MARUTI INFRASTRUCTURE
RG-MH-07758 · RERA P50500013816 · Last updated on MahaRERA portal: 3 Jan 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 7 months past the filed date
- Completion date moved by 39 months
- 2 extensions taken
Clear
- No litigation declared
- No complaints on record
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Nagpur registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
MARUTI INFRASTRUCTURE is a Residential / Group Housing project by MARUTI INFRASTRUCTURE in Nagpur, Maharashtra, registered with MahaRERA as P50500013816 on 27 Oct 2017. Possession was promised by 31 Mar 2026 and is now 7 months past that date. The completion date has moved by 39 months from the original filing. 15 of the 32 units on this registration are recorded sold or booked, and 4 of 11 construction stages are filed complete.
At a glance
Project
- NameMARUTI INFRASTRUCTURE
- TypeResidential / Group Housing
- Location
- -
- Sukli
- Nagpur (Rural)
- Nagpur
- 441110
- Pincode441110
- MapView location on Google Maps (as filed on RERA)
- RERA no.P50500013816
- ReraGenie IDRG-MH-07758
Builder
- NameMARUTI INFRASTRUCTURE
- Entity typePartnership
- PartnerAKASH VISHNU KANOJE
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on27 Oct 2017
- Promised completion31 Mar 2026
- Revised completionRevised to 31 Mar 2026 (originally 30 Dec 2022)
- Buildings1 building record
- Documents filed172 files
Current status
Figures as on 3 Jan 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| SHREE RAM APARTMENT | NA | 6 | 4 | 32 | 0 | 32 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 3 Jan 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
4 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 95%.
SHREE RAM APARTMENT: 71% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 95% |
| Sanitary Fittings within the flats / premises | 95% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 95% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 95% |
Progress on shared amenities15
As on 3 Jan 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 95% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 95% |
| Storm Water Drains | Yes | 95% |
| Landscaping & Tree Planting | Yes | 95% |
| Street Lighting | Yes | 95% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 95% |
| Solid Waste Management And Disposal | Yes | 95% |
| Water conservation /Rain water harvesting | Yes | 95% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 95% |
| Aggregate area of recreational Open Space | Yes | 95% |
| Open Parking | Yes | 95% |
Parking filed2
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| SHREE RAM APARTMENT | NA | Rs 3.54 cr | Rs 3.54 cr |
Certifying professionals and partners6
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | G M INGLL |
| Engineer | SANDEEP KESHRAO GADPAYLE |
| Engineer | GAJENDRA INGLE |
| Chartered Accountant | AMIT DARAK |
| Chartered Accountant | MJM ASSOCIATES |
| Chartered Accountant | Priyanka Parse |
| Partner | Role in project |
|---|---|
| MARUTI INFRASTRUCTURE | - |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterSir/Mam it is seen from my Registration Certificate that our Project due date to Complete is 30/12/2022, however due to Pandemic of COVID, we faced extreme Labour shortages and disruption in work completion due to which we couldn’t complete the Project on time. I request you to Kindly grant us the Extension for further One year that is till 30/12/2023 so that we can complete the Project as early as possible.
Reason as filed by the promoterDelay in completion was due to several factors beyond the Promoter’s control, including the COVID-19 pandemic, which resulted in lockdowns, labour migration, and disruption of the supply chain. The Promoter also faced financial constraints, due to which the project could not be completed within the extended timeline.
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 3 Oct 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 3 Oct 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 3 Oct 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 3 Oct 2017Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed172
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 172 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 5 (FY 2020-2021)File: Form 5_31_3_21 maruti.pdf | 3 Jan 2026 |
| Form 5 (FY 2019-2020)File: Form 5_31_3_20.pdf | 3 Jan 2026 |
| Form 5 (FY 2018-2019)File: Form 5_31_3_19.PDF | 3 Jan 2026 |
| Form 5 (FY 2017-2018)File: Form 5_31_3_19.PDF | 3 Jan 2026 |
| Form 5 (FY 2021-2022)File: Form 5_31_3_22 maruti.pdf | 2 Jan 2026 |
| Form 1File: MARUTI INFRASTRUCTURE form 1 (1).pdf | 30 Dec 2025 |
| Form 2File: maruti infra form 2.pdf | 30 Dec 2025 |
| Form 3File: Form 3 Oct to Dec 23 Maruti Infrastructure (1).pdf | 30 Dec 2025 |
| Disclosure of Sold and Booked InventoryFile: MARUTI INFRASTRUCTURE dsbi signed.pdf | 30 Dec 2025 |
| Form 1File: MARUTI INFRASTRUCTURE form 1 (1).pdf | 30 Dec 2025 |
| Form 2File: maruti infra form 2.pdf | 30 Dec 2025 |
| Form 3File: Form 3 Oct to Dec 23 Maruti Infrastructure (1).pdf | 30 Dec 2025 |
| Disclosure of Sold and Booked InventoryFile: MARUTI INFRASTRUCTURE dsbi signed.pdf | 30 Dec 2025 |
| Form 1File: MARUTI INFRASTRUCTURE form 1 (1).pdf | 30 Dec 2025 |
| Form 2File: maruti infra form 2.pdf | 30 Dec 2025 |
| Form 3File: Form 3 Oct to Dec 23 Maruti Infrastructure (1).pdf | 30 Dec 2025 |
| Disclosure of Sold and Booked InventoryFile: MARUTI INFRASTRUCTURE dsbi signed.pdf | 30 Dec 2025 |
| Form 1File: MARUTI INFRASTRUCTURE form 1 (1).pdf | 30 Dec 2025 |
| Form 2File: maruti infra form 2.pdf | 30 Dec 2025 |
| Form 3File: Form 3 Oct to Dec 23 Maruti Infrastructure (1).pdf | 30 Dec 2025 |
| Disclosure of Sold and Booked InventoryFile: MARUTI INFRASTRUCTURE dsbi signed.pdf | 30 Dec 2025 |
| Form 1File: MARUTI INFRASTRUCTURE form 1 (1).pdf | 30 Dec 2025 |
| Form 2File: maruti infra form 2.pdf | 30 Dec 2025 |
| Form 3File: Form 3 Oct to Dec 23 Maruti Infrastructure (1).pdf | 30 Dec 2025 |
| Disclosure of Sold and Booked InventoryFile: MARUTI INFRASTRUCTURE dsbi signed.pdf | 30 Dec 2025 |
| Form 1File: MARUTI INFRASTRUCTURE form 1 (1).pdf | 30 Dec 2025 |
| Form 2File: maruti infra form 2.pdf | 30 Dec 2025 |
| Form 3File: Form 3 Oct to Dec 23 Maruti Infrastructure (1).pdf | 30 Dec 2025 |
| Disclosure of Sold and Booked InventoryFile: MARUTI INFRASTRUCTURE dsbi signed.pdf | 30 Dec 2025 |
| Form 1File: MARUTI INFRASTRUCTURE form 1 (1).pdf | 30 Dec 2025 |
| Form 2File: maruti infra form 2.pdf | 30 Dec 2025 |
| Form 3File: Form 3 Oct to Dec 23 Maruti Infrastructure (1).pdf | 30 Dec 2025 |
| Disclosure of Sold and Booked InventoryFile: MARUTI INFRASTRUCTURE dsbi signed.pdf | 30 Dec 2025 |
| Form 1File: MARUTI INFRASTRUCTURE form 1 (1).pdf | 30 Dec 2025 |
| Form 2File: maruti infra form 2.pdf | 30 Dec 2025 |
| Form 3File: Form 3 Oct to Dec 23 Maruti Infrastructure (1).pdf | 30 Dec 2025 |
| Disclosure of Sold and Booked InventoryFile: MARUTI INFRASTRUCTURE dsbi signed.pdf | 30 Dec 2025 |
| Form 1File: MARUTI INFRASTRUCTURE form 1 (1).pdf | 30 Dec 2025 |
| Form 2File: maruti infra form 2.pdf | 30 Dec 2025 |
| Form 3File: Form 3 Oct to Dec 23 Maruti Infrastructure (1).pdf | 30 Dec 2025 |
| Disclosure of Sold and Booked InventoryFile: MARUTI INFRASTRUCTURE dsbi signed.pdf | 30 Dec 2025 |
| Form 1File: MARUTI INFRASTRUCTURE form 1 (1).pdf | 30 Dec 2025 |
| Form 2File: maruti infra form 2.pdf | 30 Dec 2025 |
| Form 3File: Form 3 Oct to Dec 23 Maruti Infrastructure (1).pdf | 30 Dec 2025 |
| Disclosure of Sold and Booked InventoryFile: MARUTI INFRASTRUCTURE dsbi signed.pdf | 30 Dec 2025 |
| Form 1File: MARUTI INFRASTRUCTURE form 1 (1).pdf | 30 Dec 2025 |
| Form 2File: maruti infra form 2.pdf | 30 Dec 2025 |
| Form 3File: Form 3 Oct to Dec 23 Maruti Infrastructure (1).pdf | 30 Dec 2025 |
| Disclosure of Sold and Booked InventoryFile: MARUTI INFRASTRUCTURE dsbi signed.pdf | 30 Dec 2025 |
| Form 1File: MARUTI INFRASTRUCTURE form 1 (1).pdf | 30 Dec 2025 |
| Form 2File: maruti infra form 2.pdf | 30 Dec 2025 |
| Form 3File: Form 3 Oct to Dec 23 Maruti Infrastructure (1).pdf | 30 Dec 2025 |
| Disclosure of Sold and Booked InventoryFile: MARUTI INFRASTRUCTURE dsbi signed.pdf | 30 Dec 2025 |
| Form 1File: MARUTI INFRASTRUCTURE form 1 (1).pdf | 30 Dec 2025 |
| Form 2File: maruti infra form 2.pdf | 30 Dec 2025 |
| Form 3File: Form 3 Oct to Dec 23 Maruti Infrastructure (1).pdf | 30 Dec 2025 |
| Disclosure of Sold and Booked InventoryFile: MARUTI INFRASTRUCTURE dsbi signed.pdf | 30 Dec 2025 |
| Form 1File: MARUTI INFRASTRUCTURE form 1 (1).pdf | 30 Dec 2025 |
| Form 2File: maruti infra form 2.pdf | 30 Dec 2025 |
| Form 3File: Form 3 Oct to Dec 23 Maruti Infrastructure (1).pdf | 30 Dec 2025 |
| Disclosure of Sold and Booked InventoryFile: MARUTI INFRASTRUCTURE dsbi signed.pdf | 30 Dec 2025 |
| Form 1File: MARUTI INFRASTRUCTURE form 1 (1).pdf | 30 Dec 2025 |
| Form 2File: maruti infra form 2.pdf | 30 Dec 2025 |
| Form 3File: Form 3 Oct to Dec 23 Maruti Infrastructure (1).pdf | 30 Dec 2025 |
| Disclosure of Sold and Booked InventoryFile: MARUTI INFRASTRUCTURE dsbi signed.pdf | 30 Dec 2025 |
| Form 1File: MARUTI INFRASTRUCTURE form 1 (1).pdf | 30 Dec 2025 |
| Form 2File: maruti infra form 2.pdf | 30 Dec 2025 |
| Form 3File: Form 3 Oct to Dec 23 Maruti Infrastructure (1).pdf | 30 Dec 2025 |
| Disclosure of Sold and Booked InventoryFile: MARUTI INFRASTRUCTURE dsbi signed.pdf | 30 Dec 2025 |
| Form 1File: MARUTI INFRASTRUCTURE form 1 (1).pdf | 30 Dec 2025 |
| Form 2File: maruti infra form 2.pdf | 30 Dec 2025 |
| Form 3File: Form 3 Oct to Dec 23 Maruti Infrastructure (1).pdf | 30 Dec 2025 |
| Disclosure of Sold and Booked InventoryFile: MARUTI INFRASTRUCTURE dsbi signed.pdf | 30 Dec 2025 |
| Form 1File: MARUTI INFRASTRUCTURE form 1 (1).pdf | 30 Dec 2025 |
| Form 2File: maruti infra form 2.pdf | 30 Dec 2025 |
| Form 3File: Form 3 Oct to Dec 23 Maruti Infrastructure (1).pdf | 30 Dec 2025 |
| Disclosure of Sold and Booked InventoryFile: MARUTI INFRASTRUCTURE dsbi signed.pdf | 30 Dec 2025 |
| Form 1File: MARUTI INFRASTRUCTURE form 1 (1).pdf | 30 Dec 2025 |
| Form 2File: maruti infra form 2.pdf | 30 Dec 2025 |
| Form 3File: Form 3 Oct to Dec 23 Maruti Infrastructure (1).pdf | 30 Dec 2025 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Nagpur
Computed across the 2,800+ Nagpur projects on ReraGenie, from their own filings.
Free monthly report: Nagpur on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 4 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 172 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep MARUTI INFRASTRUCTURE on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near -2,800+ in Nagpur
Filed coordinates, straight-line distance. 7 registered projects within 2 km.
A2 Universal
Aditya Anagha Multi State Credit Co-Operat
Nagpur Marina
HOABL Impactum Land Private Limited
CANAL FRONT-02
SHIVAJI LAND BUILDERS AND DEVELOPERS
MAuli Nagar 12
P SQUARE REALTY
KANCHAN NAGARI 7
SHUBH INFRASTRUCTURE
MAULI TOWN- 21
KIRTISAGAR REALTY PRIVATE LIMITED
See every Nagpur project, with the district possession charts
Builder: MARUTI INFRASTRUCTURE
MARUTI INFRASTRUCTURE has 1 registration on MahaRERA, including MARUTI INFRASTRUCTURE. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Nagpur district page.
Frequently asked questions
What does it mean that MARUTI INFRASTRUCTURE shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if MARUTI INFRASTRUCTURE is delayed beyond 31 Mar 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of MARUTI INFRASTRUCTURE?
The registered promoter entity is MARUTI INFRASTRUCTURE, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in MARUTI INFRASTRUCTURE?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for MARUTI INFRASTRUCTURE?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at MARUTI INFRASTRUCTURE?
The professionals named in the filing: Architect: G M INGLL; Engineer: SANDEEP KESHRAO GADPAYLE; Engineer: GAJENDRA INGLE; Chartered Accountant: AMIT DARAK; Chartered Accountant: MJM ASSOCIATES; Chartered Accountant: Priyanka Parse. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in MARUTI INFRASTRUCTURE?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback