Home / Browse projects / Bengaluru Urban, Karnataka / MAHINDRA ZEN

Registration approved No litigation declared Residential/Group Housing project

MAHINDRA ZEN

By MAHINDRA LIFESPACE DEVELOPERS LIMITED

RG-KA-19951 · RERA PRM/KA/RERA/1251/310/PR/210324/006712 · Last updated on RERA Karnataka portal: 14 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • 1 complaint at RERA Karnataka

Clear

  • No litigation declared
  • Completion date never moved
  • Separate project account declared
Dec 2028Possession promisedno revision filed
0 of 18Construction stages donefurthest along: Earth work and other leveling..., 95%
1 of 228Units unsoldnot recorded sold or booked
1Complaints at RERA Karnatakaon this registration
Jump to the 167 documents Report an error

MAHINDRA ZEN is a Residential/Group Housing project by MAHINDRA LIFESPACE DEVELOPERS LIMITED in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/310/PR/210324/006712 on 21 Mar 2024. Possession is promised by 31 Dec 2028. 227 of the 228 units on this registration are recorded sold or booked, and 0 of 18 construction stages are filed complete. 1 complaint is on record with the regulator.

At a glance

Project

  • NameMAHINDRA ZEN
  • TypeResidential/Group Housing
  • Location
    • Bengaluru South
    • Bengaluru Urban
    • 560068
  • Pincode560068
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/310/PR/210324/006712
  • ReraGenie IDRG-KA-19951

Builder

  • NameMAHINDRA LIFESPACE DEVELOPERS LIMITED
  • Entity typeCompany
  • CINL45200MH1999PLC118949
  • GSTIN29AAACG8904C1ZR
  • Authorized SignatoryNandan V Mallya
  • Managing Director & Chief Executive OfficerAMIT KUMAR SINHA
  • DirectorsMr. AMEET PRATAPSINH HARIANI, Dr. ANISH DILIP SHAH, Mr. ANUJ PURI, Ms. AMRITA VERMA CHOWDHURY, Ms. ASHA KHARGA, Ms. RUCHA NANVATI, Mr. AMIT KUMAR SINHA
  • Project HeadR. Aswath Prasad
  • Other registrations4 more →
  • Declared earlier projects6 →

Key dates

this monthRegisteredMar 2024PromisedDec 2028

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on21 Mar 2024
  • Promised completion31 Dec 2028
  • Revised completionNone
  • Buildings2 building records
  • Documents filed167 files

Current status

100%227 of 228 units booked
8.8%Of the estimated cost spent so far

Figures as on 14 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
WING A---1260126
WING B---1020102

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 14 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 18 construction stages are filed complete. The stage furthest along is Earth work and other leveling preparation work, at 95%.

Building: 42% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work95%
Foundation footing work82%
Upto Plinth Level35%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)48%
Retaining wall (All types)78%
RCC or MS Framed structure80%
Masonry Construction35%
Plastering inside , outside & Ceiling55%
Joinery: Doors, Windows, Ventilators etc40%
Basic work of Water supply, Sanitary and Electrification32%
Dadoing, Skirting, Flooring, Tiles work (All types)38%
Railing and Grill fixing68%
Electrification, Water supply and Sanitary Finishing0%
Painting0%
Fire prevention and fire fighting fitting and fixture with network10%
Weather Proof work(tile,concrete)52%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work10%
Internal and External work including landscapes as per sanctioned drawings0%

Progress on shared amenities40

As on 14 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes0%
Sewage and Drainage SystemYes0%
Water conservation/rain water harvesting/recharge of ground waterYes0%
Energy managementYes0%
Fire protection and fire safety requirementsYes0%
Solid waste management and disposalYes0%
Emergency Evacuation servicesYes0%
Internal Roads & FootpathsYes0%
Electricity supply transformer and substationYes0%
Storm water drainsYes0%
Use of renewable energyYes0%
Sewage Treatment Plant (STP)Yes20%
Parks & Tree plantingYes0%
Street LightingYes0%
ElectricityYes0%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes0%
Club HouseYes0%
Community HallYes0%
Outdoor Sports facilityYes0%
Indoor Sports facilityYes0%
Swimming PoolYes0%
GymYes0%
ParksYes0%
Power BackupYes0%
Piped GasYes0%
Water and SanitationYes0%
Air ConditioningNoNot applicable
StaircasesYes56%
LiftsYes0%
Corridor/LobbiesYes45%
Fire escapesYes0%
Common entrance and exit for the building/common portico/foyer/verandahYes0%
BasementYes68%
TerraceYes0%
Outer WallYes0%
Open parking areasYes0%
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyYes0%
Common storage spacesNoNot applicable

Land and ownership2

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area17,199 sq m
Named landowners2
LandownerVillageDistrict
Mahindra Lifespace Developers Limited--
Mahindra Lifespace Developers Limited--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 205.66 cr
Cost incurredRs 18.10 cr
Spent of the estimate8.8%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 176.46 crRs 15.80 cr
On-site expenditure-Consultants FeesRs 20.39 cr-
Principal sum and interest payable to financial institutions-Scheduled BanksRs 8.80 cr-
On-site expenditure-Site Overhead-Rs 2.23 cr
Payment of taxes-Rs 7.39 lakh

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAnup Naik
EngineerVishnu Kumar
Chartered AccountantVINAY TYAGARAJ

Complaints filed with RERA Karnataka1

Case no.ComplainantRespondentFiled
00255/2026-MAHINDRA LIFESPACE DEVELOPERS LIMITED12/03/2026

Documents filed167

As listed on the registration, under the names the promoter filed them with; the newest 80 of 167 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/310/PR/210324/006712 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form 4 CA Certificate QU Sep 26.pdf14 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Form 5 Architect Certificate QU Sep 26.pdf14 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form 6 Engineer Certificate QU Sep 26.pdf14 Oct 2026
Q2 2026-27 Water supply and sewage board14 Oct 2026
Q2 2026-27 KSPCB- PCB (10 Acres to 125 Acres)14 Oct 2026
Q2 2026-27 KSPCB- MOEF (Above 50 Acres)14 Oct 2026
Q2 2026-27 KPTCL- BESCOM14 Oct 2026
Q2 2026-27 Fire and Safety14 Oct 2026
Q2 2026-27 Airport Authority of India14 Oct 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form 4 CA Certificate QU June 26.pdf13 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Form 5 Architect Certificate QU June 26.pdf13 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form 6 Engineer Certificate QU June 26.pdf13 Jul 2026
Q1 2026-27 Water supply and sewage board13 Jul 2026
Q1 2026-27 KSPCB- PCB (10 Acres to 125 Acres)13 Jul 2026
Q1 2026-27 KSPCB- MOEF (Above 50 Acres)13 Jul 2026
Q1 2026-27 KPTCL- BESCOM13 Jul 2026
Q1 2026-27 Fire and Safety13 Jul 2026
Q1 2026-27 Airport Authority of India13 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form 4 CA Certificate QU March 26.pdf13 Apr 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Form 5 Architect Certificate QU March 26.pdf13 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form 6 Engineer Certificate QU March 26.pdf13 Apr 2026
Q4 2025-26 Water supply and sewage board13 Apr 2026
Q4 2025-26 KSPCB- PCB (10 Acres to 125 Acres)13 Apr 2026
Q4 2025-26 KSPCB- MOEF (Above 50 Acres)13 Apr 2026
Q4 2025-26 KPTCL- BESCOM13 Apr 2026
Q4 2025-26 Fire and Safety13 Apr 2026
Q4 2025-26 Airport Authority of India13 Apr 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form 4 CA Certificate QU Dec 25.pdf13 Jan 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Form 5 Architect Certificate QU Dec 25.pdf13 Jan 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form 6 Engineer Certificate QU Dec 25.pdf13 Jan 2026
Q3 2025-26 Water supply and sewage board13 Jan 2026
Q3 2025-26 KSPCB- PCB (10 Acres to 125 Acres)13 Jan 2026
Q3 2025-26 KSPCB- MOEF (Above 50 Acres)13 Jan 2026
Q3 2025-26 KPTCL- BESCOM13 Jan 2026
Q3 2025-26 Fire and Safety13 Jan 2026
Q3 2025-26 Airport Authority of India13 Jan 2026
Hissa TippaniFile: 2 Hissa Tippani.pdf14 Mar 2024
Village MapFile: Village Map.pdf14 Mar 2024
Form 1 CA CertificateFile: 1 Form 1 CA Certificate.pdf5 Mar 2024
Sale Deed to MLDLFile: 2 Sale Deed to MLDL.pdf5 Mar 2024
Khatha Sy No 65 and 116 2File: 2 Khatha Sy No 65 and 116 2.pdf5 Mar 2024
Unit Wise Carpet AreaFile: 4 Unit Wise Carpet Area.pdf5 Mar 2024
6&7 Single plot declarationFile: 6&7 Single plot declaration.pdf5 Mar 2024
Carpet Area calculationFile: 8 Carpet Area calculation.pdf5 Mar 2024
Village MapFile: 9 Village Map.pdf5 Mar 2024
Commencement Certificate DeclarationFile: 10 Commencement Certificate Declaration.pdf5 Mar 2024
Building LicenseFile: 11 Building License.pdf5 Mar 2024
Site PlanFile: 12 Site Plan.pdf5 Mar 2024
Basement Floor PlanFile: 12 Basement Floor Plan.pdf5 Mar 2024
Ground Floor PlanFile: 12 Ground Floor Plan.pdf5 Mar 2024
First Floor PlanFile: 12 First Floor Plan.pdf5 Mar 2024
Second Floor PlanFile: 12 Second Floor Plan.pdf5 Mar 2024
Third Floor PlanFile: 12 Third Floor Plan.pdf5 Mar 2024
Typical Floor Plan (4th to 18th and 20th to 25th)File: 12 Typical Floor Plan (4th to 18th and 20th to 25th).pdf5 Mar 2024
19th Floor PlanFile: 12 19th Floor Plan.pdf5 Mar 2024
Terrace Floor PlanFile: 12 Terrace Floor Plan.pdf5 Mar 2024
Elevation and Club House SectionFile: 12 Elevation and Club House Section.pdf5 Mar 2024
Wing A Section DrawingFile: 12 Wing A Section Drawing.pdf5 Mar 2024
Wing B SectionFile: 12 Wing B Section.pdf5 Mar 2024
ElevationsFile: 12 Elevations.pdf5 Mar 2024
Proforma for Agreement for SaleFile: 16 Proforma for Agreement for Sale.pdf5 Mar 2024
Form B AffidavitFile: Form B Affidavit.pdf5 Mar 2024
Proforma of Allotment LetterFile: Proforma of Allotment Letter.pdf5 Mar 2024
Source of Fund with supporting documentsFile: 2 Source of Fund.pdf17 Nov 2023
Q2 FY23-24 Audited Financials-File: 2 Q2 FY23-24 Audited Financials-.pdf17 Nov 2023
Sale Deed to MLDLFile: 3 Sale Deed to MLDL.pdf17 Nov 2023
EC Sy No 65 and 116 2File: 3 EC Sy No 65 and 116 2.pdf17 Nov 2023
Unit Wise Carpet AreaFile: 9 Unit Wise Carpet Area.pdf17 Nov 2023
Akarbandh Sy No 65 and Sy No 116File: 10 Akarbandh Sy No 65 and Sy No 116.pdf17 Nov 2023
Allotment LetterFile: 17 Allotment Letter.pdf17 Nov 2023
Agreement of SaleFile: 18 Agreement of Sale.pdf17 Nov 2023
Balance Sheet Q1 2023-24File: 2 Balance Sheet Q1 2023-24.pdf28 Oct 2023
Source of FundFile: 2 Source of Fund.pdf28 Oct 2023
MR 1 1994-95File: 3 MR 1 1994-95.pdf28 Oct 2023
MR 17 Non Availablity EndorsementFile: 3 MR 17 Non Availablity Endorsement.pdf28 Oct 2023
MR 40 1982-83File: 3 MR 40 1982-83.pdf28 Oct 2023
MR No 4 Sy No 65File: 3 MR No 4 Sy No 65.pdf28 Oct 2023
MR No 4 Sy No 116 2File: 3 MR No 4 Sy No 116 2.pdf28 Oct 2023
Original conversion order dated 29 07 1997File: 4 Original conversion order dated 29 07 1997.pdf28 Oct 2023
Carpet Area CalculationFile: 10 Carpet Area Calculation.pdf28 Oct 2023

Promoter's earlier projects2

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

2 under way, not due yet
ProjectLocationStatusPromisedDelivered
Mahindra Eden Phase-2Mahindra Eden Sy. No. 49 & 50/2, Holiday Village Road, Vajarahalli Village, Kanakapura Road, Bengaluru: 560062.OngoingJul 2027Not due yet
Mahindra Eden Phase-1Mahindra Eden Sy. No. 49 & 50/2, Holiday Village Road, Vajarahalli Village, Kanakapura Road, Bengaluru: 560062.OngoingMar 2027Not due yet

How this compares with Bengaluru Urban

100%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep MAHINDRA ZEN on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmMAHINDRA ZENOther 22Dot size: filed unitsN

Filed coordinates, straight-line distance. 22 registered projects within 2 km.

Builder: MAHINDRA LIFESPACE DEVELOPERS LIMITED

MAHINDRA LIFESPACE DEVELOPERS LIMITED has 5 registrations on RERA Karnataka, including MAHINDRA EDEN PHASE-2 and MAHINDRA NEWHAVEN. Its filings declare 6 earlier projects, none of them declared completed. Litigation is declared on 2 of its registrations. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if MAHINDRA ZEN is delayed beyond 31 Dec 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of MAHINDRA ZEN?

The registered promoter entity is MAHINDRA LIFESPACE DEVELOPERS LIMITED, a company as per the filing. Its CIN L45200MH1999PLC118949 and GSTIN 29AAACG8904C1ZR can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in MAHINDRA ZEN?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against MAHINDRA ZEN?

Each case number above is a complaint filed with RERA Karnataka. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

Who certifies construction progress at MAHINDRA ZEN?

The professionals named in the filing: Architect: Anup Naik; Engineer: Vishnu Kumar; Chartered Accountant: VINAY TYAGARAJ. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in MAHINDRA ZEN?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About MAHINDRA ZEN. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save MAHINDRA ZEN to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.