ReraGenieLog inGet a buyer report

Home / Browse projects / Bengaluru Rural, Karnataka / MERUSRI SUNSCAPE

Registration approved No litigation declared Residential/Group Housing project

MERUSRI SUNSCAPE

By MERUSRI SUNSCAPE LLP

RG-KA-59274 · RERA PRM/KA/RERA/1250/303/PR/050725/007893 · Last updated on RERA Karnataka portal: 15 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Mar 2030Possession promisedno revision filed
0 of 16Construction stages donefurthest along: Earth work and other leveling..., 16%
62 of 76Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 183 documents Report an error

MERUSRI SUNSCAPE is a Residential/Group Housing project by MERUSRI SUNSCAPE LLP in Bengaluru Rural, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1250/303/PR/050725/007893 on 5 Jul 2025. Possession is promised by 31 Mar 2030. 14 of the 76 units on this registration are recorded sold or booked, and 0 of 16 construction stages are filed complete.

At a glance

Project

  • NameMERUSRI SUNSCAPE
  • TypeResidential/Group Housing
  • Location
    • Devanahalli
    • Bengaluru Rural
    • 562110
  • Pincode562110
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1250/303/PR/050725/007893
  • ReraGenie IDRG-KA-59274

Builder

  • NameMERUSRI SUNSCAPE LLP
  • Entity typePartnership Firm
  • LLPINACJ-4786
  • GSTIN29ACBFM6680M1ZK
  • Authorized SignatoryVENKATESWARA REDDY MADDURI

Key dates

this monthRegisteredJul 2025PromisedMar 2030

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on5 Jul 2025
  • Promised completion31 Mar 2030
  • Revised completionNone
  • Buildings1 building record
  • Documents filed183 files

Current status

18%14 of 76 units booked
16.6%Of the estimated cost spent so far

Figures as on 15 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
MERUSRI SUNSCAPE---76076

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 15 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 16 construction stages are filed complete. The stage furthest along is Earth work and other leveling preparation work, at 16%.

Building: 16% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work16%
Foundation footing work16%
Upto Plinth Level16%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)16%
Retaining wall (All types)16%
RCC or MS Framed structure16%
Masonry Construction16%
Plastering inside , outside & Ceiling16%
Joinery: Doors, Windows, Ventilators etc16%
Basic work of Water supply, Sanitary and Electrification16%
Dadoing, Skirting, Flooring, Tiles work (All types)16%
Railing and Grill fixing16%
Electrification, Water supply and Sanitary Finishing16%
Painting16%
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)Not applicable
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work16%
Internal and External work including landscapes as per sanctioned drawings16%

Progress on shared amenities44

As on 15 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes16%
Sewage and Drainage SystemYes16%
Water conservation/rain water harvesting/recharge of ground waterYes16%
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Solid waste management and disposalNoNot applicable
Emergency Evacuation servicesNoNot applicable
ROADSYes16%
PARKS & TREE PLANTINGYes16%
SEWAGE TREATMENT PLANT (STP)Yes16%
ELECTRICITY SUPPLY TRANSFORMER AND SUBSTATIONYes16%
Internal Roads & FootpathsNoNot applicable
Electricity supply transformer and substationNoNot applicable
Storm water drainsNoNot applicable
Use of renewable energyNoNot applicable
Sewage Treatment Plant (STP)NoNot applicable
Parks & Tree plantingNoNot applicable
Street LightingNoNot applicable
ElectricityYes16%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes16%
Club HouseYes16%
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolNoNot applicable
GymNoNot applicable
ParksNoNot applicable
Power BackupYes16%
Piped GasNoNot applicable
Water and SanitationYes16%
Air ConditioningNoNot applicable
StaircasesYes16%
LiftsNoNot applicable
Corridor/LobbiesNoNot applicable
Fire escapesNoNot applicable
Common entrance and exit for the building/common portico/foyer/verandahNoNot applicable
BasementNoNot applicable
TerraceNoNot applicable
Outer WallNoNot applicable
Open parking areasNoNot applicable
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable
Common storage spacesNoNot applicable

