Home / Browse projects / Mumbai Suburban, Maharashtra / MEGHMANISHA

Registration lapsed No litigation declared Residential / Group Housing project

MEGHMANISHA

By VASTAV DEVELOPERS PVT LTD

RG-MH-86467 · RERA P51800018919 · Last updated on MahaRERA portal: 31 Oct 2023

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 27 months past the filed date
  • 1 complaint at MahaRERA
  • Completion date moved by 21 months
  • 2 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Jul 2024Possession promised27 months past this date
3 of 11Construction stages donefurthest along: Slabs of Super Structure, 81%
1Complaints at MahaRERAon this registration
Jump to the 81 documents Report an error

MEGHMANISHA is a Residential / Group Housing project by VASTAV DEVELOPERS PVT LTD in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800018919 on 14 Dec 2018. Possession was promised by 31 Jul 2024 and is now 27 months past that date. The completion date has moved by 21 months from the original filing. 1 complaint is on record with the regulator.

At a glance

Project

  • NameMEGHMANISHA
  • TypeResidential / Group Housing
  • Location
    • VEER SAVARKAR MARG
    • BHANDUP EAST
    • Kurla
    • Mumbai Suburban
    • 400042
  • Pincode400042
  • RERA no.P51800018919
  • ReraGenie IDRG-MH-86467

Builder

  • NameVASTAV DEVELOPERS PVT LTD
  • Entity typeCompany
  • Managing DirectorAJIT GANESH KARANDIKAR
  • Other registrations2 more →
  • No longer live2 lapsed, de-registered or revoked
  • Declared earlier projects3 →

Key dates

27 months past promisethis monthRegisteredDec 2018First promiseOct 2022Revised toJul 2024

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on14 Dec 2018
  • Promised completion31 Jul 2024
  • Revised completionRevised to 31 Jul 2024 (originally 30 Oct 2022)
  • Buildings1 building record
  • Documents filed81 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
MEGHMANISHA CHS LTDNA170000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 31 Oct 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

3 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 81%.

MEGHMANISHA CHS LTD: 55% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor80%
Slabs of Super Structure81%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises40%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks65%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.35%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 31 Oct 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes50%
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed1

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots1
Closed/Covered1

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area923 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI2742.0
Proposed, not sanctioned1,845 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branch90 FEET ROAD, MULUND EAST, MUMBAI - 400081

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectR P ASUNDARIA
EngineerDATTARAM RAWOOL
Chartered AccountantRAHUL GHARAT
PartnerRole in project
VASTAV DEVELOPERS PVT LTD-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800017855Oct 2022 → Jul 2024

Reason as filed by the promoterRCC Work upto 15th Slab is complete. Brickwork and internal/ external plaster completed upto 10th floor. Due to shortage of funds and no support from Banks/ Financial Institutions, Project got delayed. With the support of Society, New Flat Purchasers, we will complete it before the expiry of the extended period

EXT51800012617Oct 2022 → Oct 2023

Reason as filed by the promoterWe have already purchased the entire required TDR and are in process of applying for Full Commencement Certificate but still it will not be possible to complete the project as per revised date ( 30/10/2022) given by RERA authorities. We are negotiating with Banks / NBFCs / Private Investors for construction finance and are hopeful of getting the financial assistance from them in short time and we will complete the project much before the proposed date of extension.

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC12400639Pooja Ajinkya ZingadeVASTAV DEVELOPERS PVT LTD03/11/2024

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 10 Dec 2018
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 1 Nov 2018
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 1 Nov 2018
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 29 Jul 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed81

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 81 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Declaration in FORM BFile: AFFIDAVIT CUM DECLARATION.pdf31 Oct 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: MM-SEP-FORM1.pdf31 Oct 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: MM-SEP-FORM1.pdf31 Oct 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: MM-FORM2-SEP-23.pdf31 Oct 2023
Disclosure of sold/ booked inventoryFile: MM-SILD-UNSOLD 30-10-2023.pdf31 Oct 2023
Certificates of CA (Form 3)File: FORM-3_compressed.pdf31 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: form-5 MM.pdf31 Oct 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM-1-MM-30-6-23.pdf6 Sep 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: MM-FORM2-30-6-23.pdf6 Sep 2023
Certificates of CA (Form 3)File: MM-3FORM- 30-6-23_compressed.pdf6 Sep 2023
Commencement Certificates / NA Order for plotted developmentFile: 2381222-FurtherCC-signed.pdf29 Jul 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: MM-Form 1 31-3-2023.pdf22 Jun 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM-2 MM.pdf22 Jun 2023
Form 2AFile: FORM-2A -MM.pdf22 Jun 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM-2A -MM.pdf22 Jun 2023
Certificates of CA (Form 3)File: March-2023-MM-Form-3.pdf9 Jun 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: MM FORM-1-DEC-2022.pdf25 Feb 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: MM-FORM-2 DEC-2022.pdf25 Feb 2023
Certificates of CA (Form 3)File: FORM-3-DEC-2022-MM.pdf25 Feb 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: MM- ARCT.pdf11 Nov 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arct Cert-30-6-2022.pdf11 Nov 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENG CERTIFICATES- MM.PDF11 Nov 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 30-9-19.pdf11 Nov 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer's Certificate-MM-31-3-2022.pdf11 Nov 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 30-6-22.pdf11 Nov 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: DEC-21.PDF11 Nov 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: 1 Annual Audit Report of Statutory CA (Form 5) (FY 2017-18).pdf9 Nov 2022
Proforma of Agreement for saleFile: FREE SALE.pdf8 Nov 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FORM 2A_MM-22.pdf7 Nov 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form-5-21-22.pdf2 Nov 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: Form 5 2017-18.pdf28 Oct 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: form 5 -2019-20.pdf28 Oct 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5-2020-21.pdf28 Oct 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM-2_MM.pdf11 Oct 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM-1 MM-OCT 2022.pdf6 Oct 2022
Certificates of CA (Form 3)File: FORM-3 MM (1).pdf29 Sep 2022
Declaration about Commencement CertificateFile: Declaration for CC0001.PDF28 Sep 2022
CERSAI detailsFile: CERSAI_Search_Report_200248309037_For_Asset_Based_Search_28_09_2022_13_00_37_838.pdf28 Sep 2022
Disclosure of sold/ booked inventoryFile: MM-SOLD-UNSOLD.pdf12 Jul 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FORM 2A_MM-21.pdf4 Jul 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arcitect Certificate-MM-31-3-2022.pdf2 Jun 2022
Commencement Certificates / NA Order for plotted developmentFile: Meghmanisha_2276991_FurtherCC_signed.pdf9 Jul 2021
Status of Formation of Legal Entity (Society/Co Op etc.)File: MM_MahaRERA_230621.pdf23 Jun 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: form 50001.PDF13 Mar 2020
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 12-19 MM.pdf24 Feb 2020
Form 2AFile: Form 2 12-19 MM.pdf24 Feb 2020
Certificates of CA (Form 3)File: FORM 3- No-02.PDF24 Feb 2020
Certificates of CA (Form 3)File: FORM 3- No-04.PDF24 Feb 2020
Certificates of CA (Form 3)File: FORM 3- No-05.PDF24 Feb 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 MM 3-19.PDF21 Feb 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 MM 12-19.PDF21 Feb 2020
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENG 31-12-18.pdf21 Feb 2020
Form 2AFile: FORM 2A 9-19 MM.PDF21 Feb 2020
Form 2AFile: Form 2A 12-19 MM.pdf21 Feb 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certifcate MM -30-9-2018.pdf20 Feb 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 30-09-2019 - MM.pdf20 Feb 2020
Certificates of CA (Form 3)File: CA-MM.PDF16 Sep 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCT CERT-MM.PDF29 Aug 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENG CERTIFICATES- MM.PDF29 Aug 2019
Form 2AFile: FORM 2A-MM.PDF29 Aug 2019
Certificates of CA (Form 3)File: CA-MM.PDF29 Aug 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: MM ARCT 31-12-18.pdf4 Jun 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENG 31-12-18.pdf4 Jun 2019
Form 2AFile: 2A FORM 31-12-18.pdf4 Jun 2019
Copy of the legal title reportFile: Title Certificate-MM.PDF10 Dec 2018
Certificates of CA (Form 3)File: CA -MM 30-9-18.PDF10 Dec 2018
Proforma of Allotment letterFile: FREE SALE.pdf10 Dec 2018
Commencement Certificates / NA Order for plotted developmentFile: Meghmanisha 1st CC(Up To Stilt Slab).pdf16 Nov 2018
Declaration in FORM BFile: Form B.PDF16 Nov 2018
Layout approvalFile: LAYOUT.PDF1 Nov 2018
Building plan approvalFile: 1.pdf1 Nov 2018
Building plan approvalFile: 2.pdf1 Nov 2018
Building plan approvalFile: 3.pdf1 Nov 2018
Building plan approvalFile: 4.pdf1 Nov 2018
PAN CardFile: VDPL NEW PAN CARD.PDF1 Nov 2018
Details of encumbrancesFile: NON ENCUMBRANCE.PDF1 Nov 2018
Copy of Layout Approval (in case of layout)File: LAYOUT.PDF1 Nov 2018
Building Plan Approval (IOD)File: 1.pdf1 Nov 2018
Building Plan Approval (IOD)File: 2.pdf1 Nov 2018
Building Plan Approval (IOD)File: 3.pdf1 Nov 2018

Promoter's earlier projects3

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

3 delivered late
ProjectLocationFlatsStatusPromisedDelivered
KAPIL KIRAN CHS LTDCHAPHEKAR BANDHU MARG MULUND EAST MUMBAI 40008166CompletedFeb 2017Late, Jul 2017
CHANDRAVIJAY CHS LTDMAHATMA PHULE ROAD MULUND EAST MUMBAI 40008135CompletedApr 2015Late, Oct 2015
MULUND AASAWARIMITHAGAR ROAD MULUND EAST MUMBAI 40008129CompletedMar 2015Late, Jul 2015

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one moved by 21 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is among them

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep MEGHMANISHA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near BHANDUP EAST6,700+ in Mumbai Suburban

Builder: VASTAV DEVELOPERS PVT LTD

VASTAV DEVELOPERS PVT LTD has 3 registrations on MahaRERA, including AWANTIKA CHS LTD and MEGHMANISHA. Its filings disclose 3 earlier MahaRERA projects: declares 0 of 3 past projects completed on time. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What does it mean that MEGHMANISHA shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if MEGHMANISHA is delayed beyond 31 Jul 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of MEGHMANISHA?

The registered promoter entity is VASTAV DEVELOPERS PVT LTD, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in MEGHMANISHA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against MEGHMANISHA?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for MEGHMANISHA?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at MEGHMANISHA?

The professionals named in the filing: Architect: R P ASUNDARIA; Engineer: DATTARAM RAWOOL; Chartered Accountant: RAHUL GHARAT. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in MEGHMANISHA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About MEGHMANISHA. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save MEGHMANISHA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.