Rajesh Construction: RERA track record
GSTIN 27AAMFR7747R1Z0 · Partnership · attribution by exact filing name, entity resolution in progress
Rajesh Construction has 8 registrations on MahaRERA, including Mahavir Krupa D and MAHAVIR UTSAV B. Its filings disclose 11 earlier MahaRERA projects: declares 4 of 11 past projects completed on time.
Projects by this developer
Showing all 8 projects.
Largest first, by the unit count in the filing.
| Project | Location | Units | Booked | Registered | Status |
|---|---|---|---|---|---|
| MAHAVIR NEYTRAP99000048189 | Pasthal, Palghar, 401504 | 29 | 0% | 15 Dec 2022 | Completed |
| MAHAVIR VIHAR BUILDING NO 4 TYPE EP99000049657 | Pasthal, Palghar, 401504 | 14 | 100% | 22 Feb 2023 | Registered |
| Mahavir TirthPR1240002601570 | Pasthal, Palghar, 401504 | 12 | 0% | 18 Aug 2026 | Registered |
| Mahavir Krupa DP99000000244 | pasthal, Palghar, 401501 | - | - | 10 Jul 2017 | Completed |
| MAHAVIR KUTIRP99000046061 | Pasthal, Palghar, 401504 | - | - | 15 Jun 2022 | Completed |
| MAHAVIR SADAN AP99000021076 | Pasthal, Palghar, 401504 | - | - | 31 May 2019 | Completed |
| MAHAVIR SADAN BP99000028787 | Pasthal, Palghar, 401504 | - | - | 30 Mar 2021 | Completed |
| MAHAVIR UTSAV BP99000015701 | Mahavir Residency, Palghar, 401506 | - | - | 16 Mar 2018 | Completed |
What this promoter declares as its own experience
Rajesh Construction declares experience on 11 earlier projects. 2 of them carry a registration number we could match on MahaRERA, all under this promoter's own name.
2 of these declarations can be compared with the dates those projects' own registrations hold. Every one of them gives the same original completion date its registration holds.
From the promoter experience table each promoter files with MahaRERA, matched to the register by registration number. A declaration naming another promoter's project is a claim of involvement, and involvement takes several shapes: a parent and its project company, one firm re-registering under a second name, or a joint venture between two separate developers. We publish the claim as filed and do not treat it as proof that the entities are one builder.
Past projects, as disclosed in RERA filings
| Project | Promised completion | Actual completion | Delivery |
|---|---|---|---|
| Mahavir Virat A | 31 Jan 2011 | 25 Jun 2011 | +5 months |
| Mahavir Virat BCD | 31 Mar 2011 | 25 Jul 2011 | +4 months |
| Mahavir Virat E | 31 May 2011 | 16 Aug 2011 | +3 months |
| Mahavir Krupa A | 31 Oct 2013 | 25 Sep 2014 | +11 months |
| Mahavir Krupa B | 31 Oct 2013 | 25 Sep 2014 | +11 months |
| Mahavir Business Centre 2 | 31 May 2017 | 28 May 2017 | On time |
| Mahavir Utsav A | 31 May 2017 | 20 Jun 2017 | +1 months |
| Mahavir Krupa C | 31 Oct 2017 | 25 Sep 2014 | On time |
| MAHAVIR SADAN A P99000021076 | 30 Jun 2021 | 2 Aug 2021 | +1 months |
| MAHAVIR SADAN B p99000028787 | 30 Dec 2023 | 2 Jan 2023 | On time |
| MAHAVIR NEYTRA P99000048189 | 31 Dec 2027 | 4 Mar 2025 | On time |
Frequently asked questions
How do I verify Rajesh Construction as a legal entity before signing?
Your agreement for sale must name the exact entity registered for the project, not a group brand. Cross-check its GSTIN 27AAMFR7747R1Z0 on the MCA and GST portals before signing anything. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.
How should I use this delivery record when booking with Rajesh Construction?
Add the median slip shown above to any possession date this promoter quotes you, and plan your rent, loan and school-year decisions around that stressed date. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.
The record above looks clean. What should I still check?
A clean filing history is a good sign, not a guarantee. Filings only show what promoters must disclose: they do not show build quality, the state of approvals still pending, or whether the agreement they offer follows MahaRERA's model clauses. Check the specific project's certificates and agreement deviations, and confirm sales pace is matched by construction pace quarter on quarter.