Home / Browse projects / Ahmednagar, Maharashtra / Mauli Green Park Phase-1
Mauli Green Park Phase-1
RG-MH-13657 · RERA P52200026981 · Last updated on MahaRERA portal: 31 Dec 2025
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 15 other registrations.
See what the report covers Free either way: or have every new Ahmednagar registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Mauli Green Park Phase-1 is a Residential / Group Housing project by Mauli Developers in Ahmednagar, Maharashtra, registered with MahaRERA as P52200026981 on 7 Nov 2020. Possession is promised by 30 Jun 2028. 14 of the 142 units on this registration are recorded sold or booked, and 116 of 165 construction stages are filed complete.
At a glance
Project
- NameMauli Green Park Phase-1
- TypeResidential / Group Housing
- Location
- Walawane Parner Road
- Near Tata Motors
- Supa
- Parner
- Ahmednagar
- 414301
- Pincode414301
- RERA no.P52200026981
- ReraGenie IDRG-MH-13657
Builder
- NameMauli Developers
- Entity typePartnership
- PartnersAnand Bhausaheb Shinde, Vijay Dattatray Hajare
- Other registrations15 more →
- Completed4 of 16
- No longer live8 lapsed, de-registered or revoked
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on7 Nov 2020
- Promised completion30 Jun 2028
- Revised completionNone
- Buildings15 building records
- Documents filed71 files
Current status
Figures as on 31 Dec 2025, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Building-1 A Wing | NA | 5 | 4 | 16 | 0 | 16 |
| Building-2 | NA | 5 | 4 | 17 | 0 | 17 |
| Building-3 | NA | 6 | 5 | 20 | 0 | 20 |
| R 1 Row House | NA | 2 | 2 | 1 | 0 | 1 |
| R 2 Row House | NA | 2 | 2 | 1 | 0 | 1 |
| R 3 Row House | NA | 2 | 2 | 1 | 0 | 1 |
| R 4 Row House | NA | 2 | 2 | 1 | 0 | 1 |
| R 5 Row House | NA | 2 | 2 | 1 | 0 | 1 |
| R 6 Row House | NA | 2 | 2 | 1 | 0 | 1 |
| Building-4 | NA | 6 | 5 | 30 | 0 | 30 |
| Building-5 | NA | 6 | 5 | 20 | 0 | 20 |
| B-5 Twin Bunglow | NA | 2 | 2 | 1 | 0 | 1 |
| B-6 Twin Bunglow | NA | 2 | 2 | 1 | 0 | 1 |
| Bunglow | NA | 3 | 2 | 1 | 0 | 1 |
| Building-6 | NA | 6 | 5 | 30 | 0 | 30 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building15
As on 31 Dec 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
116 of 165 construction stages are filed complete across 15 buildings. The stage furthest along is Basement (if any), at 0%.
Building-1 A Wing73%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Building-273%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Building-373%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
R 1 Row House73%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
R 2 Row House73%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
R 3 Row House73%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
R 4 Row House73%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
R 5 Row House73%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
R 6 Row House73%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Building-473%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Building-573%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
B-5 Twin Bunglow73%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
B-6 Twin Bunglow73%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Bunglow73%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Building-636%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities16
As on 31 Dec 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 100% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | Yes | 100% |
| Community Buildings | Yes | 100% |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | Yes | 100% |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 90% |
| Aggregate area of recreational Open Space | Yes | 100% |
| Open Parking | No | Not applicable |
| Lift | Yes | 100% |
Parking filed179
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Open Space | Total |
|---|---|---|---|
| Building-1 A Wing | 0 | 23 | 23 |
| Building-2 | 0 | 28 | 28 |
| Building-3 | 0 | 25 | 25 |
| Building-4 | 0 | 37 | 37 |
| Building-5 | 0 | 25 | 25 |
| Bunglow | 1 | 3 | 4 |
| Building-6 | 0 | 37 | 37 |
Land and ownership
Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Ar Shankar A Buchade |
| Engineer | Ganesh Yenare |
| Chartered Accountant | Aniket Baldawa |
| Chartered Accountant | Tamhane Ghadage & Company |
| Partner | Role in project |
|---|---|
| Mauli Developers | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 10 Apr 2022 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 10 Apr 2022 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 12 Feb 2022 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 12 Feb 2022Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 29 Nov 2024
Documents filed71
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 1File: Form 1.pdf | 31 Dec 2025 |
| Form 2File: Form 2.pdf | 31 Dec 2025 |
| Form 3File: FORM 3.pdf | 31 Dec 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold unsold total.pdf | 31 Dec 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf | 22 May 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Form Phase I.pdf | 13 May 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA Certificate.pdf | 13 May 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3.pdf | 13 May 2025 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold Phase I.pdf | 13 May 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2024-25)File: FORM 5.pdf | 13 May 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2024-25)File: Form 5.pdf | 13 May 2025 |
| Details of encumbrances concerned to FinanceFile: Details of Encumbrance to finance.pdf | 6 Feb 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3.pdf | 6 Feb 2025 |
| Disclosure of sold/ booked inventoryFile: sold unsold inventory (1).pdf | 6 Feb 2025 |
| Details of encumbrances concerned to LegalFile: Details of Encumbrance to finance.pdf | 6 Feb 2025 |
| Proforma of Allotment letterFile: ALLOTMENT LETTER.pdf | 9 Dec 2024 |
| Details of encumbrancesFile: Encumbrance finamce.pdf | 1 Dec 2024 |
| Details of encumbrances concerned to FinanceFile: Encumbrance legal.pdf | 1 Dec 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 Ph-I.pdf | 1 Dec 2024 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold-Ph-I.pdf | 1 Dec 2024 |
| Details of encumbrances concerned to LegalFile: Encumbrance legal.pdf | 1 Dec 2024 |
| Other - TechnicalFile: self Declaration of OC in phase I.pdf | 1 Dec 2024 |
| Architect’s Certificate on Completion of Project (Form 4)File: Form 4 phase I.pdf | 29 Nov 2024 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC.pdf | 29 Nov 2024 |
| Architect’s Certificate on Completion of Project (Form 4)File: Form 4 phase I -Corrected.pdf | 26 Nov 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1-Ph-I.pdf | 21 Nov 2024 |
| Architect’s Certificate on Completion of Project (Form 4)File: FORM 4 PHASE I.pdf | 21 Nov 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A Phase I.pdf | 21 Nov 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: P1 20 21.pdf | 10 Apr 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: P1 21 22.pdf | 10 Apr 2023 |
| OtherFile: Format C.pdf | 29 May 2022 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold Inventory_compressed.pdf | 26 May 2022 |
| Declaration about Commencement CertificateFile: Declaration about commencement certificate (2).pdf | 15 May 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2 A (1).pdf | 15 May 2022 |
| CERSAI detailsFile: CERSAI_Search_Report_200237344456_For_Asset_Based_Search_15_05_2022_17_16_12_024.pdf | 15 May 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: 20-21.pdf | 15 May 2022 |
| Layout approvalFile: Revised Site1_compressed.pdf | 10 Apr 2022 |
| Copy of the legal title reportFile: New Search-compressed.pdf | 10 Apr 2022 |
| Copy of Layout Approval (in case of layout)File: Revised Site1_compressed.pdf | 10 Apr 2022 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Completion Certificate B1,B2,R1-R6,B5,B6,Bunglow.pdf | 17 Feb 2022 |
| Building plan approvalFile: Revised Site Layout_compressed (1).pdf | 12 Feb 2022 |
| Building plan approvalFile: Revised Building No 3_compressed.pdf | 12 Feb 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: Revised Site Layout_compressed (1).pdf | 12 Feb 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: Revised Building No 3_compressed.pdf | 12 Feb 2022 |
| Commencement Certificates / NA Order for plotted developmentFile: Revised commenncement certificate_1_11zon.pdf | 12 Feb 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate Rera.pdf | 8 Jul 2021 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engg Certificate Rera.pdf | 8 Jul 2021 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engg Certificate Rera.pdf | 8 Jul 2021 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: RERA CA CERTIFICATE.pdf | 8 Jul 2021 |
| Layout approvalFile: Layout- New.pdf | 4 Nov 2020 |
| Building plan approvalFile: Building-1 A Wing.pdf | 4 Nov 2020 |
| Building plan approvalFile: Building-2.pdf | 4 Nov 2020 |
| Building plan approvalFile: Building-3.pdf | 4 Nov 2020 |
| Building plan approvalFile: R1-R6.pdf | 4 Nov 2020 |
| Building plan approvalFile: B3-B6.pdf | 4 Nov 2020 |
| Building plan approvalFile: Banglow.pdf | 4 Nov 2020 |
| Details of encumbrancesFile: encumbrance.pdf | 4 Nov 2020 |
| Copy of Layout Approval (in case of layout)File: Layout- New.pdf | 4 Nov 2020 |
| Building Plan Approval / NA Order for plotted developmentFile: Building-1 A Wing.pdf | 4 Nov 2020 |
| Building Plan Approval / NA Order for plotted developmentFile: Building-2.pdf | 4 Nov 2020 |
| Building Plan Approval / NA Order for plotted developmentFile: Building-3.pdf | 4 Nov 2020 |
| Building Plan Approval / NA Order for plotted developmentFile: R1-R6.pdf | 4 Nov 2020 |
| Building Plan Approval / NA Order for plotted developmentFile: B3-B6.pdf | 4 Nov 2020 |
| Building Plan Approval / NA Order for plotted developmentFile: Banglow.pdf | 4 Nov 2020 |
| Commencement Certificates / NA Order for plotted developmentFile: Bandhkam Permission.pdf | 4 Nov 2020 |
| Commencement Certificates / NA Order for plotted developmentFile: NA Order.pdf | 4 Nov 2020 |
| Declaration in FORM BFile: Form B.pdf | 4 Nov 2020 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate.pdf | 4 Nov 2020 |
| Proforma of Allotment letterFile: Agreement Declaration.pdf | 4 Nov 2020 |
| PAN CardFile: Ferm Pan Card.pdf | 3 Nov 2020 |
| Copy of the legal title reportFile: Search Report Updated.pdf | 3 Nov 2020 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Ahmednagar
Computed across the 490+ Ahmednagar projects on ReraGenie, from their own filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- Red flags and clear checks, the possession story, sanctions and sales, land and title, who you are dealing with
- Joined against the promoter's 15 other registrations, which the RERA portal never shows together
- All 71 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep Mauli Green Park Phase-1 on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Near Tata Motors490+ in Ahmednagar
NATURE VALLEY
RADHAKRUSHNA MADHUKAR KALE
Arihant Pearl
Madan Nemichand Bafana
ARIHANT HILLS
Madan Nemichand Bafana
AABHAS PLAZA
PAWAR NAGARE BUILDCON
ARIHANT PARK PHASE - 4
MADAN NEMICHAND BAFANA
ARIHANT PARK PHASE - 5
MADAN NEMICHAND BAFANA
See every Ahmednagar project, with the district possession charts
Builder: Mauli Developers
MAULI DEVELOPERS has 16 registrations on MahaRERA, including GURUMAULI APARTMENT and SAI CORNER. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Ahmednagar district page.
Frequently asked questions
What are my rights if Mauli Green Park Phase-1 is delayed beyond 30 Jun 2028?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Mauli Green Park Phase-1?
The registered promoter entity is Mauli Developers, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Mauli Green Park Phase-1?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Mauli Green Park Phase-1?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Mauli Green Park Phase-1?
The professionals named in the filing: Architect: Ar Shankar A Buchade; Engineer: Ganesh Yenare; Chartered Accountant: Aniket Baldawa; Chartered Accountant: Tamhane Ghadage & Company. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Mauli Green Park Phase-1?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.