MADAN RATAN CITY
By EMAAR DEVELOPERS & BUILDERS PVT LTD
RG-MH-00821 · RERA P50500001473 · Last updated on MahaRERA portal: 7 May 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Completion date moved by 66 months
- 3 extensions taken
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
- All 2 earlier projects delivered on promise
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Nagpur registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
MADAN RATAN CITY is a Others project by EMAAR DEVELOPERS & BUILDERS PVT LTD in Nagpur, Maharashtra, registered with MahaRERA as P50500001473 on 28 Jul 2017. Possession is promised by 31 Dec 2026. The completion date has moved by 66 months from the original filing. 0 of the 48 units on this registration are recorded sold or booked, and 28 of 77 construction stages are filed complete.
At a glance
Project
- NameMADAN RATAN CITY
- TypeOthers
- Location
- MOUZA CHIKHALI KHURD
- Nagpur (M Corp.)
- Nagpur (Urban)
- Nagpur
- 440032
- Pincode440032
- MapView location on Google Maps (as filed on RERA)
- RERA no.P50500001473
- ReraGenie IDRG-MH-00821
Builder
- NameEMAAR DEVELOPERS & BUILDERS PVT LTD
- Entity typeCompany
- Managing DirectorMADAN BALAJI RATAN
- Declared earlier projects2 →
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on28 Jul 2017
- Promised completion31 Dec 2026
- Revised completionRevised to 31 Dec 2026 (originally 30 Jun 2021)
- Buildings7 building records
- Documents filed176 files
Current status
Figures as on 7 May 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| AMARO APARTMENT G-6 | NA | 8 | 0 | 0 | 0 | 0 |
| AMARO APARTMENT 7TH FLOOR | NA | 1 | 0 | 0 | 0 | 0 |
| AMBER G-6 FLOOR | NA | 7 | 0 | 48 | 0 | 48 |
| ADEN VILLA-1 | NA | 2 | 0 | 0 | 0 | 0 |
| ADEN VILLA-2 | NA | 3 | 0 | 0 | 0 | 0 |
| ADEN VILLA-3 | NA | 2 | 0 | 0 | 0 | 0 |
| AMBER 7TH FLOOR | NA | 1 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building7
As on 7 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
28 of 77 construction stages are filed complete across 7 buildings. The stage furthest along is Sanitary Fittings within the flats / premises, at 95%.
AMARO APARTMENT G-673%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 75% |
| Sanitary Fittings within the flats / premises | 55% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 70% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 50% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 50% |
AMARO APARTMENT 7TH FLOOR0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
AMBER G-6 FLOOR83%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 85% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 85% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 85% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 55% |
ADEN VILLA-178%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 95% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 95% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 95% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 75% |
ADEN VILLA-274%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 90% |
| Sanitary Fittings within the flats / premises | 85% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 80% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 80% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 75% |
ADEN VILLA-380%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 75% |
AMBER 7TH FLOOR0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities16
As on 7 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 85% |
| Water Supply | Yes | 25% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 50% |
| Storm Water Drains | Yes | 50% |
| Landscaping & Tree Planting | Yes | 70% |
| Street Lighting | Yes | 55% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 25% |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 25% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 55% |
| Electrical meter room, sub-station, receiving station | Yes | 35% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | Yes | 0% |
| Entrance Gate and Security Cabin | Yes | 85% |
Parking filed106
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Open Space | Total |
|---|---|---|---|
| AMARO APARTMENT G-6 | 51 | 0 | 51 |
| AMARO APARTMENT 7TH FLOOR | 0 | 8 | 8 |
| AMBER G-6 FLOOR | 1 | 0 | 1 |
| ADEN VILLA-1 | 9 | 0 | 9 |
| ADEN VILLA-2 | 8 | 0 | 8 |
| ADEN VILLA-3 | 9 | 0 | 9 |
| AMBER 7TH FLOOR | 0 | 20 | 20 |
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners7
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | AR ADITYA INDURKAR |
| Engineer | ER MUQSIT AHMED SHAIKH |
| Engineer | AAJ ENGINEERS & CONSULTANTS PVT LTD |
| Engineer | ER ARUN UTTARWAR |
| Chartered Accountant | Khanzode & Shenwai Chartered Accountants |
| Chartered Accountant | A M DABKE & ASSOCIATES |
| Chartered Accountant | RAKESH THAKRE & CO |
| Partner | Role in project |
|---|---|
| EMAAR DEVELOPERS & BUILDERS PVT LTD | - |
Extensions applied for3
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterDUE TO PENDAMIC THERE WAS COMPLETE LOCK DOWN IN 2020,WHICH WAS SLOWLY LIFTED FROM JUNE TO AUGUST 2020. MIGRANT LABOURERS RETURNED TO WORK ONLY AFTER DIWALI 2020.CONSTRUCTION ACTIVITY RESUMED IN NOVEMBER 2020.AGAIN IN MARCH 2021 A LOCK DOWN WAS IMPOSED IN MAHARASHTRA WHICH IS STILL CONTIUNING TILL DATE .CONSTRUCTION ACTIVITY CAN NOT BE STARTED FOR NON AVAILABILITY OF LABOUR AND MATERIAL. UNDER THE CIRCUMSTANCES WE REQUEST YOU TO EXTEND THE COMPLETION DATE TO 30/06/2022.LETTER TO THE EFFECT IS ENCLOSED.
Reason as filed by the promoterThe housing project is on Land admeasuring 18200 sq. mts. The permissible builtup area is 21090 sq. mts Sanctioned FSI is 14317 sq. mts. Since the permissible built up area is more than 20000 sq. mts promoters are required to construct and hand over 54 1BHK apartments to MHADA for LIG category people. The project was initially delayed due to introduction of GST as there was confusion among customers because of GST impact and booking suffered on this account. After that due to demonetization of high value currency notes booking was further impacted and construction was delayed. After these issu
Reason as filed by the promoterDELAY IN GETTING REVISED SANCTIONED MAP AND STP WORK AND ENVIRONMENTAL CLEARANCE IS PENDING DUE TO THE NECESSARY APPROVALS FROM THE COMPETENT AUTHORITIES OF THE STATE GOVERNMENT AS THE NEW STATE GOVERNMENT IS YET TO BE FORMED IN MAHARASHTRA. CPM PERT AND JUSTIFICATION FOR DELAY IN WORK ATTACHED HEREWITH ALONG WITH OTHER DOCUMENTS INCLUDING QUARTERLY PROGRESS FORMS
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 24 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 24 Jul 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 24 Jul 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 24 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Dec 2026
Documents filed176
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 176 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 1File: Form 1 Architech Certificate Q4 FY 25-26.pdf | 7 May 2026 |
| Form 2File: Form 2 Engineer Certificate Q4 FY 25-26.pdf | 7 May 2026 |
| Form 3File: Form 3 CA Certificate Q4 FY 25-26.pdf | 7 May 2026 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of sold unsold inventory.pdf | 7 May 2026 |
| Self-declaration of Quarterly ProgressFile: Self Declaration.pdf | 7 May 2026 |
| Form 1File: Form 1 Q3 FY 25-26.pdf | 20 Jan 2026 |
| Form 2File: Form 2 Q3 FY 25-26.pdf | 20 Jan 2026 |
| Form 3File: Form3 Q3 FY 25-26.pdf | 20 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: Sold - unsold.pdf | 20 Jan 2026 |
| Self-declaration of Quarterly ProgressFile: Self Declaration.pdf | 20 Jan 2026 |
| Form 1File: Form 1 Q2 FY 25-26.pdf | 12 Oct 2025 |
| Form 2File: Form 2 Q2 FY 25-26.pdf | 12 Oct 2025 |
| Form 3File: Form 3 Q2 FY 25-26.pdf | 12 Oct 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold Q2 FY 25-26.pdf | 12 Oct 2025 |
| Self-declaration of Quarterly ProgressFile: Self Declaration.pdf | 12 Oct 2025 |
| Form 2A (FY 2024-2025)File: FORM-2A.pdf | 29 Sep 2025 |
| Form 5 (FY 2024-2025)File: Emaar Form 5.pdf | 27 Sep 2025 |
| Form 1File: Form 1.pdf | 20 Jul 2025 |
| Form 2File: Form 2.pdf | 20 Jul 2025 |
| Form 3File: Form 3 Q1 FY 25-26.pdf | 20 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of sold and Unsold Inventory.pdf | 20 Jul 2025 |
| Self-declaration of Quarterly ProgressFile: Self Declaration.pdf | 20 Jul 2025 |
| Form 1File: FORM 1 Architect Certificate 30624.pdf | 3 Jun 2025 |
| Form 2File: FORM 2 Engineer Certificate30624.pdf | 3 Jun 2025 |
| Form 3File: Form 3 Q1 FY 24-25.pdf | 3 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold 30-06-24.pdf | 3 Jun 2025 |
| Form 1File: Form1 Architect Certificate 30924.pdf | 3 Jun 2025 |
| Form 2File: Form 2 Engineer Certificate 30924.pdf | 3 Jun 2025 |
| Form 3File: Form 3 Q2 FY 24-25.pdf | 3 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold 30-09-24.pdf | 3 Jun 2025 |
| Form 1File: Form 1 Architects Certificate.pdf | 3 Jun 2025 |
| Form 2File: Form 2 Engineers Certificate.pdf | 3 Jun 2025 |
| Form 3File: Form 3 CA Certificate Q3 FY 24-25.pdf | 3 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of sold-booked inventory.pdf | 3 Jun 2025 |
| Form 1File: Emaar Form 1.pdf | 3 Jun 2025 |
| Form 2File: Emaar Form 2.pdf | 3 Jun 2025 |
| Form 3File: FORM-3_compressed.pdf | 3 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of Sold Unsold 31032025.pdf | 3 Jun 2025 |
| Form 1File: Form 1 30-06-2023.pdf | 3 Jun 2025 |
| Form 2File: Form 2 30-06-2023.pdf | 3 Jun 2025 |
| Form 3File: Form 3 30-06-2023.pdf | 3 Jun 2025 |
| Form 1File: Form 1 30-09-2023.pdf | 3 Jun 2025 |
| Form 2File: Form 2 30-09-2023.pdf | 3 Jun 2025 |
| Form 3File: Form 3 30-09-2023.pdf | 3 Jun 2025 |
| Form 1File: Form 1 31-12-2023.pdf | 3 Jun 2025 |
| Form 2File: Form 2 31-12-2023.pdf | 3 Jun 2025 |
| Form 3File: Form 3 31-12-2023.pdf | 3 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of Sold- Booked Inventory.pdf | 3 Jun 2025 |
| Form 1File: Form 1 31-03-24.pdf | 3 Jun 2025 |
| Form 2File: Form 2 31-03-24.pdf | 3 Jun 2025 |
| Form 3File: FORM 3 31-03-2024.pdf | 3 Jun 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architects Certificate.pdf | 10 Feb 2025 |
| Certificates of CA (Form 3)File: Form 3 CA Certificate Q3 FY 24-25.pdf | 10 Feb 2025 |
| Certificates of CA (Form 5)File: Form 5.pdf | 10 Feb 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engineers Certificate.pdf | 10 Feb 2025 |
| Disclosure of sold/ booked inventoryFile: Disclosure of sold-booked inventory.pdf | 10 Feb 2025 |
| Other - TechnicalFile: CPM PERT.pdf | 1 Feb 2025 |
| Other - TechnicalFile: Justification for Extension.pdf | 1 Feb 2025 |
| Other - TechnicalFile: Mada Letter.pdf | 1 Feb 2025 |
| Other - TechnicalFile: Map Revision Application.pdf | 1 Feb 2025 |
| Other - TechnicalFile: MHDA Indemnity bond.pdf | 1 Feb 2025 |
| Declaration in FORM BFile: Form B Emaar project Extensioncompressed.pdf | 11 Dec 2024 |
| Declaration in FORM BFile: Form B Emaar _compressed.pdf | 2 Dec 2024 |
| Declaration in FORM BFile: Form B Emaar _compressed.pdf | 2 Dec 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect Certificate.pdf | 2 Dec 2024 |
| Certificates of CA (Form 3)File: Form 3_compressed.pdf | 2 Dec 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engineers Certificate.pdf | 2 Dec 2024 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold 30-06-24.pdf | 25 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold 30-09-24.pdf | 25 Oct 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 Architect Certificate 30624.pdf | 23 Oct 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form1 Architect Certificate 30924.pdf | 23 Oct 2024 |
| Certificates of CA (Form 3)File: Form 3 Q1 FY 24-25.pdf | 23 Oct 2024 |
| Certificates of CA (Form 3)File: Form 3 Q2 FY 24-25.pdf | 23 Oct 2024 |
| Certificates of CA (Form 5)File: Form 5 23-24.pdf | 23 Oct 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engineer Certificate 30924.pdf | 23 Oct 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 Engineer Certificate30624.pdf | 23 Oct 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A 23-24.pdf | 23 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 23-24.pdf | 23 Oct 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 31-03-24.pdf | 6 Jun 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 31-03-24.pdf | 6 Jun 2024 |
Promoter's earlier projects2
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| RATAN GOVERDHAN PLAZA | HOUSE NO 551 & 369 C GAWALIPURA MAHAL NAGPUR 440032 | 52 | Completed | Jun 2016 | May 2016 |
| RATAN HEIGHT | 477 MEDICAL CHOWK NAGPUR 440009 | 65 | Completed | Dec 2014 | Nov 2014 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Nagpur
Computed across the 2,800+ Nagpur projects on ReraGenie, from their own filings.
Free monthly report: Nagpur on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 176 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep MADAN RATAN CITY on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Nagpur (M Corp.)2,800+ in Nagpur
Filed coordinates, straight-line distance. 39 registered projects within 2 km.
Anant Residency
Ajay Anantrao Bhure
Royal Heritage
Shriniwasa Developers
RADHA-RAMAN SAHANIWAS
RADHIKA RAMAN SENAD
BALASAHEB DEORAS SAHANIWAS PHASE 2
PRAKASH NARAYANRAO RAOLE
Bhosle Enclave Chitra Tej Apartment
Ruby Infrastructure Company
NATRAJ TOWER
MEGHA RAJESH TOMAR
See every Nagpur project, with the district possession charts
Builder: EMAAR DEVELOPERS & BUILDERS PVT LTD
EMAAR DEVELOPERS & BUILDERS PVT LTD has 1 registration on MahaRERA, including MADAN RATAN CITY. Its filings disclose 2 earlier MahaRERA projects: declares 2 of 2 past projects completed on time. Read the full track record. See more projects on the Nagpur district page.
Frequently asked questions
What are my rights if MADAN RATAN CITY is delayed beyond 31 Dec 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of MADAN RATAN CITY?
The registered promoter entity is EMAAR DEVELOPERS & BUILDERS PVT LTD, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in MADAN RATAN CITY?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for MADAN RATAN CITY?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at MADAN RATAN CITY?
The professionals named in the filing: Architect: AR ADITYA INDURKAR; Engineer: ER MUQSIT AHMED SHAIKH; Engineer: AAJ ENGINEERS & CONSULTANTS PVT LTD; Engineer: ER ARUN UTTARWAR; Chartered Accountant: Khanzode & Shenwai Chartered Accountants; Chartered Accountant: A M DABKE & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in MADAN RATAN CITY?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback