Home / Browse projects / Palghar, Maharashtra / Mahavir Tirth
Mahavir Tirth
RG-MH-62796 · RERA PR1240002601570 · Last updated on MahaRERA portal: 5 May 2026
Source: official MahaRERA filing
Red flags
- Allotment letter deviates from the model form
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- No encumbrance on the project land
- Separate project account declared
- All 1 earlier projects delivered on promise
Buyer report
Built from this project's filings on the day you order, in plain language.
- 1 condition on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 7 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 3 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Mahavir Tirth is a Residential / Group Housing project by RAJESH CONSTRUCTION in Palghar, Maharashtra, registered with MahaRERA as PR1240002601570 on 18 Aug 2026. Possession is promised by 31 Dec 2032.
At a glance
Project
- NameMahavir Tirth
- TypeResidential / Group Housing
- Location
- Tarapur Road
- Pasthal
- Palghar
- 401504
- Pincode401504
- MapView location on Google Maps (as filed on RERA)
- RERA no.PR1240002601570
- ReraGenie IDRG-MH-62796
Builder
- NameRAJESH CONSTRUCTION
- Entity typePartnership
- GSTIN27AAMFR7747R1Z0
- Track record11 past projects →
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on18 Aug 2026
- Promised completion31 Dec 2032
- Revised completionNone
- Buildings12 building records
- Documents filed3 files
Current status
Figures as on 5 May 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Mahavir Tirth Bungalow No 1 | NA | 3 | 3 | 1 | 0 | 1 |
| Mahavir Tirth Bungalow No 2 | NA | 3 | 3 | 1 | 0 | 1 |
| Mahavir Tirth Bungalow No 3 | NA | 3 | 3 | 1 | 0 | 1 |
| Mahavir Tirth Bungalow No 4 | NA | 3 | 3 | 1 | 0 | 1 |
| Mahavir Tirth Bungalow No 5 | NA | 3 | 3 | 1 | 0 | 1 |
| Mahavir Tirth Bungalow No 6 | NA | 3 | 3 | 1 | 0 | 1 |
| Mahavir Tirth Bungalow No 7 | NA | 3 | 3 | 1 | 0 | 1 |
| Mahavir Tirth Bungalow No 8 | NA | 3 | 3 | 1 | 0 | 1 |
| Mahavir Tirth Bungalow No 9 | NA | 3 | 3 | 1 | 0 | 1 |
| Mahavir Tirth Bungalow No 10 | NA | 3 | 3 | 1 | 0 | 1 |
| Mahavir Tirth Bungalow No 11 | NA | 3 | 3 | 1 | 0 | 1 |
| Mahavir Tirth Bungalow No 12 | NA | 3 | 3 | 1 | 0 | 1 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building12
As on 5 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing.
Mahavir Tirth Bungalow No 10%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | Not applicable |
| Podiums (if any) | Not applicable |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Mahavir Tirth Bungalow No 20%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | Not applicable |
| Podiums (if any) | Not applicable |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Mahavir Tirth Bungalow No 30%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | Not applicable |
| Podiums (if any) | Not applicable |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Mahavir Tirth Bungalow No 40%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | Not applicable |
| Podiums (if any) | Not applicable |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Mahavir Tirth Bungalow No 50%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | Not applicable |
| Podiums (if any) | Not applicable |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Mahavir Tirth Bungalow No 60%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | Not applicable |
| Podiums (if any) | Not applicable |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Mahavir Tirth Bungalow No 70%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | Not applicable |
| Podiums (if any) | Not applicable |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Mahavir Tirth Bungalow No 80%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | Not applicable |
| Podiums (if any) | Not applicable |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Mahavir Tirth Bungalow No 90%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | Not applicable |
| Podiums (if any) | Not applicable |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Mahavir Tirth Bungalow No 100%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | Not applicable |
| Podiums (if any) | Not applicable |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Mahavir Tirth Bungalow No 110%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | Not applicable |
| Podiums (if any) | Not applicable |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Mahavir Tirth Bungalow No 120%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | Not applicable |
| Podiums (if any) | Not applicable |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 5 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | 0% |
| Water Supply | No | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | No | 0% |
| Storm Water Drains | No | 0% |
| Landscaping & Tree Planting | No | Not applicable |
| Street Lighting | No | 100% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | No | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | No | 100% |
| Aggregate area of recreational Open Space | No | 100% |
| Open Parking | No | Not applicable |
Parking filed12
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Stilt / Ground | Total |
|---|---|---|
| Mahavir Tirth Bungalow No 1 | 1 | 1 |
| Mahavir Tirth Bungalow No 2 | 1 | 1 |
| Mahavir Tirth Bungalow No 3 | 1 | 1 |
| Mahavir Tirth Bungalow No 4 | 1 | 1 |
| Mahavir Tirth Bungalow No 5 | 1 | 1 |
| Mahavir Tirth Bungalow No 6 | 1 | 1 |
| Mahavir Tirth Bungalow No 7 | 1 | 1 |
| Mahavir Tirth Bungalow No 8 | 1 | 1 |
| Mahavir Tirth Bungalow No 9 | 1 | 1 |
| Mahavir Tirth Bungalow No 10 | 1 | 1 |
| Mahavir Tirth Bungalow No 11 | 1 | 1 |
| Mahavir Tirth Bungalow No 12 | 1 | 1 |
Land and ownership4
MahaRERA does not publish landowner contact details.
| Landowner | Village | District |
|---|---|---|
| Shail Rajesh Mehta | Vileparle | Mumbai Suburban |
| Nisha Rajesh Mehta | Vileparle | Mumbai Suburban |
| Sonal Manoj Mehta | Vileparle | Mumbai Suburban |
| Vandana Lopesh Vasa | - | Mumbai Suburban |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA.
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Vastushilp Associates |
| Engineer | Darsh Consult |
| Chartered Accountant | C D Chauhan & Co |
| Partner | Role in project |
|---|---|
| RAJESH CONSTRUCTION | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
Documents filed3
As listed on the registration. The files themselves are on the MahaRERA portal.
| Document | Uploaded |
|---|---|
| ANNEXURE A | 5 May 2026 |
| approval plans | 30 Apr 2026 |
| NA Order | 30 Apr 2026 |
Promoter's earlier projects1
As disclosed by the promoter in this filing.
| Project | Status | Promised | Delivered | Litigation |
|---|---|---|---|---|
| MAHAVIR NEYTRA | Completed | Dec 2027 | Mar 2025 | No |
How this compares with Palghar
Computed across the 3,200 Palghar projects on ReraGenie, from their own filings.
Track Mahavir Tirth
Save this project to your account and get an email when its filing changes: status, dates, complaints, new documents. Free during the pilot beta.
Other projects near Pasthal3,200 in Palghar
DREAM CITY
VISHAL DILIP SANKHE HUF
BALAJI COMPLEX PHASE-2
B R HOUSING
RAMSETU
SATVIK BUILDERS & DEVELOPERS
MAHAVIR NEYTRA
RAJESH CONSTRUCTION
VAISHNAVI RESIDENCY
Vaishnavi Developers
MAHAVIR VIHAR BUILDING NO 4 TYPE E
RAJESH CONSTRUCTION
See every Palghar project, with the district possession charts
Builder: RAJESH CONSTRUCTION
Rajesh Construction has 8 registrations on MahaRERA, including Mahavir Krupa D and MAHAVIR UTSAV B. Its filings disclose 11 earlier MahaRERA projects: 4 of 11 past projects completed on time. Read the full track record. See more projects on the Palghar district page.
Frequently asked questions
What are my rights if Mahavir Tirth is delayed beyond 31 Dec 2032?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Mahavir Tirth?
The registered promoter entity is RAJESH CONSTRUCTION, a partnership as per the filing. Its GSTIN 27AAMFR7747R1Z0 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Mahavir Tirth?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Mahavir Tirth?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Mahavir Tirth?
The professionals named in the filing: Architect: Vastushilp Associates; Engineer: Darsh Consult; Chartered Accountant: C D Chauhan & Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Mahavir Tirth?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.