ReraGenieLog inGet a buyer report

Home / Browse projects / Nagpur, Maharashtra / MATRIX ROYAL RESIDENCY

Registered No litigation declared Residential / Group Housing project

MATRIX ROYAL RESIDENCY

By Suchitkumar Diwan Ramteke

RG-MH-44126 · RERA P50500053229 · Last updated on MahaRERA portal: 14 Apr 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 33 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Nagpur registration emailed to you, free during the pilot beta.
Dec 2028Possession promisedmoved 33 months from the original
0 of 22Construction stages doneacross 2 buildings; furthest along: Excavation, 50%
15 of 58Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 90 documents Report an error

MATRIX ROYAL RESIDENCY is a Residential / Group Housing project by Suchitkumar Diwan Ramteke in Nagpur, Maharashtra, registered with MahaRERA as P50500053229 on 23 Oct 2023. Possession is promised by 31 Dec 2028. The completion date has moved by 33 months from the original filing. 43 of the 58 units on this registration are recorded sold or booked, and 0 of 22 construction stages are filed complete.

At a glance

Project

  • NameMATRIX ROYAL RESIDENCY
  • TypeResidential / Group Housing
  • Location
    • Wanadongri
    • Wanadongri (CT)
    • Hingna
    • Nagpur
    • 441110
  • Pincode441110
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P50500053229
  • ReraGenie IDRG-MH-44126

Builder

  • NameSuchitkumar Diwan Ramteke
  • Entity typeIndividual

Key dates

this monthRegisteredOct 2023First promiseMar 2026Revised toDec 2028

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on23 Oct 2023
  • Promised completion31 Dec 2028
  • Revised completionRevised to 31 Dec 2028 (originally 31 Mar 2026)
  • Buildings2 building records
  • Documents filed90 files

Current status

74%43 of 58 units booked

Figures as on 14 Apr 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Matrix royal A WingNA8726531
Matrix Royal B WingNA8727027

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 14 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Excavation, at 50%.

Matrix royal A Wing5%
ActivityProgress
Excavation50%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Matrix Royal B Wing5%
ActivityProgress
Excavation50%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 14 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes0%
Street LightingYes10%
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes10%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed88

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots88
Closed/Covered52
Open Space36
BuildingClosed/CoveredOpen SpaceTotal
Matrix royal A Wing52052
Matrix Royal B Wing03636

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area1,859 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on19 Jun 2025

Approvals and building plan

Sanctioning authorityOffice of the nagar Parishad Wanadongri
Permissible FSI4161.95
Proposed, not sanctioned4,162 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchManish nagar, Nagpur, 440015

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAr Ravi Choudhari
EngineerNitin Dandekar
Chartered AccountantRishi Lashkare lashkare
Chartered AccountantRavindra Lashkare
PartnerRole in project
Suchitkumar Diwan Ramteke-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA22042620699Mar 2026 → Dec 2028

Reason as filed by the promoterWe are writing to request an extension of the registration for our project, MATRIX ROYAL RESIDENCY, which consists of a total of 2 Wings - A & B Wing. The current registration is valid until 31-03-2026, and we request an extension until 31-12-2028. We would like to bring to your notice the current ground reality and the reasons for this request: • Current Progress: Out of the total 2 Wings sanctioned, we have successfully commenced the construction of 2 wings but due to unforeseen circumstances, we couldn’t complete the construction of the project within the time line originally mentioned. • S

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 18 Aug 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 1 May 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 17 Aug 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 22 May 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2028

Documents filed90

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 90 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 1File: Form 1 Architecte Certificate March 2026.pdf14 Apr 2026
Form 2File: Form 2 Engineer Certificate March 2026.pdf14 Apr 2026
Form 3File: Form 3 CA Certificate March 2026.pdf14 Apr 2026
Disclosure of Sold and Booked InventoryFile: Matrix Royal Residency - Disclosure of Sold Inventory - MARCH 2026.pdf14 Apr 2026
Form 1File: Form 1 Arct Cert June 2025.pdf14 Apr 2026
Form 2File: Form 2 Engineer Cert June 2025.pdf14 Apr 2026
Disclosure of Sold and Booked InventoryFile: Matrix Royal Residency - Disclosure of Sold Inventory - June 2025.pdf14 Apr 2026
Form 3File: Form 3 CA Certificate June 2025_compressed.pdf14 Apr 2026
Disclosure of Sold and Booked InventoryFile: Matrix Royal Residency - Disclosure of Sold Inventory - Sept 2025.pdf14 Apr 2026
Form 1File: Form 1 Architecte Cert Sep 2025.pdf14 Apr 2026
Form 2File: Form 2 Engineer Cert September 2025.pdf14 Apr 2026
Form 3File: Form 3 CA Certificate Sep 2025_compressed.pdf14 Apr 2026
Form 1File: Form 1 Arct Cert Dec 2025.pdf14 Apr 2026
Form 2File: Form 2 ENgineerCert Dec 2025.pdf14 Apr 2026
Disclosure of Sold and Booked InventoryFile: Matrix Royal Residency - Disclosure of Sold Inventory - Dec 2025.pdf14 Apr 2026
Form 3File: Form 3 CA Certificate Dec 2025_compressed.pdf14 Apr 2026
Form 1File: Matrix Royal Residency - Form 1.pdf3 Nov 2025
Form 3File: Matrix Royal Residency - Form 3.pdf3 Nov 2025
Form 2File: Matrix Royal Residency - Form 2.pdf3 Nov 2025
Disclosure of Sold and Booked InventoryFile: Matrix Royal Residency - Disclosure.pdf3 Nov 2025
Form 1File: Matrix Royal Residency - Form 1 - December 2024.pdf19 Jun 2025
Form 2File: Matrix Royal Residency - Form 2 - December 2024.pdf19 Jun 2025
Form 3File: Matrix Royal Residency - Form 3 - December 2024.pdf19 Jun 2025
Disclosure of Sold and Booked InventoryFile: Matrix Royal Residency - Disclosure - December 2024.pdf19 Jun 2025
Form 1File: Matrix Royal Residency - Form 1 - September 2024.pdf19 Jun 2025
Form 2File: Matrix Royal Residency - Form 2 - September 2024.pdf19 Jun 2025
Form 3File: Matrix Royal Residency - Form 3 - September 2024.pdf19 Jun 2025
Disclosure of Sold and Booked InventoryFile: Matrix Royal Residency - Disclosure - September 2024.pdf19 Jun 2025
Form 1File: Matrix Royal Residency - Form 1 - June 2024.pdf19 Jun 2025
Form 2File: Matrix Royal Residency - Form 2 - June 2024.pdf19 Jun 2025
Form 3File: Matrix Royal Residency - Form 3 - June 2024.pdf19 Jun 2025
Disclosure of Sold and Booked InventoryFile: Matrix Royal Residency - Disclosure - June 2024.pdf19 Jun 2025
Form 1File: Architect Certificate - March 2024.pdf19 Jun 2025
Form 2File: Engineer Certificate - March 2024.pdf19 Jun 2025
Form 3File: CA Certificate - March 2024.pdf19 Jun 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold - March 2024.pdf19 Jun 2025
Form 1File: Matrix Royal Recidency - Architect Cert - Dec 2023.pdf19 Jun 2025
Form 2File: Matrix Royal Recidency - Engineer Cert - Dec 2023.pdf19 Jun 2025
Form 3File: Matrix Royal Recidency - CA Cert - Dec 2023.pdf19 Jun 2025
Disclosure of Sold and Booked InventoryFile: Matrix Royal Recidency - Disclosure - Dec 2023.pdf19 Jun 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Matrix Royal Residency - Form 1.pdf7 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Matrix Royal Residency - Form 3_compressed.pdf7 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Matrix Royal Residency - Form 2.pdf7 May 2025
Disclosure of sold/ booked inventoryFile: Matrix Royal Residency - Disclosure.pdf7 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Matrix Royal Residency - Form 1 - December 2024.pdf22 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Matrix Royal Residency - Form 3 - December 2024_compressed.pdf22 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Matrix Royal Residency - Form 2 - December 2024.pdf22 Jan 2025
Disclosure of sold/ booked inventoryFile: Matrix Royal Residency - Disclosure - December 2024.pdf22 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Matrix Royal Residency - Form 1 - June 2024.pdf23 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Matrix Royal Residency - Form 1 - September 2024.pdf23 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Matrix Royal Residency - Form 3 - June 2024_compressed.pdf23 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Matrix Royal Residency - Form 3 - September 2024_compressed.pdf23 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Matrix Royal Residency - Form 2 - June 2024.pdf23 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Matrix Royal Residency - Form 2 - September 2024.pdf23 Dec 2024
Disclosure of sold/ booked inventoryFile: Matrix Royal Residency - Disclosure - June 2024.pdf23 Dec 2024
Disclosure of sold/ booked inventoryFile: Matrix Royal Residency - Disclosure - September 2024.pdf23 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate - March 2024.pdf22 May 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate - March 2024.pdf22 May 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Sold - March 2024.pdf22 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate - March 2024_compressed (5).pdf22 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Matrix Royal Recidency - Architect Cert - Dec 2023.pdf24 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Matrix Royal Recidency - Engineer Cert - Dec 2023.pdf24 Jan 2024
Disclosure of sold/ booked inventoryFile: Matrix Royal Recidency - Disclosure - Dec 2023.pdf24 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Matrix Royal Recidency - CA Cert - Dec 2023.pdf24 Jan 2024
Declaration about Commencement CertificateFile: Format D Declaration of CC Matrix.pdf18 Oct 2023
Proforma of Agreement for saleFile: Draft Agreement to Sell.pdf6 Oct 2023
Copy of the legal title reportFile: Legal Title Report.pdf18 Aug 2023
Details of encumbrances concerned to FinanceFile: Encumbrance Certificate - Finance.pdf18 Aug 2023
Details of encumbrances concerned to FinanceFile: Encumbrance Certificate - Legal.pdf18 Aug 2023
Details of encumbrances concerned to LegalFile: Encumbrance Certificate - Finance.pdf18 Aug 2023
Details of encumbrances concerned to LegalFile: Encumbrance Certificate - Legal.pdf18 Aug 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA Certificate Matrix.pdf18 Aug 2023
Deviation Report with respect to model copy of AgreementFile: Deviation Report with respect to Model agreement.pdf18 Aug 2023
Deviation Report with respect to model copy of AgreementFile: Deviation Report with respect to Allotment Letter.pdf18 Aug 2023
Building plan approvalFile: Sanction Map.pdf17 Aug 2023
PAN CardFile: PAN.pdf17 Aug 2023
Building Plan Approval / NA Order for plotted developmentFile: Sanction Map.pdf17 Aug 2023
Building plan approvalFile: Development Commencement Certificates.pdf22 May 2023
Building Plan Approval / NA Order for plotted developmentFile: Development Commencement Certificates.pdf22 May 2023
Declaration in FORM BFile: FORM B.pdf22 May 2023

How this compares with Nagpur

74%of this project is bookeddistrict median 35%
13%of Nagpur projects moved their completion datethis one moved by 33 months
22%of Nagpur registrations have lapsed or been cancelledthis one is on the register

Computed across the 2,800+ Nagpur projects on ReraGenie, from their own filings.

Free monthly report: Nagpur on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep MATRIX ROYAL RESIDENCY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Wanadongri2,800+ in Nagpur

2 kmMATRIX ROYAL RESIDENCYCompleted 10Lapsed / revoked 4Other 24Dot size: filed unitsN

Filed coordinates, straight-line distance. 38 registered projects within 2 km.

Builder: Suchitkumar Diwan Ramteke

Suchitkumar Diwan Ramteke has 1 registration on MahaRERA, including MATRIX ROYAL RESIDENCY. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Nagpur district page.

Frequently asked questions

What are my rights if MATRIX ROYAL RESIDENCY is delayed beyond 31 Dec 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of MATRIX ROYAL RESIDENCY?

The registered promoter entity is Suchitkumar Diwan Ramteke, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in MATRIX ROYAL RESIDENCY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for MATRIX ROYAL RESIDENCY?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at MATRIX ROYAL RESIDENCY?

The professionals named in the filing: Architect: Ar Ravi Choudhari; Engineer: Nitin Dandekar; Chartered Accountant: Rishi Lashkare lashkare; Chartered Accountant: Ravindra Lashkare. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in MATRIX ROYAL RESIDENCY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About MATRIX ROYAL RESIDENCY. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save MATRIX ROYAL RESIDENCY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.