Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
Dec 2027Possession promisedno revision filed
65 of 81Construction stages doneacross 9 buildings; furthest along: Plinth, 0%
1 of 80Units unsoldnot recorded sold or booked
Jump to the 49 documents Report an error

MARUTI SHAHI KUTIR- 2 is a Residential/Group Housing project by RACHANA REALITIES in Gandhinagar, Gujarat, registered with GujRERA as PR/GJ/GANDHINAGAR/DEHGAM/AUDA/RAA11143/030123 on 3 Jan 2023. Possession is promised by 31 Dec 2027. 79 of the 80 units on this registration are recorded sold or booked, and 65 of 81 construction stages are filed complete.

At a glance

Project

  • NameMARUTI SHAHI KUTIR- 2
  • TypeResidential/Group Housing
  • Location
    • MARUTI SHAHIKUTIR-2
    • OPP. MARUTI FLORA 2
    • B/H SHRINATH BUNGLOWS
    • OPP. UMIYA MATA MANDIR
    • NARODA
    • DEHGAM
    • Dehgam
    • Gandhinagar
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/GANDHINAGAR/DEHGAM/AUDA/RAA11143/030123
  • ReraGenie IDRG-GJ-01745

Builder

  • NameRACHANA REALITIES
  • Entity typePARTNERSHIP FIRM

Key dates

this monthRegisteredJan 2023PromisedDec 2027

Key facts

Registration and timeline

  • StatusValid until 31 Dec 2027
  • Registered on3 Jan 2023
  • Promised completion31 Dec 2027
  • Revised completionNone
  • Buildings9 building records
  • Documents filed49 files

Current status

99%79 of 80 units booked
100.0%Of the estimated cost spent so far

Figures as on 1 Jan 2026, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Type-C---606
Type-D---606
Type-E---101
Type-F---23023
Type-G---23023
Type-H---606
Type-I---505
Type-A---505
Type-B---505

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building9

As on 1 Jan 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

65 of 81 construction stages are filed complete across 9 buildings. The stage furthest along is Plinth, at 0%.

Type-C78%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
Type-D78%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
Type-E78%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
Type-F89%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
Type-G78%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
Type-H78%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
Type-I78%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
Type-A78%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
Type-B89%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%

Progress on shared amenities19

As on 1 Jan 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes85%
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)Yes100%
Storm water drainsYes100%
Landscaping and tree plantingYes75%
Street lightingYes65%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingYes90%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes85%
Electrical meter room, sub-station, receiving stationYes75%
Fire fightingYes75%
Drinking water facilitiesNoNot applicable
Emergency evacuationNoNot applicable
Use of renewable energyYes65%
SecurityYes10%
Letter boxNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area12,201 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 17.00 cr
Cost incurredRs 17.00 cr
Spent of the estimate100.0%
BuildingWingEstimatedIncurred
Type-FNARs 4.59 crRs 4.59 cr
Type-GNARs 4.59 crRs 4.59 cr
Type-CNARs 1.36 crRs 1.36 cr
Type-DNARs 1.36 crRs 1.36 cr
Type-ANARs 1.27 crRs 1.27 cr
Type-BNARs 1.27 crRs 1.27 cr
Type-HNARs 1.19 crRs 1.19 cr
Type-INARs 1.02 crRs 1.02 cr
Type-ENARs 34.00 lakhRs 34.00 lakh

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSavan Sureshkumar Saxena
EngineerSHAH SMIT VYOMESHBHAI

Documents filed49

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/GANDHINAGAR/DEHGAM/AUDA/RAA11143/030123 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Accountant's certificate (Form 3)1 Jan 2026
Architect's certificate (Form 1)26 Dec 2025
Engineer's certificate (Form 2)26 Dec 2025
Engineer's certificate annexure26 Dec 2025
Site photograph, Type-C22 Dec 2025
Site photograph, Type-D22 Dec 2025
Site photograph, Type-E22 Dec 2025
Site photograph, Type-F22 Dec 2025
Site photograph, Type-G22 Dec 2025
Site photograph, Type-H22 Dec 2025
Site photograph, Type-I22 Dec 2025
Site photograph, Type-A22 Dec 2025
Site photograph, Type-B22 Dec 2025
RERA registration certificate3 Jan 2023
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Gandhinagar

99%of this project is bookeddistrict median 53%
16%of Gandhinagar projects moved their completion datethis one has not

Computed across the 1,600+ Gandhinagar projects on ReraGenie, from their own filings.

Keep MARUTI SHAHI KUTIR- 2 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Gandhinagar1,600+ in Gandhinagar

2 kmMARUTI SHAHI KUTIR- 2Other 43Dot size: filed unitsN

Filed coordinates, straight-line distance. 43 registered projects within 2 km.

Builder: RACHANA REALITIES

RACHANA REALITIES has 1 registration on GujRERA, including MARUTI SHAHI KUTIR- 2. Read the full track record. See more projects on the Gandhinagar district page.

Frequently asked questions

What are my rights if MARUTI SHAHI KUTIR- 2 is delayed beyond 31 Dec 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of MARUTI SHAHI KUTIR- 2?

The registered promoter entity is RACHANA REALITIES, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in MARUTI SHAHI KUTIR- 2?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at MARUTI SHAHI KUTIR- 2?

The professionals named in the filing: Architect: Savan Sureshkumar Saxena; Engineer: SHAH SMIT VYOMESHBHAI. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in MARUTI SHAHI KUTIR- 2?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About MARUTI SHAHI KUTIR- 2. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save MARUTI SHAHI KUTIR- 2 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.