ReraGenieLog inGet a buyer report

Home / Browse projects / Ahmednagar, Maharashtra / MAULI TOWER

Completed No litigation declared Residential / Group Housing project

MAULI TOWER

By MAYUR ANAND SHINDE

RG-MH-38576 · RERA P52200050742 · Last updated on MahaRERA portal: 5 Nov 2024

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

Nothing adverse is on this record. The buyer report still reads the filed documents themselves.

See what the report covers Free either way: or have every new Ahmednagar registration emailed to you, free during the pilot beta.
Dec 2025Possession promisedregistration recorded completed
10 of 11Construction stages donefurthest along: Podiums (if any), 0%
0Complaints at MahaRERAon this registration
Jump to the 61 documents Report an error

MAULI TOWER is a Residential / Group Housing project by MAYUR ANAND SHINDE in Ahmednagar, Maharashtra, registered with MahaRERA as P52200050742 on 28 Apr 2023. The registration is recorded completed; possession was promised by 31 Dec 2025.

At a glance

Project

  • NameMAULI TOWER
  • TypeResidential / Group Housing
  • Location
    • NAGAR DAUND ROAD
    • KEDGAON
    • Ahmadnagar (M Corp.)
    • Nagar
    • Ahmednagar
    • 414005
  • Pincode414005
  • RERA no.P52200050742
  • ReraGenie IDRG-MH-38576

Builder

  • NameMAYUR ANAND SHINDE
  • Entity typeIndividual

Key dates

this monthRegisteredApr 2023PromisedDec 2025Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on28 Apr 2023
  • Promised completion31 Dec 2025
  • Revised completionNone
  • Buildings1 building record
  • Documents filed61 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Mauli TowerNA60000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 5 Nov 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.

Mauli Tower: 91% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities16

As on 5 Nov 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable
LIFT WITH BACKUPYes100%

Parking filed26

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots26
Closed/Covered26

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area370 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI946.91
Proposed, not sanctioned947 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSUPA

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMayur Shinde
EngineerMayur Shinde
Chartered AccountantAaquib Patel
PartnerRole in project
MAYUR ANAND SHINDE-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 5 Nov 2024
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 4 Nov 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 10 Mar 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 10 Mar 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 5 Nov 2024

Documents filed61

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Copy of the legal title reportFile: Legal Search.pdf5 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf5 Nov 2024
Architect’s Certificate on Completion of Project (Form 4)File: Form 4.pdf5 Nov 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf5 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: fORM 2.pdf5 Nov 2024
Other - LegalFile: 7-12.pdf5 Nov 2024
Other - LegalFile: Sale Deed.pdf5 Nov 2024
Status of Formation of Legal Entity (Society/Co Op etc.)File: DEED OF DECLARATION.pdf5 Nov 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC.pdf5 Nov 2024
Disclosure of sold/ booked inventoryFile: Sold Unsold Inventory.pdf5 Nov 2024
Other - FinanceFile: GST.pdf5 Nov 2024
Other - TechnicalFile: RERA Certificate.pdf5 Nov 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5.pdf5 Nov 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A.pdf5 Nov 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5.pdf5 Nov 2024
Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: Format B.pdf5 Nov 2024
Disclosure for secured/unsecured finance availed for the projectFile: Disclosure for Secure Unsecured Loans.pdf5 Nov 2024
Layout approvalFile: Sanction Plan.pdf4 Nov 2024
Copy of Layout Approval (in case of layout)File: Sanction Plan.pdf4 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Architect Q 2.pdf8 Jun 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Architect Q 3.pdf8 Jun 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Architect Q 4.pdf8 Jun 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Architect Q 1 2024.pdf8 Jun 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Engineer Q 2.pdf8 Jun 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Engineer Q 3.pdf8 Jun 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Engineer Q 4.pdf8 Jun 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Engineer Q 1 2024.pdf8 Jun 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A - Engineer.pdf8 Jun 2024
Disclosure of sold/ booked inventoryFile: Inventory Disclosure - Promoter Letterhead Q2.pdf8 Jun 2024
Disclosure of sold/ booked inventoryFile: Inventory Disclosure - Promoter Letterhead Q3.pdf8 Jun 2024
Disclosure of sold/ booked inventoryFile: Inventory Disclosure - Promoter Letterhead Q4.pdf8 Jun 2024
Disclosure of sold/ booked inventoryFile: Inventory Disclosure - Promoter Letterhead Q1 2024.pdf8 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 Q 2_11zon.pdf8 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 Q 3_11zon.pdf8 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 Q 4_11zon.pdf8 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 Q 1 2024_11zon.pdf8 Jun 2024
Other - TechnicalFile: Mauli Tower B Plan (1).pdf1 Apr 2023
PAN CardFile: 11zon_removed-pages-PDF.pdf16 Mar 2023
Copy of the legal title reportFile: Search Report.pdf16 Mar 2023
Declaration in FORM BFile: Mauli Tower Form B.pdf16 Mar 2023
Layout approvalFile: Mauli tower plan_11zon.pdf10 Mar 2023
Building plan approvalFile: Mauli tower plan_11zon.pdf10 Mar 2023
Details of encumbrances concerned to FinanceFile: No Encumbrance Declaration Finance Mauli Tower.pdf10 Mar 2023
Details of encumbrances concerned to FinanceFile: No Encumbrance Declaration Legal Mauli Tower.pdf10 Mar 2023
Details of encumbrances concerned to LegalFile: No Encumbrance Declaration Finance Mauli Tower.pdf10 Mar 2023
Details of encumbrances concerned to LegalFile: No Encumbrance Declaration Legal Mauli Tower.pdf10 Mar 2023
Copy of Layout Approval (in case of layout)File: Mauli tower plan_11zon.pdf10 Mar 2023
Building Plan Approval / NA Order for plotted developmentFile: Mauli tower plan_11zon.pdf10 Mar 2023
Commencement Certificates / NA Order for plotted developmentFile: Mauli Tower CC.pdf10 Mar 2023
Declaration about Commencement CertificateFile: Declaration About Commencement Certificate Mauli Tower.pdf10 Mar 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate Mauli Tower.pdf10 Mar 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate For Cost Estimation Mauli Tower.pdf10 Mar 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Engineer Quality Assurance Certificate Mauli Tower.pdf10 Mar 2023
CERSAI detailsFile: Mauli Tower Cersai.pdf10 Mar 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 - MAULI TOWER_11zon (1).pdf10 Mar 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Discloser of intrest Format.pdf10 Mar 2023
Proforma of Agreement for saleFile: Agreement to sale Flat Mauli Tower.pdf10 Mar 2023
Proforma of Allotment letterFile: Allotment Letter Flat Mauli Tower.pdf10 Mar 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Bank Account Final Mauli Tower.pdf10 Mar 2023
Deviation Report with respect to Allotment letterFile: Deviation Allotment Flat Mauli tower.pdf10 Mar 2023
Deviation Report with respect to model copy of AgreementFile: Deviation ATS Apartment Mauli Tower.pdf10 Mar 2023

How this compares with Ahmednagar

7%of Ahmednagar projects moved their completion datethis one has not
28%of Ahmednagar registrations have lapsed or been cancelledthis one is completed

Computed across the 490+ Ahmednagar projects on ReraGenie, from their own filings.

Keep MAULI TOWER on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near KEDGAON490+ in Ahmednagar

Builder: MAYUR ANAND SHINDE

MAYUR ANAND SHINDE has 1 registration on MahaRERA, including MAULI TOWER. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Ahmednagar district page.

Frequently asked questions

What are my rights if MAULI TOWER is delayed beyond 31 Dec 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of MAULI TOWER?

The registered promoter entity is MAYUR ANAND SHINDE, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in MAULI TOWER?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for MAULI TOWER?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at MAULI TOWER?

The professionals named in the filing: Architect: Mayur Shinde; Engineer: Mayur Shinde; Chartered Accountant: Aaquib Patel. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in MAULI TOWER?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About MAULI TOWER. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save MAULI TOWER to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.