Home / Browse projects / Pune, Maharashtra / MATOSHREE RESIDENCY
MATOSHREE RESIDENCY
RG-MH-89022 · RERA P52100048256 · Last updated on MahaRERA portal: 30 May 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 10 months past the filed date
- Completion date moved by 14 months
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
MATOSHREE RESIDENCY is a Residential / Group Housing project by KRUSHNAI DEVELOPERS in Pune, Maharashtra, registered with MahaRERA as P52100048256 on 22 Dec 2022. Possession was promised by 31 Dec 2025 and is now 10 months past that date. The completion date has moved by 14 months from the original filing. 10 of the 20 units on this registration are recorded sold or booked, and 3 of 11 construction stages are filed complete.
At a glance
Project
- NameMATOSHREE RESIDENCY
- TypeResidential / Group Housing
- Location
- AMBEGAON BK ROAD
- AMBEGAON BUDRUK
- AMBEGAON Bk
- Haveli
- Pune
- 411046
- Pincode411046
- RERA no.P52100048256
- ReraGenie IDRG-MH-89022
Builder
- NameKRUSHNAI DEVELOPERS
- Entity typePartnership
- PartnersSACHIN SHANKAR CHAVAN, SACHIN BHAGAWAN MANE, VAIBHAV TUKARAM MHASKE
- Other registrations1 more →
- No longer live2 lapsed, de-registered or revoked
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on22 Dec 2022
- Promised completion31 Dec 2025
- Revised completionRevised to 31 Dec 2025 (originally 30 Oct 2024)
- Buildings1 building record
- Documents filed100 files
Current status
Figures as on 30 May 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| MATOSHREE RESIDENCY | NA | 4 | 4 | 20 | 0 | 20 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 30 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
3 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 97%.
MATOSHREE RESIDENCY: 80% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 97% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 97% |
| Sanitary Fittings within the flats / premises | 97% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 97% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 97% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 97% |
Progress on shared amenities15
As on 30 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 96% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 96% |
| Storm Water Drains | Yes | 96% |
| Landscaping & Tree Planting | Yes | 96% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 96% |
| Energy managemcnt | Yes | 96% |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 96% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed32
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership31
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| MADHAV VASANTRAO SHINDE | Pune (M Corp.) | Pune |
| NANDKISHOR DNYANOBA SHINDE | Pune (M Corp.) | Pune |
| SANJAY SUBHASH MITHARI | Shahapur | Kolhapur |
| AMOL ASHOK MANE | Dattawad | Kolhapur |
| MAHESH ANANDRAO SHINDE | Katraj | Pune |
| NITIN SHANKARRAO DHAMALE | AMBEGAON Bk | Pune |
| ASHOK GANPATRAO PATIL | Dhebewadi | Satara |
| MOHAN DAMODAR KADAM | Palus | Sangli |
| PRAVIN SHIVAJI JADHAV | Tadasar | Sangli |
| SUBHASH ANKUSH SHINGATE | Mardhe | Satara |
| SARASWATI RAMCHANDRA KHARADE | hingangaon bu. | Sangli |
| KUNDAN SHIVAJI NIKAM | Tadasar | Sangli |
| ANIL SHIVAJI SHINDE | Kadegaon | Sangli |
| PUNAM MAHESH DHANAWADE | Satara | Satara |
| LAXMAN KONDIBA BAKAL | Tadasar | Sangli |
| VANDANA RAHUL KHADE | Tadasar | Sangli |
| SATISH NARAYAN KADAM | Burungwadi | Sangli |
| GANESH TANAJI MHASKE | AMBEGAON Bk | Pune |
| DEVIDAS NARAYAN POTU | Pune (M Corp.) | Pune |
| GANESH SURYAKANT DHEKALE | Pune (M Corp.) | Pune |
| TIRTH BERA | Pune (M Corp.) | Pune |
| SARIKA SANTOSH BHILARE | Virwadi | Pune |
| YOGITA MAHADEV MAHADIK | Nevari | Sangli |
| PARVATI JALINDAR ABHANG | Yede | Sangli |
| AJIT JANARDAN DHUMAL | Satara | Satara |
| SIMA VASANT SALUNKHE | AMBEGAON Bk | Pune |
| VASANT TULSHIRAM GHADAGE | Kurli | Sangli |
| BALASAHEB KHASHABA SURYAWANSHI | Karve | Satara |
| KRUSHNAT MARUTI CHANNE | Kheradewangi | Sangli |
| MALLAMA MANIKRAO ALANGE | AMBEGAON Bk | Pune |
| PRATAP DAMODAR MAHALIK | AMBEGAON Bk | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| MATOSHREE RESIDENCY | NA | Rs 1.85 cr | Rs 1.85 cr |
| - | NA | Rs 15.30 lakh | Rs 15.30 lakh |
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | RUSHIKESH ZAGADE |
| Engineer | RUSHIKESH G ZAGADE |
| Chartered Accountant | GANESH PRABHAKAR DHINDLE |
| Chartered Accountant | SACHIN KASHYAP |
| Partner | Role in project |
|---|---|
| KRUSHNAI DEVELOPERS | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterWe M/s Krushnai Developers project- MATOSHREE RESIDENCY , PROJECT REGISTRATION NUMBER: P52100048256 Do hereby declare that the Extension of project status because of the time period is not sufficient for completion for project. Project was delayed because fund flow are shorted to complete construction and this time funds are available and work in process .we are going to complete project within the stipulated time WITHIN DATED 31/12/2025. accordingly the information provided by us is true and correct.. For your reference attached herewith schedule of balance completion.
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 23 Nov 2022 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 23 Nov 2022 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 12 Oct 2022 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 12 Oct 2022Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed100
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 100 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: FORM 1 ARCHITECT CERTIFICATE.pdf | 30 May 2026 |
| Withdrawal Update Form 2File: FORM 2 ENGINEER CERTIFICATE.pdf | 30 May 2026 |
| Withdrawal Update Form 3File: FORM 3 CA CERTIFICATE.pdf | 30 May 2026 |
| Withdrawal Update Form 1File: FORM 1 ARCHITECT CERTIFICATE.pdf | 26 Nov 2025 |
| Withdrawal Update Form 2File: FORM 2 ENGINEER CERTIFICATE.pdf | 26 Nov 2025 |
| Withdrawal Update Form 3File: FORM 3 CA CERTIFICATE.pdf | 26 Nov 2025 |
| Form 5 (FY 2024-2025)File: FORM 5-2024-25.pdf | 14 Jul 2025 |
| Form 1File: FORM 1 ARCHITECT CERTIFICATE 31-03-2025.pdf | 26 Jun 2025 |
| Form 2File: FORM 2 ENGINEER CERTIFICATE-31-03-2025.pdf | 26 Jun 2025 |
| Form 3File: FORM 3 CA CERTIFICATE-31-03-2025.pdf | 26 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD AND BOOKED INVENTORY.pdf | 26 Jun 2025 |
| Form 1File: FORM 1 ARCHITECT CERTIFICATE-31-12-2024.pdf | 26 Jun 2025 |
| Form 2File: FORM 2 ENGINEER CERTIFICATE-31-12-2024.pdf | 26 Jun 2025 |
| Form 3File: FORM 3 CA CERTIFICATE-31-12-2024.pdf | 26 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD NVENTORY-31-12-2024.pdf | 26 Jun 2025 |
| Form 1File: FORM 1 ARCHITECT CERTIFICATE-30-09-2024.pdf | 26 Jun 2025 |
| Form 2File: FORM 2 ENGINEER CERTIFICATE-30-09-2024.pdf | 26 Jun 2025 |
| Form 3File: FORM 3 CA CERTIFICATE-30-09-2024.pdf | 26 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD NVENTORY-30-09-2024.pdf | 26 Jun 2025 |
| Form 1File: FORM 1 ARCHITECT CERTIFICATE-30-06-2024.pdf | 26 Jun 2025 |
| Form 2File: FORM 2 ENGINEER CERTIFICATE-30-06-2024.pdf | 26 Jun 2025 |
| Form 3File: FORM 3 CA CERTIFICATE-30-06-2024.pdf | 26 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD NVENTORY-30-06-2024.pdf | 26 Jun 2025 |
| Form 1File: FORM 1 ARCHITECT CERTIFICATE.pdf | 26 Jun 2025 |
| Form 2File: FORM 2 ENGINEER CERTIFICATE.pdf | 26 Jun 2025 |
| Form 3File: FORM 3 CA CERTIFICATE.pdf | 26 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD INVENTORY-31-03-2024.pdf | 26 Jun 2025 |
| Form 1File: FORM 1 ARCHITECT CERTIFICATE.pdf | 26 Jun 2025 |
| Form 2File: FORM 2 ENGINEER CERTIFICATE.pdf | 26 Jun 2025 |
| Form 3File: FORM 3 CA CERTIFICATE.pdf | 26 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD INVENTORY-31-03-2024.pdf | 26 Jun 2025 |
| Form 1File: FORM 1 ARCHITECT CERTIFICATE.pdf | 26 Jun 2025 |
| Form 2File: FORM 2 ENGINEER CERTIFICATE.pdf | 26 Jun 2025 |
| Form 3File: FORM 3 CA CERTIFICATE.pdf | 26 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD INVENTORY-30-09-2023.pdf | 26 Jun 2025 |
| Form 1File: FORM 1 ARCHITECT CERTIFICATE.pdf | 26 Jun 2025 |
| Form 2File: FORM 2 ENGINEER CERTIFICATE.pdf | 26 Jun 2025 |
| Form 3File: FORM 3 CA CERTIFICATE.pdf | 26 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD INVENTORY-30-06-2023.pdf | 26 Jun 2025 |
| Form 1File: FORM 1 ARCHITECT CERTIFICATE.pdf | 26 Jun 2025 |
| Form 2File: FORM 2 ENGINEER CERTIFICATE.pdf | 26 Jun 2025 |
| Form 3File: FORM 3 CA CERTIFICATE.pdf | 26 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD INVENTORY-31-03-2023.pdf | 26 Jun 2025 |
| Form 1File: FORM 1 ARCHITECT CERTIFICATE.pdf | 26 Jun 2025 |
| Form 2File: FORM 2 ENGINEER CERTIFICATE.pdf | 26 Jun 2025 |
| Form 3File: FORM 3 CA CERTIFICATE.pdf | 26 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD INVENTORY-31-12-2022.pdf | 26 Jun 2025 |
| Form 2A (FY 2022-2023)File: FORM 2A-2022-23 ENGINEER.pdf | 26 Jun 2025 |
| Form 2A (FY 2023-2024)File: FORM 2A-2023-24 ENGINEER.pdf | 26 Jun 2025 |
| Form 2A (FY 2024-2025)File: FORM 2A-2024-25 ENGINEER.pdf | 26 Jun 2025 |
| Form 5 (FY 2022-2023)File: FORM 5 CA CERTIFICATE.pdf | 26 Jun 2025 |
| Form 5 (FY 2023-2024)File: FORM 5 F Y 2023-24.pdf | 26 Jun 2025 |
| Other - LegalFile: PERT CHART-CONSTRUCTION SCHEDULE.pdf | 12 Apr 2025 |
| Other - LegalFile: DECLARATION.pdf | 11 Apr 2025 |
| Other - LegalFile: SCHEDULE OF BALANCE COMPLETION.pdf | 11 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 ARCHITECT CERTIFICATE-30-06-2024.pdf | 8 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 ARCHITECT CERTIFICATE-30-09-2024.pdf | 8 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 ARCHITECT CERTIFICATE-31-12-2024.pdf | 8 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 ARCHITECT CERTIFICATE 31-03-2025.pdf | 8 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 CA CERTIFICATE-30-06-2024.pdf | 8 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 CA CERTIFICATE-30-09-2024.pdf | 8 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 CA CERTIFICATE-31-12-2024.pdf | 8 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 CA CERTIFICATE-31-03-2025.pdf | 8 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 ENGINEER CERTIFICATE-30-06-2024.pdf | 8 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 ENGINEER CERTIFICATE-30-09-2024.pdf | 8 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 ENGINEER CERTIFICATE-31-12-2024.pdf | 8 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 ENGINEER CERTIFICATE-31-03-2025.pdf | 8 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD AND BOOKED INVENTORY.pdf | 8 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 CA CERTIFICATE.pdf | 8 Apr 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 ARCHITECT CERTIFICATE.pdf | 4 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 ENGINEER CERTIFICATE.pdf | 4 Apr 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 CA CERTIFICATE.pdf | 4 Apr 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5 CA CERTIFICATE.pdf | 4 Apr 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 ARCHITECT CERTIFICATE.pdf | 30 Oct 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 ENGINEER CERTIFICATE.pdf | 30 Oct 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 CA CERTIFICATE.pdf | 22 Jul 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 ARCHITECT CERTIFICATE.pdf | 20 Jul 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 2 ENGINEER CERTIFICATE.pdf | 20 Jul 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 ENGINEER CERTIFICATE.pdf | 20 Jul 2023 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: DECLARATION ABOUT SEPERATE BANK ACCOUNT.pdf | 20 Jul 2023 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 4 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 1 other registration, which the RERA portal never shows together
- All 100 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep MATOSHREE RESIDENCY on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near AMBEGAON BUDRUK13,700+ in Pune
Sai Nagari Phase I
Saikedareshwar Developers LLP
SAI NAGARI Phase V
Saikedareshwar Developers LLP
Sai Nagari Phase II
Saikedareshwar Developers LLP
Sai Nagari Phase IV
Saikedareshwar Developers LLP
Sai Nagari Phase III
Saikedareshwar Developers LLP
Bella Casa - Phase 1
Kakkad Infra LLP
Builder: KRUSHNAI DEVELOPERS
KRUSHNAI DEVELOPERS has 2 registrations on MahaRERA, including VRUNDAAVAN HEIGHTS and MATOSHREE RESIDENCY. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What does it mean that MATOSHREE RESIDENCY shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if MATOSHREE RESIDENCY is delayed beyond 31 Dec 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of MATOSHREE RESIDENCY?
The registered promoter entity is KRUSHNAI DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in MATOSHREE RESIDENCY?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for MATOSHREE RESIDENCY?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at MATOSHREE RESIDENCY?
The professionals named in the filing: Architect: RUSHIKESH ZAGADE; Engineer: RUSHIKESH G ZAGADE; Chartered Accountant: GANESH PRABHAKAR DHINDLE; Chartered Accountant: SACHIN KASHYAP. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in MATOSHREE RESIDENCY?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback