ReraGenieLog inGet a buyer report

Home / Browse projects / Thane, Maharashtra / MEGA 75 WEST

Registered No litigation declared Residential / Group Housing project

MEGA 75 WEST

By Mohammed Yusuf Salim Chaudhary

RG-MH-32709 · RERA P51700080395 · Last updated on MahaRERA portal: 4 Aug 2025

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form
  • All 1 earlier projects delivered on promise

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 3 other registrations and every project registered within 2 km.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Dec 2028Possession promisedno revision filed
3 of 11Construction stages donefurthest along: Slabs of Super Structure, 15%
69 of 69Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 43 documents Report an error

MEGA 75 WEST is a Residential / Group Housing project by Mohammed Yusuf Salim Chaudhary in Thane, Maharashtra, registered with MahaRERA as P51700080395 on 2 Jun 2025. Possession is promised by 31 Dec 2028. 0 of the 69 units on this registration are recorded sold or booked, and 3 of 11 construction stages are filed complete.

At a glance

Project

  • NameMEGA 75 WEST
  • TypeResidential / Group Housing
  • Location
    • SECTOR 10A
    • VASHI
    • NAVI MUMBAI
    • Navi Mumbai (M Corp.)
    • Thane
    • 400703
  • Pincode400703
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700080395
  • ReraGenie IDRG-MH-32709

Builder

  • NameMohammed Yusuf Salim Chaudhary
  • Entity typeIndividual
  • Other registrations3 more →
  • Completed2 of 4
  • Declared earlier projects2 →

Key dates

this monthRegisteredJun 2025PromisedDec 2028

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on2 Jun 2025
  • Promised completion31 Dec 2028
  • Revised completionNone
  • Buildings1 building record
  • Documents filed43 files

Current status

0%0 of 69 units booked
14.0%Work done, per cost certificate

Figures as on 4 Aug 2025, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
MEGA 75 WESTNA151469069

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 4 Aug 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

3 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 15%.

MEGA 75 WEST: 30% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure15%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks10%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 4 Aug 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed112

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots112
Closed/Covered107
Open Space5

Land and ownership2

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area1,500 sq m
Land owned byThe promoter, with other names on the file
Named landowners2
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on23 Jul 2025
LandownerVillageDistrict
MEGA GROUPNavi Mumbai (M Corp.)Thane
URJA CHS LTDNavi Mumbai (M Corp.)Thane

Approvals and building plan

Sanctioning authorityNAVI MUMBAI MUNICIPAL CORPORATION
Permissible FSI5995.79
Proposed, not sanctioned5,996 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSHOP NO 18, SATRA PLAZA,, PALM BEACH ROAD,, SECTOR 19D, NAVI MUMBAI, MAHARASHTRA-400703
Estimated costRs 24.18 cr
Cost incurredRs 3.39 cr
Work done14.04%
BuildingWingEstimatedIncurred
MEGA 75 WESTNARs 21.76 crRs 3.39 cr
-NARs 2.42 cr-

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMRS SHAFQUAT ZEYAUL IMAM
EngineerMR VILAS AGHARKAR
Chartered AccountantMR RUSHABH AGARWAL
PartnerRole in project
Mohammed Yusuf Salim Chaudhary-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 16 Aug 2024
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 27 May 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 30 Jul 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 27 May 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2028

Documents filed43

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Architect certificate30062025.pdf4 Aug 2025
Withdrawal Update Form 2File: Engineer Certificate30062025.pdf4 Aug 2025
Withdrawal Update Form 3File: Form-3 Mega 75 West Q1 FY 2025-26 (1).pdf4 Aug 2025
Declaration in FORM BFile: Form B_.pdf29 May 2025
Declaration in FORM BFile: FORM B _DEVELOPER.pdf29 May 2025
Declaration about all RERA Designated Bank Accounts (Format A)File: Format A Declaration.pdf23 May 2025
Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: Format B_Bank.pdf23 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3 .pdf16 May 2025
Other - LegalFile: FORM B_ Affidavit Society.pdf6 Dec 2024
Other - LegalFile: Form B _ Affidavit cum declaration.pdf5 Dec 2024
Proforma of Agreement for saleFile: AGREEMENT FOR SALE_MEGA 75 WEST.pdf5 Dec 2024
Declaration about all RERA Designated Bank Accounts (Format A)File: Additional Declaration regarding Bank.pdf14 Nov 2024
Other - TechnicalFile: SELF DECLARATION FOR 69 FLATS.pdf13 Nov 2024
Declaration about all RERA Designated Bank Accounts (Format A)File: SOCIETY DECLARATION FOR SEPRATE BANK ACCOUNT.pdf11 Nov 2024
Details of encumbrances concerned to FinanceFile: ENCUBRANCE FINANCE.pdf8 Nov 2024
Declaration about Commencement CertificateFile: DECLARATION OF FORMAT D.pdf8 Nov 2024
Details of encumbrances concerned to LegalFile: ENCUBRANCE FINANCE.pdf8 Nov 2024
Proforma of Allotment letterFile: Model of Allotment letter.pdf5 Nov 2024
Deviation Report with respect to Allotment letterFile: DIVIATION SHEET ALLOTMENT LETTER.pdf5 Nov 2024
Deviation Report with respect to model copy of AgreementFile: DEVIATION SHEET AGREEMENT FOR SALE.pdf5 Nov 2024
Details of encumbrances concerned to FinanceFile: ENCUMBRANCE LETTER _ LEGAL.pdf19 Oct 2024
Disclosure of sold/ booked inventoryFile: Disclosure of sold booked inventory.pdf19 Oct 2024
Details of encumbrances concerned to LegalFile: ENCUMBRANCE LETTER _ LEGAL.pdf19 Oct 2024
Other - TechnicalFile: CC SANTIONED PLAN.pdf19 Oct 2024
Other - LegalFile: URJA _ LEASE DEED _2 of 2.pdf17 Aug 2024
Other - LegalFile: URJA LEASE DEED _1 OF 2.pdf17 Aug 2024
Copy of the legal title reportFile: Title Report.pdf16 Aug 2024
CERSAI detailsFile: CERSAI_Search_Report_200316768542 Date 12_08_2024_15_27_17_145.pdf12 Aug 2024
Disclosure for secured/unsecured finance availed for the projectFile: DISCLOSURE FOR SECURED UNSECURED FINANCE.pdf8 Aug 2024
Building plan approvalFile: CC Drawing.pdf30 Jul 2024
PAN CardFile: URJA CHS_ PAN CARD.pdf30 Jul 2024
Building Plan Approval / NA Order for plotted developmentFile: CC Drawing.pdf30 Jul 2024
Other - LegalFile: URJA_ MODIFIED AGREEMENT.pdf6 Jun 2024
Other - LegalFile: DECLARATION CERSAI.pdf6 Jun 2024
Other - TechnicalFile: ANNEXURE DISTRICT WISE EMAIL ID.pdf6 Jun 2024
Other - TechnicalFile: SELF DECLARATION PROPRIETORSHIPS.pdf6 Jun 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: DISCLOSURE OF INTEREST ANNEXURE A.pdf6 Jun 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEERS CERTIFICATE.pdf5 Jun 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1_Architect.pdf28 May 2024
Layout approvalFile: CC Drawing.pdf27 May 2024
PAN CardFile: 1 PAN Card.pdf27 May 2024
Copy of Layout Approval (in case of layout)File: CC Drawing.pdf27 May 2024
Commencement Certificates / NA Order for plotted developmentFile: COMMENCEMENT CERTIFICATE.pdf27 May 2024

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
Mega NovaPlot no.11 Sector-9 Ulwa Navi Mumbai38CompletedFeb 2017Feb 2017

How this compares with Thane

0%of this project is bookeddistrict median 26%
24%of Thane projects moved their completion datethis one has not
23%of Thane registrations have lapsed or been cancelledthis one is on the register

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep MEGA 75 WEST on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near VASHI, NAVI MUMBAI7,600+ in Thane

2 kmMEGA 75 WESTCompleted 9Lapsed / revoked 3Other 25Dot size: filed unitsN

Filed coordinates, straight-line distance. 37 registered projects within 2 km.

Builder: Mohammed Yusuf Salim Chaudhary

Mohammed Yusuf Salim Chaudhary has 4 registrations on MahaRERA, including Mega Ista and MEGA NEXUS. Its filings disclose 2 earlier MahaRERA projects: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What are my rights if MEGA 75 WEST is delayed beyond 31 Dec 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of MEGA 75 WEST?

The registered promoter entity is Mohammed Yusuf Salim Chaudhary, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in MEGA 75 WEST?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for MEGA 75 WEST?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at MEGA 75 WEST?

The professionals named in the filing: Architect: MRS SHAFQUAT ZEYAUL IMAM; Engineer: MR VILAS AGHARKAR; Chartered Accountant: MR RUSHABH AGARWAL. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in MEGA 75 WEST?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About MEGA 75 WEST. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save MEGA 75 WEST to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.