKYLINK HOSPITALITY LLP18/07/2024
CC12400554Jamess Gerald MenezesSKYLINK HOSPITALITY LLP24/10/2024
CC12500383Suniil AjmeraSKYLINK HOSPITALITY LLP05/02/2025
CC12500470SAMMAAN CAPITAL LTD . .SKYLINK HOSPITALITY LLP12/02/2025
CC12500402SAMMAAN CAPITAL LTD . .SKYLINK HOSPITALITY LLP06/02/2025
CC12500471SAMMAAN CAPITAL LTDSKYLINK HOSPITALITY LLP12/02/2025
CC12500731SAMMAAN CAPITAL LTDSKYLINK HOSPITALITY LLP03/03/2025
CC12500732SAMMAAN CAPITAL LTDSKYLINK HOSPITALITY LLP03/03/2025
CC12501055Swapnil G. PrabhuSKYLINK HOSPITALITY LLP28/03/2025
CC12502397Santosh SInghSKYLINK HOSPITALITY LLP15/07/2025
CC12503240KUMAR RAMAKRISHNANSKYLINK HOSPITALITY LLP12/09/2025
CC12504247Sunil Balkrishna KaleSKYLINK HOSPITALITY LLP01/12/2025

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 7 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 18 Aug 2020
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 18 Aug 2020
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 18 Aug 2020Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed103

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 103 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Disclosure of sold/ booked inventoryFile: 1 Dec 17.pdf14 Mar 2023
Disclosure of sold/ booked inventoryFile: 2 March 18.pdf14 Mar 2023
Disclosure of sold/ booked inventoryFile: 3 June 18.pdf14 Mar 2023
Disclosure of sold/ booked inventoryFile: 4 Sept 18.pdf14 Mar 2023
Disclosure of sold/ booked inventoryFile: 5 Dec 18.pdf14 Mar 2023
Disclosure of sold/ booked inventoryFile: 6 March 19.pdf14 Mar 2023
Disclosure of sold/ booked inventoryFile: 7 June 19.pdf14 Mar 2023
Disclosure of sold/ booked inventoryFile: 8 Sept 19.pdf14 Mar 2023
Disclosure of sold/ booked inventoryFile: 9 Dec 19.pdf14 Mar 2023
Disclosure of sold/ booked inventoryFile: 10 March 20.pdf14 Mar 2023
Disclosure of sold/ booked inventoryFile: 11 June 20.pdf14 Mar 2023
Disclosure of sold/ booked inventoryFile: 12 Sep 20.pdf14 Mar 2023
Disclosure of sold/ booked inventoryFile: 13 Dec20.pdf14 Mar 2023
Disclosure of sold/ booked inventoryFile: 14 MArch 21.pdf14 Mar 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 1 Ozone Dec 2017_001.pdf10 Mar 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 2 Ozone March 2018.pdf10 Mar 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 3 Ozone Jun 2018_001.pdf10 Mar 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 4 Ozone Sep 2018_001.pdf10 Mar 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 5 Ozone Dec 2018_001.pdf10 Mar 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 6 Ozone Mar 2019_001.pdf10 Mar 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 7 Ozone Jun 2019_001.pdf10 Mar 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 8 ozone Sep 2019_001.pdf10 Mar 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 9 Ozone Dec 2019_001.pdf10 Mar 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 10 Ozone March 2020_001.pdf10 Mar 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 11 Ozone Jun 2020_001.pdf10 Mar 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 12 Ozone Sep 2020_001.pdf10 Mar 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 13 Ozone Dec 2020.pdf10 Mar 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 14 Ozone March 2021_001.pdf10 Mar 2023
Certificates of CA (Form 3)File: 1 31-12-2017_001.pdf10 Mar 2023
Certificates of CA (Form 3)File: 2 31-03-2018_001.pdf10 Mar 2023
Certificates of CA (Form 3)File: 3 30-06-2018_001.pdf10 Mar 2023
Certificates of CA (Form 3)File: 4 30-09-2018_001.pdf10 Mar 2023
Certificates of CA (Form 3)File: 5-12-2018_001.pdf10 Mar 2023
Certificates of CA (Form 3)File: 6 31-03-2019_001.pdf10 Mar 2023
Certificates of CA (Form 3)File: 7 30-06-2019_001.pdf10 Mar 2023
Certificates of CA (Form 3)File: 8 30-09-2019_001.pdf10 Mar 2023
Certificates of CA (Form 3)File: 9 31-12-2019_001.pdf10 Mar 2023
Certificates of CA (Form 3)File: 10 31-03-2020_001.pdf10 Mar 2023
Certificates of CA (Form 3)File: 11 30-06-2020_001.pdf10 Mar 2023
Certificates of CA (Form 3)File: 12 30-09-2020_001.pdf10 Mar 2023
Certificates of CA (Form 3)File: 13 31-12-2020_001.pdf10 Mar 2023
Certificates of CA (Form 3)File: 14 31-03-2021_001.pdf10 Mar 2023
Disclosure of sold/ booked inventoryFile: Disclosure of sold inventory - Mirabilis.pdf25 Nov 2021
Declaration about Commencement CertificateFile: Mirabilis_Declaration of CC final.pdf6 Nov 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: MIRABILLS_Architect's Certificate 30 06 2021.pdf6 Nov 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: MIRABILLS_Architect's Certificate 30 09 2021.pdf6 Nov 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: RERA FORM 2 - September 2021_compressed.pdf6 Nov 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: RERA FORM 2 - June 2021_compressed.pdf6 Nov 2021
Disclosure of sold/ booked inventoryFile: Mirabilis_New Sales MIS_compressed.pdf6 Nov 2021
Disclosure of sold/ booked inventoryFile: Updated Disclosure of Inventary - Mirabilis - 29-6-21.pdf29 Jun 2021
Building plan approvalFile: IOA- 19-6-2020 -.pdf18 Aug 2020
Layout approvalFile: 1.pdf18 Aug 2020
Layout approvalFile: 2.pdf18 Aug 2020
Layout approvalFile: 3.pdf18 Aug 2020
Layout approvalFile: 4.pdf18 Aug 2020
Layout approvalFile: 5.pdf18 Aug 2020
Layout approvalFile: 6.pdf18 Aug 2020
Layout approvalFile: 7.pdf18 Aug 2020
Building plan approvalFile: IOA- 19-6-2020 -.pdf18 Aug 2020
Building plan approvalFile: IOA- 19-6-2020 -.pdf18 Aug 2020
Copy of Layout Approval (in case of layout)File: 1.pdf18 Aug 2020
Copy of Layout Approval (in case of layout)File: 2.pdf18 Aug 2020
Copy of Layout Approval (in case of layout)File: 3.pdf18 Aug 2020
Copy of Layout Approval (in case of layout)File: 4.pdf18 Aug 2020
Copy of Layout Approval (in case of layout)File: 5.pdf18 Aug 2020
Copy of Layout Approval (in case of layout)File: 6.pdf18 Aug 2020
Copy of Layout Approval (in case of layout)File: 7.pdf18 Aug 2020
Building Plan Approval (IOD)File: IOA- 19-6-2020 -.pdf18 Aug 2020
Building Plan Approval (IOD)File: IOA- 19-6-2020 -.pdf18 Aug 2020
Building Plan Approval (IOD)File: IOA- 19-6-2020 -.pdf18 Aug 2020
Commencement Certificates / NA Order for plotted developmentFile: Further CC - 19-6-2020.pdf18 Aug 2020
OtherFile: Architect Certificate.pdf3 Jun 2019
OtherFile: Rera Application signed copy - 28-1-2019.pdf30 Jan 2019
OtherFile: Acknowledgement - RERA.pdf30 Jan 2019
OtherFile: Declaration.pdf4 Jan 2019
OtherFile: BASEMENT FLOOR.PDF4 Jan 2019
OtherFile: GROUND FLOOR PLAN.PDF4 Jan 2019
OtherFile: 1ST FLOOR.PDF4 Jan 2019
OtherFile: 8TH FLOOR.PDF4 Jan 2019
OtherFile: TERRACE FLOOR.PDF4 Jan 2019

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one moved by 30 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is among them

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep MIRABILIS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near NA6,700+ in Mumbai Suburban

2 kmMIRABILISCompleted 44Lapsed / revoked 21Other 45Dot size: filed unitsN

Filed coordinates, straight-line distance. 110 registered projects within 2 km.

Builder: SKYLINK HOSPITALITY LLP

SKYLINK HOSPITALITY LLP has 1 registration on MahaRERA, including MIRABILIS. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What does it mean that MIRABILIS shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if MIRABILIS is delayed beyond 30 Dec 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of MIRABILIS?

The registered promoter entity is SKYLINK HOSPITALITY LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in MIRABILIS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against MIRABILIS?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for MIRABILIS?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at MIRABILIS?

The professionals named in the filing: Architect: M/s Dot Architects Pvt Ltd as L.S. / Architect; Engineer: Global Engineering Services. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in MIRABILIS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About MIRABILIS. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save MIRABILIS to a free account