ReraGenieLog inGet a buyer report

Home / Browse projects / Raigarh, Maharashtra / MARIYAM APARTMENT

Registration lapsed No litigation declared Others project

MARIYAM APARTMENT

By KHALID ABDUL KADIR BEBAN

RG-MH-30591 · RERA P52000032553 · Last updated on MahaRERA portal: 28 Dec 2021

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 46 months past the filed date

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.
Dec 2022Possession promised46 months past this date
5 of 11Construction stages donefurthest along: Sanitary Fittings within the flats /..., 90%
11 of 20Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 19 documents Report an error

MARIYAM APARTMENT is a Others project by KHALID ABDUL KADIR BEBAN in Raigarh, Maharashtra, registered with MahaRERA as P52000032553 on 11 Jan 2022. Possession was promised by 31 Dec 2022 and is now 46 months past that date. 9 of the 20 units on this registration are recorded sold or booked, and 5 of 11 construction stages are filed complete.

At a glance

Project

  • NameMARIYAM APARTMENT
  • TypeOthers
  • Location
    • CTS No 1188
    • Koliwada
    • Ashtami
    • Roha
    • Raigarh
    • 402109
  • Pincode402109
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52000032553
  • ReraGenie IDRG-MH-30591

Builder

  • NameKHALID ABDUL KADIR BEBAN
  • Entity typeIndividual
  • Declared earlier projects1 →

Key dates

46 months past promisethis monthRegisteredJan 2022PromisedDec 2022

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on11 Jan 2022
  • Promised completion31 Dec 2022
  • Revised completionNone
  • Buildings1 building record
  • Documents filed19 files

Current status

45%9 of 20 units booked

Figures as on 28 Dec 2021, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
MARIYAM APARTMENTNA6518220

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 28 Dec 2021, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 11 construction stages are filed complete. The stage furthest along is Sanitary Fittings within the flats / premises, at 90%.

MARIYAM APARTMENT: 68% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Sanitary Fittings within the flats / premises90%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks75%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 28 Dec 2021, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes50%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed1

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots1
Closed/Covered1

Land and ownership4

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area405 sq m
Land owned byThe promoter, with other names on the file
Named landowners4
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on24 Sep 2025
LandownerVillageDistrict
Mohmad Arfaat Nazir Ahmed KirkireNavi Mumbai (M Corp.)Thane
Mohammad Aatif Nazir Ahmed KirkireNavi Mumbai (M Corp.)Thane
Mohammad Sadaat Nazir Ahmed KirkireNavi Mumbai (M Corp.)Thane
Smt Akhatari Nazir Ahmed KirkireNavi Mumbai (M Corp.)Thane

Approvals and building plan

Sanctioning authorityChief Officer, Municipal Council, Roha
Permissible FSI809.4
Proposed, not sanctioned809 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchRoha, Tal-Roha, Dist-Raigad

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectUnik Consultants
EngineerZunaid Jafarkhan Deshmukh Jafarkhan Deshmukh
Chartered AccountantCA Mudassir H Deshmukh
PartnerRole in project
KHALID ABDUL KADIR BEBAN-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 2 Nov 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 1 Sep 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 1 Sep 2021
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 9 Sep 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed19

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
CERSAI detailsFile: CERSAI_Search_Report_200226764293_For_Asset_Based_Search_28_12_2021_14_56_24_722.pdf28 Dec 2021
OtherFile: Declaration-Death.pdf25 Nov 2021
OtherFile: Death Certificate-Nazir Kirkire.pdf25 Nov 2021
Copy of the legal title reportFile: Title-Search.pdf2 Nov 2021
Details of encumbrancesFile: Encumbrance Certificate.pdf2 Nov 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect-Certificate.pdf10 Oct 2021
OtherFile: Form-D.pdf10 Oct 2021
Commencement Certificates / NA Order for plotted developmentFile: Permission-Mariyam.pdf9 Sep 2021
Declaration about Commencement CertificateFile: Form-D.pdf9 Sep 2021
Layout approvalFile: Approved-Drawing-1.pdf1 Sep 2021
Building plan approvalFile: Approved-Drawing-2.pdf1 Sep 2021
PAN CardFile: PAN-Aadhar.pdf1 Sep 2021
Copy of Layout Approval (in case of layout)File: Approved-Drawing-1.pdf1 Sep 2021
Building Plan Approval / NA Order for plotted developmentFile: Approved-Drawing-2.pdf1 Sep 2021
Commencement Certificates / NA Order for plotted developmentFile: Permission-Mariyam.pdf1 Sep 2021
Declaration in FORM BFile: Affidavit-Anne-B.pdf1 Sep 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA-Certificate-Mariyam.pdf1 Sep 2021
Proforma of Allotment letterFile: Allotment Letter.pdf1 Sep 2021
Proforma of Allotment letterFile: Agreement-for-Sale.pdf1 Sep 2021

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered late
ProjectLocationRegisteredStatusPromisedDelivered
AL HASAN RESIDENCYP52000010471Roha, RaigarhAug 2017CompletedDec 2018Late, May 2019

How this compares with Raigarh

45%of this project is bookeddistrict median 29%
20%of Raigarh projects moved their completion datethis one has not
26%of Raigarh registrations have lapsed or been cancelledthis one is among them

Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.

Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep MARIYAM APARTMENT on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Koliwada5,900+ in Raigarh

2 kmMARIYAM APARTMENTCompleted 21Lapsed / revoked 10Other 20Dot size: filed unitsN

Filed coordinates, straight-line distance. 51 registered projects within 2 km.

Builder: KHALID ABDUL KADIR BEBAN

KHALID ABDUL KADIR BEBAN has 1 registration on MahaRERA, including MARIYAM APARTMENT. Its filings disclose 1 earlier MahaRERA project: declares 0 of 1 past projects completed on time. Read the full track record. See more projects on the Raigarh district page.

Frequently asked questions

What does it mean that MARIYAM APARTMENT shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if MARIYAM APARTMENT is delayed beyond 31 Dec 2022?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of MARIYAM APARTMENT?

The registered promoter entity is KHALID ABDUL KADIR BEBAN, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in MARIYAM APARTMENT?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for MARIYAM APARTMENT?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at MARIYAM APARTMENT?

The professionals named in the filing: Architect: Unik Consultants; Engineer: Zunaid Jafarkhan Deshmukh Jafarkhan Deshmukh; Chartered Accountant: CA Mudassir H Deshmukh. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in MARIYAM APARTMENT?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About MARIYAM APARTMENT. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save MARIYAM APARTMENT to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.