MERUSRI SUNSCAPE
RG-KA-59274 · RERA PRM/KA/RERA/1250/303/PR/050725/007893 · Last updated on RERA Karnataka portal: 15 Oct 2026
Source: official RERA Karnataka filing
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
Saved.
MERUSRI SUNSCAPE is a Residential/Group Housing project by MERUSRI SUNSCAPE LLP in Bengaluru Rural, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1250/303/PR/050725/007893 on 5 Jul 2025. Possession is promised by 31 Mar 2030. 14 of the 76 units on this registration are recorded sold or booked, and 0 of 16 construction stages are filed complete.
At a glance
Project
- NameMERUSRI SUNSCAPE
- TypeResidential/Group Housing
- Location
- Devanahalli
- Bengaluru Rural
- 562110
- Pincode562110
- MapView location on Google Maps (as filed on RERA)
- RERA no.PRM/KA/RERA/1250/303/PR/050725/007893
- ReraGenie IDRG-KA-59274
Builder
- NameMERUSRI SUNSCAPE LLP
- Entity typePartnership Firm
- LLPINACJ-4786
- GSTIN29ACBFM6680M1ZK
- Authorized SignatoryVENKATESWARA REDDY MADDURI
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on5 Jul 2025
- Promised completion31 Mar 2030
- Revised completionNone
- Buildings1 building record
- Documents filed183 files
Current status
Figures as on 15 Oct 2026, this project's latest RERA Karnataka filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| MERUSRI SUNSCAPE | - | - | - | 76 | 0 | 76 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
As on 15 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
0 of 16 construction stages are filed complete. The stage furthest along is Earth work and other leveling preparation work, at 16%.
Building: 16% average across the applicable activities
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | 16% |
| Foundation footing work | 16% |
| Upto Plinth Level | 16% |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | 16% |
| Retaining wall (All types) | 16% |
| RCC or MS Framed structure | 16% |
| Masonry Construction | 16% |
| Plastering inside , outside & Ceiling | 16% |
| Joinery: Doors, Windows, Ventilators etc | 16% |
| Basic work of Water supply, Sanitary and Electrification | 16% |
| Dadoing, Skirting, Flooring, Tiles work (All types) | 16% |
| Railing and Grill fixing | 16% |
| Electrification, Water supply and Sanitary Finishing | 16% |
| Painting | 16% |
| Fire prevention and fire fighting fitting and fixture with network | Not applicable |
| Weather Proof work(tile,concrete) | Not applicable |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | Not applicable |
| Elevation work | 16% |
| Internal and External work including landscapes as per sanctioned drawings | 16% |
Progress on shared amenities44
As on 15 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | 16% |
| Sewage and Drainage System | Yes | 16% |
| Water conservation/rain water harvesting/recharge of ground water | Yes | 16% |
| Energy management | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Solid waste management and disposal | No | Not applicable |
| Emergency Evacuation services | No | Not applicable |
| ROADS | Yes | 16% |
| PARKS & TREE PLANTING | Yes | 16% |
| SEWAGE TREATMENT PLANT (STP) | Yes | 16% |
| ELECTRICITY SUPPLY TRANSFORMER AND SUBSTATION | Yes | 16% |
| Internal Roads & Footpaths | No | Not applicable |
| Electricity supply transformer and substation | No | Not applicable |
| Storm water drains | No | Not applicable |
| Use of renewable energy | No | Not applicable |
| Sewage Treatment Plant (STP) | No | Not applicable |
| Parks & Tree planting | No | Not applicable |
| Street Lighting | No | Not applicable |
| Electricity | Yes | 16% |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | Yes | 16% |
| Club House | Yes | 16% |
| Community Hall | No | Not applicable |
| Outdoor Sports facility | No | Not applicable |
| Indoor Sports facility | No | Not applicable |
| Swimming Pool | No | Not applicable |
| Gym | No | Not applicable |
| Parks | No | Not applicable |
| Power Backup | Yes | 16% |
| Piped Gas | No | Not applicable |
| Water and Sanitation | Yes | 16% |
| Air Conditioning | No | Not applicable |
| Staircases | Yes | 16% |
| Lifts | No | Not applicable |
| Corridor/Lobbies | No | Not applicable |
| Fire escapes | No | Not applicable |
| Common entrance and exit for the building/common portico/foyer/verandah | No | Not applicable |
| Basement | No | Not applicable |
| Terrace | No | Not applicable |
| Outer Wall | No | Not applicable |
| Open parking areas | No | Not applicable |
| Provision for lodging of management staff and security staff | No | Not applicable |
| Water conservation and renewable energy | No | Not applicable |
| Common storage spaces | No | Not applicable |
Land and ownership7
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| M/S. MERUSRI DEVELOPERS REPRESENTED BY Mr. VENKATESWARA REDDY MADDURI | - | - |
| M/S. MERUSRI DEVELOPERS REPRESENTED BY Mr. VENKATESWARA REDDY MADDURI | - | - |
| Mr. CHAMARAPAKU DIVAKAR REDDY | - | - |
| Mr. CHAMARAPAKU DIVAKAR REDDY | - | - |
| Mr. CHAMARAPAKU DIVAKAR REDDY | - | - |
| Mr. CHAMARAPAKU DIVAKAR REDDY | - | - |
| Mr. CHAMARAPAKU DIVAKAR REDDY | - | - |
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Cost line | Estimated | Incurred |
|---|---|---|
| Estimated Cost of Construction as certified by Engineer | Rs 70.00 cr | Rs 9.15 cr |
| On-site expenditure-Salaries of workers | - | Rs 16.86 lakh |
| Payment of taxes | - | Rs 28.10 lakh |
| Principal sum and interest payable to financial institutions-Scheduled Banks | - | Rs 2.04 cr |
Certifying professionals and partners3
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | ASIF MOHAMMED |
| Engineer | MURALIDHARA S |
| Chartered Accountant | SAMBA MOORTHY VELAKUR |
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed183
As listed on the registration, under the names the promoter filed them with; the newest 80 of 183 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1250/303/PR/050725/007893 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: SUNSCAPE FORM 4 CA Q2.pdf | 15 Oct 2026 |
| Q2 2026-27 Form-5 Certificate issued by ArchitectFile: SUNSCAPE FORM 5 ARC Q2.pdf | 15 Oct 2026 |
| Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: SUNSCAPE FORM 6 ENG Q2.pdf | 15 Oct 2026 |
| Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form 4 Sunscape CA.pdf | 15 Jul 2026 |
| Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Architect Cert Sunscape Form 5.pdf | 15 Jul 2026 |
| Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Engineer Cert Sunscape Form 6.pdf | 15 Jul 2026 |
| Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form 4 CA cert Merusri Sunscape LLP March 2026.pdf | 9 Jun 2026 |
| Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Sunscape Form 5 Architect cert Marc.pdf | 9 Jun 2026 |
| Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Sunscape Form 6 Engineer cert Marc.pdf | 9 Jun 2026 |
| Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Merusri Sunscape form 04 DEC.pdf | 30 Mar 2026 |
| Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Form 6 - Dec 2025 SUNSCAPE.pdf | 30 Mar 2026 |
| Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form 5 - Dec 2025 SUNSCAPE.pdf | 30 Mar 2026 |
| BLOCK WISE FLOOR WISE APPROVED PLAN 1File: APPROVED PLAN 1.pdf | 1 Jul 2025 |
| BLOCK WISE FLOOR WISE APPROVED PLAN 2File: APPROVED PLAN 2.pdf | 1 Jul 2025 |
| BLOCK WISE FLOOR WISE APPROVED PLAN 3File: APPROVED PLAN 3.pdf | 1 Jul 2025 |
| BLOCK WISE FLOOR WISE APPROVED PLAN 4File: APPROVED PLAN 4.pdf | 1 Jul 2025 |
| BLOCK WISE FLOOR WISE APPROVED PLAN 5File: APPROVED PLAN 5.pdf | 1 Jul 2025 |
| BLOCK WISE FLOOR WISE APPROVED PLAN 6File: APPROVED PLAN 6.pdf | 1 Jul 2025 |
| BLOCK WISE FLOOR WISE APPROVED PLAN 7File: APPROVED PLAN 7.pdf | 1 Jul 2025 |
| BIAAPA Approval LetterFile: BIAAPA Approval Letter.pdf | 1 Jul 2025 |
| BIAAPA New Approval Letter & Commencement CertificateFile: BIAAPA New Approval Letter & Commencement Certificate.pdf | 1 Jul 2025 |
| NOC KSPCB CFE NOCFile: NOC KSPCB CFE NOC.pdf | 1 Jul 2025 |
| Uganavadi Survey Sketch ADLRFile: Uganavadi Survey Sketch ADLR.pdf | 1 Jul 2025 |
| Village Map of KempalinagapuraFile: Village Map of Kempalinagapura.pdf | 1 Jul 2025 |
| Village Map of UganavadiFile: Village Map of Uganavadi.pdf | 1 Jul 2025 |
| Approved Development PlanFile: Approved Development Plan.pdf | 1 Jul 2025 |
| ALL APPROVED PLAN COPIESFile: ALL APPROVED PLAN COPIES.pdf | 1 Jul 2025 |
| ABHF-Sanction-LetterFile: ABHF-Sanction-Letter.pdf | 11 Jun 2025 |
| Approved building plan Original CopyFile: Approved building plan Original Copy.pdf | 11 Jun 2025 |
| Approved Development PlanFile: Approved Development Plan.pdf | 11 Jun 2025 |
| Approved Original Single Plot layout plan orderFile: Approved Original Single Plot layout plan order.pdf | 11 Jun 2025 |
| Approved Original Single Plot layout planFile: Approved Original Single Plot layout plan.pdf | 11 Jun 2025 |
| Approved Sanction PlanFile: Approved Sanction Plan.pdf | 11 Jun 2025 |
| Approved sanctioned drawings, floor plan, sectional drawings and elevationsFile: Approved sanctioned drawings, floor plan, sectional drawings and elevations.pdf | 11 Jun 2025 |
| BIAAPA Approval LetterFile: BIAAPA Approval Letter.pdf | 11 Jun 2025 |
| Building License from Local Authority Original CopyFile: Building License from Local Authority Original Copy.pdf | 11 Jun 2025 |
| Commencement certificateFile: Commencement certificate.pdf | 11 Jun 2025 |
| CONVERSION OM No 627791 - Sy No 13-1File: CONVERSION OM No 627791 - Sy No 13-1.pdf | 11 Jun 2025 |
| CONVERSION OM No 627793 - Sy No 13-2File: CONVERSION OM No 627793 - Sy No 13-2.pdf | 11 Jun 2025 |
| Conversion Order Sy No 13-2File: Conversion Order Sy No 13-2.pdf | 11 Jun 2025 |
| FORM 1 CAFile: FORM 1 CA.pdf | 11 Jun 2025 |
| FORM 3 ENGRFile: FORM 3 ENGR.pdf | 11 Jun 2025 |
| Merusri Developers Financials FY 2023-24File: Merusri Developers Financials FY 2023-24.pdf | 11 Jun 2025 |
| Guideline Value DeclarationFile: Guideline Value Declaration.pdf | 11 Jun 2025 |
| MODT 18394 - MORTGAGE DEEDFile: MODT 18394 - MORTGAGE DEED.pdf | 11 Jun 2025 |
| NOC AIRPORTFile: NOC AIRPORT.pdf | 11 Jun 2025 |
| NOC BESCOMFile: NOC BESCOM.pdf | 11 Jun 2025 |
| NOC from IndustrialFile: NOC from Industrial.pdf | 11 Jun 2025 |
| NOC KSPCB CFE NOCFile: NOC KSPCB CFE NOC.pdf | 11 Jun 2025 |
| OS no 436-18 Order SheetFile: OS no 436-18 Order Sheet.pdf | 11 Jun 2025 |
| OS no 436-18 Piaintiff CopyFile: OS no 436-18 Piaintiff Copy.pdf | 11 Jun 2025 |
| Project SpecificationsFile: Project Specifications.pdf | 11 Jun 2025 |
| Stability CertificateFile: Stability Certificate.pdf | 11 Jun 2025 |
| SY NO 13-1, 13-2 KEMPALINGANAPURA VILLAGE GUIDELINE VALUEFile: SY NO 13-1, 13-2 KEMPALINGANAPURA VILLAGE GUIDELINE VALUE.pdf | 11 Jun 2025 |
| SY NO 23-1, 23-3, 23-4, 24-1, 25-3 OF UGANAVADI VILLAGE GUIDELINE VALUEFile: SY NO 23-1, 23-3, 23-4, 24-1, 25-3 OF UGANAVADI VILLAGE GUIDELINE VALUE.pdf | 11 Jun 2025 |
| Uganavadi Survey Sketch 5-3-2024 by ADLRFile: Uganavadi Survey Sketch 5-3-2024.pdf | 11 Jun 2025 |
| Village Map of KempalinagapuraFile: Village Map of Kempalinagapura.pdf | 11 Jun 2025 |
| Village Map of UganavadiFile: Village Map of Uganavadi.pdf | 11 Jun 2025 |
| Ver 01_ALLOTMENT LETTERFile: Ver 01_ALLOTMENT LETTER.pdf | 11 Jun 2025 |
| Ver 01_AGREEMENT FOR SALEFile: Ver 01_AGREEMENT FOR SALE.pdf | 11 Jun 2025 |
| FORM 2 ARCHFile: FORM 2 ARCH.pdf | 11 Jun 2025 |
| STP DRAWING & DETAILSFile: STP DRAWING & DETAILS.pdf | 11 Jun 2025 |
| NOC PANCHAYATH for WATER NOCFile: NOC PANCHAYATH for WATER NOC.pdf | 11 Jun 2025 |
| ABHF-Sanction-LetterFile: ABHF-Sanction-Letter.pdf | 7 May 2025 |
| Bescom NOCFile: Bescom NOC.pdf | 7 May 2025 |
| BIAAPA Approval LetterFile: BIAAPA Approval Letter.pdf | 7 May 2025 |
| Approved Development PlanFile: Approved Development Plan.pdf | 7 May 2025 |
| CDP DrawingsFile: CDP Drawings.pdf | 7 May 2025 |
| CONVERSION OM No 627791 - Sy No 13-1File: CONVERSION OM No 627791 - Sy No 13-1.pdf | 7 May 2025 |
| CONVERSION OM No 627793 - Sy No 13-2File: CONVERSION OM No 627793 - Sy No 13-2.pdf | 7 May 2025 |
| Conversion Order Sy No 13-2File: Conversion Order Sy No 13-2.pdf | 7 May 2025 |
| KSPCB CFE NOCFile: KSPCB CFE NOC.pdf | 7 May 2025 |
| MODT 18394 - MORTGAGE DEEDFile: MODT 18394 - MORTGAGE DEED.pdf | 7 May 2025 |
| OS no 436-18 Order SheetFile: OS no 436-18 Order Sheet.pdf | 7 May 2025 |
| OS no 436-18 Piaintiff CopyFile: OS no 436-18 Piaintiff Copy.pdf | 7 May 2025 |
| UGANVADI GP EXTFile: UGANVADI GP EXT.pdf | 7 May 2025 |
| UGANVADI MP EXTFile: UGANVADI MP EXT.pdf | 7 May 2025 |
| Village Map of KempalinagapuraFile: Village Map of Kempalinagapura.pdf | 7 May 2025 |
| Village Map of UganavadiFile: Village Map of Uganavadi.pdf | 7 May 2025 |
| RTC Sy No 13-1 from 2024-25File: RTC Sy No 13-1 from 2024-25.pdf | 7 May 2025 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Bengaluru Rural
Computed across the 650+ Bengaluru Rural projects on ReraGenie, from their own filings.
Keep MERUSRI SUNSCAPE on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Bengaluru Rural650+ in Bengaluru Rural
Filed coordinates, straight-line distance. 10 registered projects within 2 km.
BARCA AT GODREJ MSR CITY
M S RAMAIAH VENTURES LLP
Prestige Parklane
APEX REALTY MANAGEMENT PRIVATE LIMITED
Sattva Vasanta Skye
Sattva Resi Private Limited
EMBASSY GREENSHORE
EMBASSY DEVELOPMENTS LIMITED
EMBASSY VERDE PHASE 2
EMBASSY DEVELOPMENTS LIMITED
Assetz Sora & Saki Phase 2
NETRA SOFTWARE TECHNOLOGIES PRIVATE LIMITE
See every Bengaluru Rural project, with the district possession charts
Builder: MERUSRI SUNSCAPE LLP
MERUSRI SUNSCAPE LLP has 1 registration on RERA Karnataka, including MERUSRI SUNSCAPE. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Rural district page.
Frequently asked questions
What are my rights if MERUSRI SUNSCAPE is delayed beyond 31 Mar 2030?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of MERUSRI SUNSCAPE?
The registered promoter entity is MERUSRI SUNSCAPE LLP, a partnership firm as per the filing. Its LLPIN ACJ-4786 and GSTIN 29ACBFM6680M1ZK can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in MERUSRI SUNSCAPE?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at MERUSRI SUNSCAPE?
The professionals named in the filing: Architect: ASIF MOHAMMED; Engineer: MURALIDHARA S; Chartered Accountant: SAMBA MOORTHY VELAKUR. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in MERUSRI SUNSCAPE?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.