Land and ownership7

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area20,942 sq m
Named landowners7
LandownerVillageDistrict
M/S. MERUSRI DEVELOPERS REPRESENTED BY Mr. VENKATESWARA REDDY MADDURI--
M/S. MERUSRI DEVELOPERS REPRESENTED BY Mr. VENKATESWARA REDDY MADDURI--
Mr. CHAMARAPAKU DIVAKAR REDDY--
Mr. CHAMARAPAKU DIVAKAR REDDY--
Mr. CHAMARAPAKU DIVAKAR REDDY--
Mr. CHAMARAPAKU DIVAKAR REDDY--
Mr. CHAMARAPAKU DIVAKAR REDDY--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 70.00 cr
Cost incurredRs 11.64 cr
Spent of the estimate16.63%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 70.00 crRs 9.15 cr
On-site expenditure-Salaries of workers-Rs 16.86 lakh
Payment of taxes-Rs 28.10 lakh
Principal sum and interest payable to financial institutions-Scheduled Banks-Rs 2.04 cr

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectASIF MOHAMMED
EngineerMURALIDHARA S
Chartered AccountantSAMBA MOORTHY VELAKUR

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed183

As listed on the registration, under the names the promoter filed them with; the newest 80 of 183 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1250/303/PR/050725/007893 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: SUNSCAPE FORM 4 CA Q2.pdf15 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: SUNSCAPE FORM 5 ARC Q2.pdf15 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: SUNSCAPE FORM 6 ENG Q2.pdf15 Oct 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form 4 Sunscape CA.pdf15 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Architect Cert Sunscape Form 5.pdf15 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Engineer Cert Sunscape Form 6.pdf15 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form 4 CA cert Merusri Sunscape LLP March 2026.pdf9 Jun 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Sunscape Form 5 Architect cert Marc.pdf9 Jun 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Sunscape Form 6 Engineer cert Marc.pdf9 Jun 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Merusri Sunscape form 04 DEC.pdf30 Mar 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Form 6 - Dec 2025 SUNSCAPE.pdf30 Mar 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form 5 - Dec 2025 SUNSCAPE.pdf30 Mar 2026
BLOCK WISE FLOOR WISE APPROVED PLAN 1File: APPROVED PLAN 1.pdf1 Jul 2025
BLOCK WISE FLOOR WISE APPROVED PLAN 2File: APPROVED PLAN 2.pdf1 Jul 2025
BLOCK WISE FLOOR WISE APPROVED PLAN 3File: APPROVED PLAN 3.pdf1 Jul 2025
BLOCK WISE FLOOR WISE APPROVED PLAN 4File: APPROVED PLAN 4.pdf1 Jul 2025
BLOCK WISE FLOOR WISE APPROVED PLAN 5File: APPROVED PLAN 5.pdf1 Jul 2025
BLOCK WISE FLOOR WISE APPROVED PLAN 6File: APPROVED PLAN 6.pdf1 Jul 2025
BLOCK WISE FLOOR WISE APPROVED PLAN 7File: APPROVED PLAN 7.pdf1 Jul 2025
BIAAPA Approval LetterFile: BIAAPA Approval Letter.pdf1 Jul 2025
BIAAPA New Approval Letter & Commencement CertificateFile: BIAAPA New Approval Letter & Commencement Certificate.pdf1 Jul 2025
NOC KSPCB CFE NOCFile: NOC KSPCB CFE NOC.pdf1 Jul 2025
Uganavadi Survey Sketch ADLRFile: Uganavadi Survey Sketch ADLR.pdf1 Jul 2025
Village Map of KempalinagapuraFile: Village Map of Kempalinagapura.pdf1 Jul 2025
Village Map of UganavadiFile: Village Map of Uganavadi.pdf1 Jul 2025
Approved Development PlanFile: Approved Development Plan.pdf1 Jul 2025
ALL APPROVED PLAN COPIESFile: ALL APPROVED PLAN COPIES.pdf1 Jul 2025
ABHF-Sanction-LetterFile: ABHF-Sanction-Letter.pdf11 Jun 2025
Approved building plan Original CopyFile: Approved building plan Original Copy.pdf11 Jun 2025
Approved Development PlanFile: Approved Development Plan.pdf11 Jun 2025
Approved Original Single Plot layout plan orderFile: Approved Original Single Plot layout plan order.pdf11 Jun 2025
Approved Original Single Plot layout planFile: Approved Original Single Plot layout plan.pdf11 Jun 2025
Approved Sanction PlanFile: Approved Sanction Plan.pdf11 Jun 2025
Approved sanctioned drawings, floor plan, sectional drawings and elevationsFile: Approved sanctioned drawings, floor plan, sectional drawings and elevations.pdf11 Jun 2025
BIAAPA Approval LetterFile: BIAAPA Approval Letter.pdf11 Jun 2025
Building License from Local Authority Original CopyFile: Building License from Local Authority Original Copy.pdf11 Jun 2025
Commencement certificateFile: Commencement certificate.pdf11 Jun 2025
CONVERSION OM No 627791 - Sy No 13-1File: CONVERSION OM No 627791 - Sy No 13-1.pdf11 Jun 2025
CONVERSION OM No 627793 - Sy No 13-2File: CONVERSION OM No 627793 - Sy No 13-2.pdf11 Jun 2025
Conversion Order Sy No 13-2File: Conversion Order Sy No 13-2.pdf11 Jun 2025
FORM 1 CAFile: FORM 1 CA.pdf11 Jun 2025
FORM 3 ENGRFile: FORM 3 ENGR.pdf11 Jun 2025
Merusri Developers Financials FY 2023-24File: Merusri Developers Financials FY 2023-24.pdf11 Jun 2025
Guideline Value DeclarationFile: Guideline Value Declaration.pdf11 Jun 2025
MODT 18394 - MORTGAGE DEEDFile: MODT 18394 - MORTGAGE DEED.pdf11 Jun 2025
NOC AIRPORTFile: NOC AIRPORT.pdf11 Jun 2025
NOC BESCOMFile: NOC BESCOM.pdf11 Jun 2025
NOC from IndustrialFile: NOC from Industrial.pdf11 Jun 2025
NOC KSPCB CFE NOCFile: NOC KSPCB CFE NOC.pdf11 Jun 2025
OS no 436-18 Order SheetFile: OS no 436-18 Order Sheet.pdf11 Jun 2025
OS no 436-18 Piaintiff CopyFile: OS no 436-18 Piaintiff Copy.pdf11 Jun 2025
Project SpecificationsFile: Project Specifications.pdf11 Jun 2025
Stability CertificateFile: Stability Certificate.pdf11 Jun 2025
SY NO 13-1, 13-2 KEMPALINGANAPURA VILLAGE GUIDELINE VALUEFile: SY NO 13-1, 13-2 KEMPALINGANAPURA VILLAGE GUIDELINE VALUE.pdf11 Jun 2025
SY NO 23-1, 23-3, 23-4, 24-1, 25-3 OF UGANAVADI VILLAGE GUIDELINE VALUEFile: SY NO 23-1, 23-3, 23-4, 24-1, 25-3 OF UGANAVADI VILLAGE GUIDELINE VALUE.pdf11 Jun 2025
Uganavadi Survey Sketch 5-3-2024 by ADLRFile: Uganavadi Survey Sketch 5-3-2024.pdf11 Jun 2025
Village Map of KempalinagapuraFile: Village Map of Kempalinagapura.pdf11 Jun 2025
Village Map of UganavadiFile: Village Map of Uganavadi.pdf11 Jun 2025
Ver 01_ALLOTMENT LETTERFile: Ver 01_ALLOTMENT LETTER.pdf11 Jun 2025
Ver 01_AGREEMENT FOR SALEFile: Ver 01_AGREEMENT FOR SALE.pdf11 Jun 2025
FORM 2 ARCHFile: FORM 2 ARCH.pdf11 Jun 2025
STP DRAWING & DETAILSFile: STP DRAWING & DETAILS.pdf11 Jun 2025
NOC PANCHAYATH for WATER NOCFile: NOC PANCHAYATH for WATER NOC.pdf11 Jun 2025
ABHF-Sanction-LetterFile: ABHF-Sanction-Letter.pdf7 May 2025
Bescom NOCFile: Bescom NOC.pdf7 May 2025
BIAAPA Approval LetterFile: BIAAPA Approval Letter.pdf7 May 2025
Approved Development PlanFile: Approved Development Plan.pdf7 May 2025
CDP DrawingsFile: CDP Drawings.pdf7 May 2025
CONVERSION OM No 627791 - Sy No 13-1File: CONVERSION OM No 627791 - Sy No 13-1.pdf7 May 2025
CONVERSION OM No 627793 - Sy No 13-2File: CONVERSION OM No 627793 - Sy No 13-2.pdf7 May 2025
Conversion Order Sy No 13-2File: Conversion Order Sy No 13-2.pdf7 May 2025
KSPCB CFE NOCFile: KSPCB CFE NOC.pdf7 May 2025
MODT 18394 - MORTGAGE DEEDFile: MODT 18394 - MORTGAGE DEED.pdf7 May 2025
OS no 436-18 Order SheetFile: OS no 436-18 Order Sheet.pdf7 May 2025
OS no 436-18 Piaintiff CopyFile: OS no 436-18 Piaintiff Copy.pdf7 May 2025
UGANVADI GP EXTFile: UGANVADI GP EXT.pdf7 May 2025
UGANVADI MP EXTFile: UGANVADI MP EXT.pdf7 May 2025
Village Map of KempalinagapuraFile: Village Map of Kempalinagapura.pdf7 May 2025
Village Map of UganavadiFile: Village Map of Uganavadi.pdf7 May 2025
RTC Sy No 13-1 from 2024-25File: RTC Sy No 13-1 from 2024-25.pdf7 May 2025

How this compares with Bengaluru Rural

18%of this project is bookeddistrict median 45%
20%of Bengaluru Rural projects moved their completion datethis one has not
0%of Bengaluru Rural registrations are shown as withdrawn or revokedthis one is not

Computed across the 650+ Bengaluru Rural projects on ReraGenie, from their own filings.

Keep MERUSRI SUNSCAPE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Rural650+ in Bengaluru Rural

2 kmMERUSRI SUNSCAPEOther 10Dot size: filed unitsN

Filed coordinates, straight-line distance. 10 registered projects within 2 km.

Builder: MERUSRI SUNSCAPE LLP

MERUSRI SUNSCAPE LLP has 1 registration on RERA Karnataka, including MERUSRI SUNSCAPE. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Rural district page.

Frequently asked questions

What are my rights if MERUSRI SUNSCAPE is delayed beyond 31 Mar 2030?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of MERUSRI SUNSCAPE?

The registered promoter entity is MERUSRI SUNSCAPE LLP, a partnership firm as per the filing. Its LLPIN ACJ-4786 and GSTIN 29ACBFM6680M1ZK can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in MERUSRI SUNSCAPE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at MERUSRI SUNSCAPE?

The professionals named in the filing: Architect: ASIF MOHAMMED; Engineer: MURALIDHARA S; Chartered Accountant: SAMBA MOORTHY VELAKUR. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in MERUSRI SUNSCAPE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About MERUSRI SUNSCAPE. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save MERUSRI SUNSCAPE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.