Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 5 other registrations and every project registered within 2 km.

See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.
Mar 2018Possession promisedregistration recorded completed
52 of 111Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 43 documents Report an error

Harbour City Sector-I is a Plotted project by Garva Land Deal Private Limited in Raigarh, Maharashtra, registered with MahaRERA as P52000009266 on 22 Aug 2017. The registration is recorded completed; possession was promised by 31 Mar 2018. 59 of the 111 units on this registration are recorded sold or booked.

At a glance

Project

  • NameHarbour City Sector-I
  • TypePlotted
  • Location
    • Dhamansai
    • Roha
    • Raigarh
    • 402109
  • Pincode402109
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52000009266
  • ReraGenie IDRG-MH-39971

Builder

  • NameGarva Land Deal Private Limited
  • Entity typeCompany
  • Managing DirectorVikrant Dattatraya Shilimkar
  • Other registrations5 more →
  • Completed2 of 6
  • No longer live2 lapsed, de-registered or revoked

Key dates

this monthRegisteredAug 2017PromisedMar 2018Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on22 Aug 2017
  • Promised completion31 Mar 2018
  • Revised completionNone
  • BuildingsNot stated in filing
  • Documents filed43 files

Current status

53%59 of 111 units booked

Figures as on 17 Feb 2023, this project's latest MahaRERA filing.

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 17 Feb 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

NA Plot Without Structure:

ActivityProgress
ExcavationNot applicable
Basement (if any)Not applicable
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/PremisesNot applicable
Sanitary Fittings within the flats / premisesNot applicable
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water TanksNot applicable
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.Not applicable
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.Not applicable

Progress on shared amenities15

As on 17 Feb 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes5%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)NoNot applicable
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes25%
Street LightingYes0%
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationNoNot applicable
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area27,070 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI27070.0

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branch93 Anand park, Rajyog Creations, off ITI road, Aundh, Pune 411007

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAmarjeet Kudalkar & Associates
EngineerRajendra Krishna Chaudhari
PartnerRole in project
Garva Land Deal Private Limited-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 30 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 30 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 30 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 30 Mar 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 3 Feb 2023

Documents filed43

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: HCS 1.pdf17 Feb 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: NA Order Sector - 1_compressed.pdf3 Feb 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1_HC SC-1JUN18.pdf11 May 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1_HC SC-1SEP18.pdf11 May 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Harbour city Sector 1compressed.pdf11 May 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2_HC SC-1_JUN18.pdf11 May 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2_HC SC-1_SEP18.pdf11 May 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Harbour Sector1 19-01-19.pdf11 May 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Harbour Sector 1 -June 19 30-03-21.pdf21 Apr 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Harbour Sector 1 -Sept 19 30-03-21.pdf21 Apr 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Harbour Sector 1 -Dec 19 30-03-21.pdf21 Apr 2021
Certificates of CA (Form 3)File: Form 3 Harbour city sector 1 Mar 19.pdf21 Apr 2021
Certificates of CA (Form 3)File: Form 3 Harbour City Sector 1 June 19.pdf21 Apr 2021
Certificates of CA (Form 3)File: Form 3 Harbour City Sector 1 Sep 19.pdf21 Apr 2021
Certificates of CA (Form 3)File: Form 3 Harour city sector 1 Dec 19.pdf21 Apr 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: FORM 5 HCS1.pdf4 Mar 2021
Architect’s Certificate on Completion of Project (Form 4)File: Form 4.pdf12 Nov 2019
Certificates of CA (Form 3)File: Harbour City Sector1.pdf12 Jul 2019
Certificates of CA (Form 3)File: FORM-3 GARVA - Harbor City Sector - 1 JUNE18_compressed.pdf13 Mar 2019
Certificates of CA (Form 3)File: FORM-3 GARVA-Harbor City Sector-1 30 SEP 18_compressed.pdf13 Mar 2019
Certificates of CA (Form 3)File: Form 3-Harbour City 1_March 18.pdf6 Oct 2018
Certificates of CA (Form 5)File: Harbour City- Sec 1.pdf30 Sep 2018
Certificates of CA (Form 3)File: Form 3 Garva_ Harbor City Sector_1_Dec'17-ilovepdf-compressed.pdf11 Apr 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Harbour Sector 1.pdf10 Apr 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate_Harbor Sector 1.pdf10 Apr 2018
Commencement Certificates / NA Order for plotted developmentFile: HC - Sector I.pdf30 Mar 2018
Status of Formation of Legal Entity (Society/Co Op etc.)File: Certificate (Harbar citi Sector) 1.pdf30 Mar 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Harbour Secotor 1 Architect.pdf20 Jan 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Harbour Secotor 1 Architect.pdf20 Jan 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Harbour Sector 1 Engineer.pdf20 Jan 2018
Certificates of CA (Form 3)File: Form 3-harbor city sector 1.pdf20 Jan 2018
Certificates of CA (Form 3)File: Harbor City Sector 1.PDF31 Jul 2017
Layout approvalFile: HC 1.pdf30 Jul 2017
Building plan approval or NA orderFile: Dec HC-1.pdf30 Jul 2017
PAN CardFile: GLDPL-PAN.pdf30 Jul 2017
Copy of the legal title reportFile: Final Report.pdf30 Jul 2017
Details of encumbrancesFile: HC-1.pdf30 Jul 2017
Copy of Layout Approval (in case of layout)File: HC 1.pdf30 Jul 2017
Building Plan Approval (IOD)File: Dec HC-1.pdf30 Jul 2017
Declaration in FORM BFile: HC 1-Form B.pdf30 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: HC-1.pdf30 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: HC-1.pdf30 Jul 2017
Proforma of Allotment letterFile: Dec HC-1.pdf30 Jul 2017

How this compares with Raigarh

53%of this project is bookeddistrict median 29%
20%of Raigarh projects moved their completion datethis one has not
26%of Raigarh registrations have lapsed or been cancelledthis one is completed

Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.

Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Harbour City Sector-I on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Dhamansai5,900+ in Raigarh

2 kmHarbour City Sector-ICompleted 20Lapsed / revoked 11Other 18Dot size: filed unitsN

Filed coordinates, straight-line distance. 49 registered projects within 2 km.

Builder: Garva Land Deal Private Limited

Garva Land Deal Private Limited has 6 registrations on MahaRERA, including Balaji Dham Phase-1 and PHALTAN MEGACITY - RESIDENTIAL. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Raigarh district page.

Frequently asked questions

What are my rights if Harbour City Sector-I is delayed beyond 31 Mar 2018?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Harbour City Sector-I?

The registered promoter entity is Garva Land Deal Private Limited, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Harbour City Sector-I?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Harbour City Sector-I?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Harbour City Sector-I?

The professionals named in the filing: Architect: Amarjeet Kudalkar & Associates; Engineer: Rajendra Krishna Chaudhari. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Harbour City Sector-I?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Harbour City Sector-I. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Harbour City Sector-I to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.