Home / Browse projects / Wardha, Maharashtra / MAJESTIC RESIDENCY
MAJESTIC RESIDENCY
RG-MH-56278 · RERA P50400050776 · Last updated on MahaRERA portal: 14 May 2026
Source: official MahaRERA filing
Red flags
- Completion date moved by 9 months
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Wardha registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
MAJESTIC RESIDENCY is a Residential / Group Housing project by SKYLINE INFRA in Wardha, Maharashtra, registered with MahaRERA as P50400050776 on 3 May 2023. The registration is recorded completed; possession was promised by 30 Sep 2026. The completion date has moved by 9 months from the original filing. 12 of the 16 units on this registration are recorded sold or booked, and 9 of 11 construction stages are filed complete.
At a glance
Project
- NameMAJESTIC RESIDENCY
- TypeResidential / Group Housing
- Location
- PALAKWADI WARDHA
- Palakwadi (Wardha)
- Wardha
- 442001
- Pincode442001
- MapView location on Google Maps (as filed on RERA)
- RERA no.P50400050776
- ReraGenie IDRG-MH-56278
Builder
- NameSKYLINE INFRA
- Entity typePartnership
- PartnersMUSTAFA SAJJAD SAIFEE, ABEDIN HAKIMMUDDIN ESSAJI, NIKESH RAJKUMAR KRIPLANI, VINOD GIRIDHARILAL RATHI, MUSTAFA HAKIMUDDIN ESSAJI, ASHISH PANJABRAO ZODE, FAKHRUDDIN HAKIMUDDIN ESSAJI
- Other registrations4 more →
- Completed1 of 5
- No longer live1 lapsed, de-registered or revoked
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on3 May 2023
- Promised completion30 Sep 2026
- Revised completionRevised to 30 Sep 2026 (originally 31 Dec 2025)
- Buildings1 building record
- Documents filed121 files
Current status
Figures as on 14 May 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| MAJESTIC RESIDENCY | NA | 5 | 4 | 16 | 0 | 16 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 14 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
9 of 11 construction stages are filed complete. The stage furthest along is Basement (if any), at 0%.
MAJESTIC RESIDENCY: 82% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 14 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | No | Not applicable |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed30
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership1
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| SKYLINE INFRA | Wardha (M Cl) | Wardha |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| MAJESTIC RESIDENCY | NA | Rs 2.85 cr | Rs 2.85 cr |
Certifying professionals and partners6
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | SHRENIK KHONDE |
| Architect | EMANATE DESIGN |
| Engineer | SAGAR NARAWADIYA |
| Chartered Accountant | DARSHAN WAKHARIYA |
| Chartered Accountant | CA ANKIT TALREJA |
| Chartered Accountant | SUMIT SANTOSH AGRAWAL & ASSOCIATES |
| Partner | Role in project |
|---|---|
| SKYLINE INFRA | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterWe, MARIGOLD REALITY (Promoter), through our Partner and Authorized Signatory MR. MUSTAFA SAJJAD SAIFEE, of the real estate project “MAJESTIC RESIDENCY”, bearing MahaRERA Registration No. P50400050776, respectfully submit this application seeking an extension of Nine (9) months i.e., up to 30/09/2026 for the completion of the project. The originally declared project completion date under MahaRERA was 31/12/2025. However, we have received the Occupation Certificate (OC) on 09/01/2026. The project experienced minor delays due to: • Delays in obtaining certain statutory approvals and completing p
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 10 Feb 2023 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 21 Apr 2023 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 13 Feb 2023 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 13 Feb 2023Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed121
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 121 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: FORM-1 MAJESHTIC RESIDENCY MAR-2026.pdf | 14 May 2026 |
| Withdrawal Update Form 2File: FORM-2 MAJESTIC RESIDENCY MAR-2026.pdf | 14 May 2026 |
| Withdrawal Update Form 3File: FORM-3 MAJESTIC RESIDENCY MAR-2026.pdf | 14 May 2026 |
| Occupational CertificateFile: OCCUPANCY CERTIFICATE.pdf | 14 May 2026 |
| Form 2A (FY 2025-2026)File: FORM 2A MARCH 2026.pdf | 4 May 2026 |
| Form 2A (FY 2024-2025)File: FORM 2A.pdf | 4 May 2026 |
| Form 1File: FORM-1 MAJESTIC RESIDENCY JUN-2023.pdf | 2 May 2026 |
| Form 2File: FORM-2 MAJESTIC RESIDENCY JUN-2023.pdf | 2 May 2026 |
| Form 3File: FORM-3 MAJESTIC RESIDENCY JUN-2023.pdf | 2 May 2026 |
| Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD JUNE 2023.pdf | 2 May 2026 |
| Form 1File: FORM-1 MAJESTIC RESIDENCY SEP-2023.pdf | 2 May 2026 |
| Form 2File: FORM-2 MAJESTIC RESIDENCY SEP-2023.pdf | 2 May 2026 |
| Form 3File: FORM-3 MAJESTIC RESIDENCY SEP-2023.pdf | 2 May 2026 |
| Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD SEPTEMBER 2023.pdf | 2 May 2026 |
| Form 1File: FORM-1 MAJESTIC RESIDENCY DEC-2023.pdf | 2 May 2026 |
| Form 2File: FORM-2 MAJESTIC RESIDENCY DEC-2023.pdf | 2 May 2026 |
| Form 3File: FORM-3 MAJESTIC RESIDENCY DEC-2023.pdf | 2 May 2026 |
| Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD DECEMBER 2023.pdf | 2 May 2026 |
| Form 1File: FORM-1 MAJESTIC RESIDENCY MAR-2024.pdf | 2 May 2026 |
| Form 2File: FORM-2 MAJESTIC RESIDENCY MAR-2024.pdf | 2 May 2026 |
| Form 3File: FORM-3 MAJESTIC RESIDENCY MAR-2024.pdf | 2 May 2026 |
| Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD MARCH 2024.pdf | 2 May 2026 |
| Form 1File: FORM-1 MAJESTIC RESIDENCY JUN-2024.pdf | 2 May 2026 |
| Form 2File: FORM-2 MAJESTIC RESIDENCY JUN-2024.pdf | 2 May 2026 |
| Form 3File: FORM-3 MAJESTIC RESIDENCY JUN-2024.pdf | 2 May 2026 |
| Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD JUNE 2024.pdf | 2 May 2026 |
| Form 1File: FORM-1 MAJESTIC RESIDENCY SEP-2024.pdf | 2 May 2026 |
| Form 2File: FORM-2 MAJESTIC RESIDENCY SEP-2024.pdf | 2 May 2026 |
| Form 3File: FORM-3 MAJESTIC RESIDENCY SEP-2024.pdf | 2 May 2026 |
| Disclosure of Sold and Booked InventoryFile: SOLD-UNSOLD SEP-2024.pdf | 2 May 2026 |
| Form 1File: FORM-1 MAJESTIC RESIDENCY DECEMBER 2024.pdf | 2 May 2026 |
| Form 2File: FORM-2 MAJESTIC RESIDENCY DEC-2024.pdf | 2 May 2026 |
| Form 3File: FORM-3 MAJESTIC RESIDENCY DEC-2024.pdf | 2 May 2026 |
| Disclosure of Sold and Booked InventoryFile: SOLD-UNSOLD DEC-2024.pdf | 2 May 2026 |
| Form 1File: FORM-1 MAJESTIC RESIDENCY MARCH 2025.pdf | 2 May 2026 |
| Form 2File: FORM-2 MAJESTIC RESIDENCY MAR-2025.pdf | 2 May 2026 |
| Form 3File: FORM-3 MAJESTIC RESIDENCY MAR-2025.pdf | 2 May 2026 |
| Disclosure of Sold and Booked InventoryFile: SOLD-UNSOLD MAR-2025.pdf | 2 May 2026 |
| Withdrawal Update Form 1File: FORM-1 MAJESHTIC RESIDENCY JUN-2025.pdf | 2 May 2026 |
| Withdrawal Update Form 1File: FORM-1 MAJESHTIC RESIDENCY SEP-2025.pdf | 2 May 2026 |
| Withdrawal Update Form 1File: FORM-1 MAJESHTIC RESIDENCY DEC-2025.pdf | 2 May 2026 |
| Withdrawal Update Form 2File: FORM-2 MAJESTIC RESIDENCY JUN-2025.pdf | 2 May 2026 |
| Withdrawal Update Form 2File: FORM-2 MAJESTIC RESIDENCY SEP-2025.pdf | 2 May 2026 |
| Withdrawal Update Form 2File: FORM-2 MAJESTIC RESIDENCY DEC-2025.pdf | 2 May 2026 |
| Withdrawal Update Form 3File: FORM-3 MAJESTIC RESIDENCY JUN-2025.pdf | 2 May 2026 |
| Withdrawal Update Form 3File: FORM-3 MAJESTIC RESIDENCY SEP-2025.pdf | 2 May 2026 |
| Withdrawal Update Form 3File: FORM-3 MAJESTIC RESIDENCY DEC-2025.pdf | 2 May 2026 |
| Form 2A (FY 2023-2024)File: FORM-2A MAJESTIC RESIDENCY MAR-2024.pdf | 2 May 2026 |
| Form 5 (FY 2024-2025)File: FORM-5 SKYLINE INFRA MAR-25.pdf | 2 May 2026 |
| Form 5 (FY 2025-2026)File: FORM-5 SKYLINE INFRA MAR-26.pdf | 2 May 2026 |
| Form 5 (FY 2023-2024)File: FORM-5 MAJESTIC RESIDENCY MAR-2024.pdf | 2 May 2026 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: MR F1.pdf | 21 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: MR F3.pdf | 21 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: MR F2.pdf | 21 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: MR Sold.pdf | 21 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM-1 MAJESTIC RESIDENCY 13-10-2024 (1).pdf | 26 Dec 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM-1 MAJESTIC RESIDENCY 07-07-2024_page-0001.pdf | 17 Aug 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Majestic Residency_Form-2-Engineers Certificate_June-23.pdf | 17 Aug 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Majestic Residency_Form-2-Engineers Certificate_Sep-23.pdf | 17 Aug 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Majestic Residency_Form-2-Engineers Certificate_Dec-23.pdf | 17 Aug 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Majestic Residency_Form-2-Engineers Certificate_Mar-24.pdf | 17 Aug 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Majestic Residency_Form-2-Engineers Certificate_june-24.pdf | 17 Aug 2024 |
| Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD MAJESTIC RESIDENCY.pdf | 17 Aug 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: JUNE-24.pdf | 17 Aug 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Majestic Residency_Form-1- Architect Certificate_June-23.pdf | 14 May 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Majestic Residency_Form-1- Architect Certificate_Sep-23.pdf | 14 May 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Majestic Residency_Form-1- Architect Certificate_Dec-23.pdf | 14 May 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Majestic Residency_Form-1- Architect Certificate_Mar-24.pdf | 14 May 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Majestic Residency_Form-2-Engineers Certificate_June-23.pdf | 14 May 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Majestic Residency_Form-2-Engineers Certificate_Sep-23.pdf | 14 May 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Majestic Residency_Form-2-Engineers Certificate_Dec-23.pdf | 14 May 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Majestic Residency_Form-2-Engineers Certificate_Mar-24.pdf | 14 May 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Majestic Residency_RERA_Form 2A_MAR-24.pdf | 14 May 2024 |
| Disclosure of sold/ booked inventoryFile: June-23.pdf | 14 May 2024 |
| Disclosure of sold/ booked inventoryFile: Sep-23.pdf | 14 May 2024 |
| Disclosure of sold/ booked inventoryFile: Dec-23.pdf | 14 May 2024 |
| Disclosure of sold/ booked inventoryFile: Mar-24.pdf | 14 May 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: JUNE-23.pdf | 14 May 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: SEP-23.pdf | 14 May 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Dec-23.pdf | 14 May 2024 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Wardha
Computed across the 290+ Wardha projects on ReraGenie, from their own filings.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 4 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 121 filed documents as one ZIP, foldered, with a manifest
Keep MAJESTIC RESIDENCY on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near PALAKWADI WARDHA290+ in Wardha
Filed coordinates, straight-line distance. 3 registered projects within 2 km.
Shri Ram Vatika
Krishnagiri Developers
LITTLE EARTH UNIT 11
SANJAY P. MANMODE, GANESH P. ATKAR AND MOH
Shree Sadguru Krushnagiri Nagari
Shree Samarth Infra
DATTADHAM PART 4
HARIBHAU WASUDEORAO WAZURKAR
Mahalaxmi CIty Part-2
Krushna Builders & Developers
ISHWAR NAGAR
Mahesh Batra & 2 Others
See every Wardha project, with the district possession charts
Builder: SKYLINE INFRA
Skyline Infra has 5 registrations on MahaRERA, including Shlok Heritage and MAJESTIC RESIDENCY. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Wardha district page.
Frequently asked questions
What are my rights if MAJESTIC RESIDENCY is delayed beyond 30 Sep 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of MAJESTIC RESIDENCY?
The registered promoter entity is SKYLINE INFRA, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in MAJESTIC RESIDENCY?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for MAJESTIC RESIDENCY?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at MAJESTIC RESIDENCY?
The professionals named in the filing: Architect: SHRENIK KHONDE; Architect: EMANATE DESIGN; Engineer: SAGAR NARAWADIYA; Chartered Accountant: DARSHAN WAKHARIYA; Chartered Accountant: CA ANKIT TALREJA; Chartered Accountant: SUMIT SANTOSH AGRAWAL & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in MAJESTIC RESIDENCY?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback