Registered No litigation declared Residential / Group Housing project

Midas Natures Nest

By Midas Dream Built Pvt Ltd

RG-MH-43549 · RERA P50400015692 · Last updated on MahaRERA portal: 22 Jul 2025

Source: official MahaRERA filing

Red flags

  • Completion date moved by 45 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Wardha registration emailed to you, free during the pilot beta.
Mar 2027Possession promisedmoved 45 months from the original
107 of 264Construction stages doneacross 24 buildings; furthest along: Staircases, 70%
11 of 24Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 115 documents Report an error

Midas Natures Nest is a Residential / Group Housing project by Midas Dream Built Pvt Ltd in Wardha, Maharashtra, registered with MahaRERA as P50400015692 on 16 Mar 2018. Possession is promised by 31 Mar 2027. The completion date has moved by 45 months from the original filing. 13 of the 24 units on this registration are recorded sold or booked, and 107 of 264 construction stages are filed complete.

At a glance

Project

  • NameMidas Natures Nest
  • TypeResidential / Group Housing
  • Location
    • Bori
    • Seloo
    • Wardha
    • 442104
  • Pincode442104
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P50400015692
  • ReraGenie IDRG-MH-43549

Builder

  • NameMidas Dream Built Pvt Ltd
  • Entity typeCompany
  • Managing DirectorManish Narayanrao Ballal

Key dates

this monthRegisteredMar 2018First promiseJun 2023Revised toMar 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on16 Mar 2018
  • Promised completion31 Mar 2027
  • Revised completionRevised to 31 Mar 2027 (originally 30 Jun 2023)
  • Buildings24 building records
  • Documents filed115 files

Current status

54%13 of 24 units booked

Figures as on 22 Jul 2025, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Wing D Bungalow No 1NA11101
Wing D Bungalow No 2NA11101
Wing D Bungalow No 3NA11101
Wing D Bungalow No 4NA11101
Wing A Bungalow No 5NA11101
Wing A Bungalow No 6NA11101
Wing A Bungalow No 7NA11101
Wing A Bungalow No 8NA11101
Wing A Bungalow No 9NA11101
Wing A Bungalow No 10NA11101
Wing B Bungalow No 11NA11101
Wing B Bungalow No 12NA11101
Wing B Bungalow No 13NA11101
Wing B Bungalow No 14NA11101
Wing B Bungalow No 15NA11101
Wing B Bungalow No 16NA11101
Wing C Bungalow No 17NA11101
Wing C Bungalow No 18NA11101
Wing C Bungalow No 19NA11101
Wing C Bungalow No 20NA11101
Wing C Bungalow No 21NA11101
Wing c bungalow No 22NA11101
Wing C Bungalow No 23NA11101
Wing C Bungalow No 24NA11101

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building20

As on 22 Jul 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection. The count above covers all 24 buildings; the table lists the first 20.

107 of 264 construction stages are filed complete across 24 buildings. The stage furthest along is Staircases, at 70%.

Wing D Bungalow No 173%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Wing D Bungalow No 29%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Wing D Bungalow No 373%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Wing D Bungalow No 473%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Wing A Bungalow No 573%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Wing A Bungalow No 673%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Wing A Bungalow No 773%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Wing A Bungalow No 835%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure40%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises40%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Wing A Bungalow No 973%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Wing A Bungalow No 1073%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Wing B Bungalow No 1173%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Wing B Bungalow No 1245%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks70%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.30%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Wing B Bungalow No 1327%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Wing B Bungalow No 149%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Wing B Bungalow No 159%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Wing B Bungalow No 169%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Wing C Bungalow No 179%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Wing C Bungalow No 189%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Wing C Bungalow No 1973%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Wing C Bungalow No 2073%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 22 Jul 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area8,737 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on22 Jul 2025

Approvals and building plan

Sanctioning authoritySubdivisional Officer Wardha
Permissible FSI8737.0
Proposed, not sanctioned1,224 sq m
Buildings approved24
Buildings sanctioned24

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchDr J c kumarappa Marg opp Maganwadi Wardha

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectManoj M Mhaisgawali
EngineerManoj Madhukarrao Mhaisgawali
Chartered AccountantAtul Bhaiyya
PartnerRole in project
Midas Dream Built Pvt Ltd-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT50400016878Jun 2023 → Mar 2027

Reason as filed by the promoterCovid and Labour Issues

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 7 Mar 2018
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 7 Mar 2018
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 7 Mar 2018
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 6 Mar 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Mar 2027

Documents filed115

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 115 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 1File: 1 Form1.pdf22 Jul 2025
Form 2File: 2 Form 2.pdf22 Jul 2025
Form 3File: Form 3 31-12-2021.pdf22 Jul 2025
Disclosure of Sold and Booked InventoryFile: 5 Inventory.pdf22 Jul 2025
Form 1File: Form 1_31-03-22.pdf22 Jul 2025
Form 2File: Form 2_31-03-22.pdf22 Jul 2025
Form 3File: Form 3 31-03-2022.pdf22 Jul 2025
Disclosure of Sold and Booked InventoryFile: Sales_31-03-22.pdf22 Jul 2025
Form 1File: Form1_30-6-22.pdf22 Jul 2025
Form 2File: Form2_30-6-22.pdf22 Jul 2025
Form 3File: Form 3 30-06-2022.pdf22 Jul 2025
Disclosure of Sold and Booked InventoryFile: Sales_30-06-22.pdf22 Jul 2025
Form 1File: Form 1_30-9-22.pdf22 Jul 2025
Form 2File: Form 2_30-09-22.pdf22 Jul 2025
Form 3File: Form 3 30-09-2022.pdf22 Jul 2025
Disclosure of Sold and Booked InventoryFile: Sales_30-09-22.pdf22 Jul 2025
Form 1File: Form 1 31-12-22.pdf22 Jul 2025
Form 2File: Form 2 31-12-22.pdf22 Jul 2025
Form 3File: Form 3 31-12-22.pdf22 Jul 2025
Disclosure of Sold and Booked InventoryFile: Sales_31-12-22.pdf22 Jul 2025
Form 1File: 1 Architect Certificate.pdf22 Jul 2025
Form 2File: 2 Engineer Certificate.pdf22 Jul 2025
Form 3File: 3 FORM 3.pdf22 Jul 2025
Disclosure of Sold and Booked InventoryFile: 5 Inventory 31-03-23.pdf22 Jul 2025
Form 2File: Engg Certificate 30-06-23.pdf22 Jul 2025
Form 3File: Form -3 30-06-2023 scan and sign.pdf22 Jul 2025
Disclosure of Sold and Booked InventoryFile: INVENTORY 30-6-23.pdf22 Jul 2025
Form 1File: form 1 30-6-2023.pdf22 Jul 2025
Form 2File: Enggi Certificate 30-9-23.pdf22 Jul 2025
Form 3File: Form -3 30-09-2023 sign and scan.pdf22 Jul 2025
Disclosure of Sold and Booked InventoryFile: INVENTORY 30-9-23.pdf22 Jul 2025
Form 1File: Arch Certi 30-9-23.pdf22 Jul 2025
Form 1File: Archi Certificate-31-12-23.pdf22 Jul 2025
Form 2File: Engg Certificate 31-12-23.pdf22 Jul 2025
Form 3File: Form -3 31-12-2023 sign and scan.pdf22 Jul 2025
Disclosure of Sold and Booked InventoryFile: INVENTORY 31-12-23.pdf22 Jul 2025
Form 1File: Arch Certificate-31-03-24.pdf22 Jul 2025
Form 2File: Engg Certificate 31-3-24.pdf22 Jul 2025
Form 3File: Form -3 31-03-2024 sign and scan.pdf22 Jul 2025
Disclosure of Sold and Booked InventoryFile: INVENTORY 31-3-24.pdf22 Jul 2025
Form 1File: Arch Certificate 30-06-24.pdf22 Jul 2025
Form 2File: Engg Certificate 30-6-24.pdf22 Jul 2025
Form 3File: Form -3 30-06-2024 sign and scan.pdf22 Jul 2025
Disclosure of Sold and Booked InventoryFile: INVENTORY 30-6-24.pdf22 Jul 2025
Form 1File: Arch Certi -30-09-24.pdf22 Jul 2025
Form 2File: Engg Certificate 30-9-24.pdf22 Jul 2025
Form 3File: form -3 30-09-2024 sign and scan.pdf22 Jul 2025
Disclosure of Sold and Booked InventoryFile: INVENTORY 30-9-24.pdf22 Jul 2025
Form 1File: Arch Certificate 31-12-24.pdf22 Jul 2025
Form 2File: Engg Certificate 31-12-24.pdf22 Jul 2025
Form 3File: Form -3 31-12-2024 sign and scan.pdf22 Jul 2025
Disclosure of Sold and Booked InventoryFile: INVENTORY 31-12-24.pdf22 Jul 2025
Form 1File: Arch Certificate 31-03-25.pdf22 Jul 2025
Form 2File: Engg Certificate 31-3-25.pdf22 Jul 2025
Form 3File: Form -3 31-03-2025 SCAN AND SIGN.pdf22 Jul 2025
Disclosure of Sold and Booked InventoryFile: INVENTORY 31-3-25.pdf22 Jul 2025
Declaration in FORM BFile: FORM- B_.pdf23 Jun 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form5 mar23.pdf17 Jun 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1 Architect Certificate.pdf27 May 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2 Engineer Certificate.pdf27 May 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: 4 Form 2A.pdf27 May 2023
Disclosure of sold/ booked inventoryFile: 5 Inventory 31-03-23.pdf27 May 2023
Certificates of CA (Form 3)File: Form 3 31-12-22.pdf27 May 2023
Certificates of CA (Form 3)File: 3 FORM 3.pdf27 May 2023
Certificates of CA (Form 3)File: Form 3 Scan.pdf29 Mar 2023
Certificates of CA (Form 3)File: Form 3 Scan.pdf29 Mar 2023
Certificates of CA (Form 3)File: form 3 Scan.pdf29 Mar 2023
Certificates of CA (Form 3)File: Form 3 31-12-21.pdf29 Mar 2023
Certificates of CA (Form 3)File: Form 3 31-03-22.pdf29 Mar 2023
Certificates of CA (Form 3)File: Form 3 30-06-22.pdf29 Mar 2023
Certificates of CA (Form 3)File: Form 3 30-09-22.pdf29 Mar 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: 2018-19.pdf29 Mar 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: 2019-20.pdf29 Mar 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: 2020-21.pdf29 Mar 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: form 5 2021-2022.pdf29 Mar 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1_31-12-21.pdf16 Feb 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1_31-03-22.pdf16 Feb 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form1_30-6-22.pdf16 Feb 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1_30-9-22.pdf16 Feb 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form1_31-12-22.pdf16 Feb 2023

How this compares with Wardha

54%of this project is bookeddistrict median 0%
5%of Wardha projects moved their completion datethis one moved by 45 months
18%of Wardha registrations have lapsed or been cancelledthis one is on the register

Computed across the 290+ Wardha projects on ReraGenie, from their own filings.

Keep Midas Natures Nest on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Bori290+ in Wardha

2 kmMidas Natures NestCompleted 9Lapsed / revoked 2Other 12Dot size: filed unitsN

Filed coordinates, straight-line distance. 23 registered projects within 2 km.

Builder: Midas Dream Built Pvt Ltd

Midas Dream Built Pvt Ltd has 1 registration on MahaRERA, including Midas Natures Nest. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Wardha district page.

Frequently asked questions

What are my rights if Midas Natures Nest is delayed beyond 31 Mar 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Midas Natures Nest?

The registered promoter entity is Midas Dream Built Pvt Ltd, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Midas Natures Nest?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Midas Natures Nest?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Midas Natures Nest?

The professionals named in the filing: Architect: Manoj M Mhaisgawali; Engineer: Manoj Madhukarrao Mhaisgawali; Chartered Accountant: Atul Bhaiyya. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Midas Natures Nest?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Midas Natures Nest. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Midas Natures Nest to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.