Registration lapsed No litigation declared Residential / Group Housing project

Laxmi Heights

By Yash Associates

RG-MH-14610 · RERA P52100023403 · Last updated on MahaRERA portal: 28 Oct 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 12 months past the filed date
  • 1 complaint at MahaRERA
  • Completion date moved by 24 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Oct 2025Possession promised12 months past this date
9 of 11Construction stages donefurthest along: Basement (if any), 0%
11 of 20Units unsoldnot recorded sold or booked
1Complaints at MahaRERAon this registration
Jump to the 123 documents Report an error

Laxmi Heights is a Residential / Group Housing project by Yash Associates in Pune, Maharashtra, registered with MahaRERA as P52100023403 on 12 Dec 2019. Possession was promised by 29 Oct 2025 and is now 12 months past that date. The completion date has moved by 24 months from the original filing. 9 of the 20 units on this registration are recorded sold or booked, and 9 of 11 construction stages are filed complete. 1 complaint is on record with the regulator.

At a glance

Project

  • NameLaxmi Heights
  • TypeResidential / Group Housing
  • Location
    • Bhairavnath Temple Road
    • Ambegaon Khurd
    • AMBEGAON KH
    • Haveli
    • Pune
    • 411046
  • Pincode411046
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100023403
  • ReraGenie IDRG-MH-14610

Builder

  • NameYash Associates
  • Entity typePartnership
  • PartnersSham Sudam Devkar, Rajendra Bapusaheb Chinde
  • Other registrations2 more →
  • No longer live3 lapsed, de-registered or revoked

Key dates

12 months past promisethis monthRegisteredDec 2019First promiseOct 2023Revised toOct 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on12 Dec 2019
  • Promised completion29 Oct 2025
  • Revised completionRevised to 29 Oct 2025 (originally 30 Oct 2023)
  • Buildings1 building record
  • Documents filed123 files

Current status

45%9 of 20 units booked
100.0%Work done, per cost certificate

Figures as on 28 Oct 2025, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Laxmi HeightsNA5420020

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 28 Oct 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

9 of 11 construction stages are filed complete. The stage furthest along is Basement (if any), at 0%.

Laxmi Heights: 82% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)100%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 28 Oct 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Land and ownership1

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area597 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on11 Oct 2025
LandownerVillageDistrict
Chandrakant KhiridParvatiPune

Approvals and building plan

Sanctioning authorityPune Municipal Corporation
Permissible FSI714.56
Proposed, not sanctioned715 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchKatraj Dhankawadi - 411046
Estimated costRs 5.32 cr
Cost incurredRs 5.32 cr
Work done100.0%
BuildingWingEstimatedIncurred
Laxmi HeightsNARs 2.66 crRs 2.66 cr
-NARs 2.66 crRs 2.66 cr

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAviva Concept & Planning
EngineerShriram Chandrakant
EngineerA.K. Structural Consultants
EngineerLaxmi Enterprises
Chartered AccountantSpak & Co
Chartered AccountantBogati & Co.
PartnerRole in project
Yash Associates-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100017916Oct 2023 → Oct 2024

Reason as filed by the promoterWe Yash Associates is developing a residential project Laxmi Heights, and I was due to complete the project on 30/10/2023. Due to the Covid-19 pandemic we were not able to construct anymore because of lack of labor contractors and the poor market condition we were unable to complete the project within the due time. Hence, we request you to kindly allow us an extension till 29/10/2024.

EXT52100027441Oct 2023 → Oct 2025

Reason as filed by the promoterI was planning to expand the project, but there was a delay in receiving the sanction plan from the local authority. This setback has postponed our project timeline as we need the official approval to proceed with the expansion.

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC12604290Chandrakant Krishna JadhavYash Associates08/07/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 14 Oct 2019
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 12 Oct 2019
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 12 Oct 2019
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 14 Oct 2019Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed123

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 123 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1 Sep 25.pdf28 Oct 2025
Withdrawal Update Form 2File: Form 2 Sep 25.pdf28 Oct 2025
Withdrawal Update Form 3File: Yash Associates Sep 25.pdf28 Oct 2025
Form 2A (FY 2019-2020)File: 1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20).pdf27 Oct 2025
Form 2A (FY 2020-2021)File: 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21).pdf27 Oct 2025
Form 2A (FY 2021-2022)File: 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22) .pdf27 Oct 2025
Form 2A (FY 2022-2023)File: 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23).pdf27 Oct 2025
Form 2A (FY 2023-2024)File: 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24).pdf27 Oct 2025
Form 5 (FY 2019-2020)File: 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20).pdf27 Oct 2025
Form 5 (FY 2020-2021)File: 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21) (5).pdf27 Oct 2025
Form 5 (FY 2021-2022)File: 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22) (2).pdf27 Oct 2025
Form 5 (FY 2022-2023)File: 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23) (6).pdf27 Oct 2025
Form 5 (FY 2023-2024)File: 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24) (16).pdf27 Oct 2025
Form 5 (FY 2024-2025)File: yash associates form 5 fy 24-25.pdf27 Oct 2025
Form 1File: Dec 19.pdf24 Oct 2025
Form 2File: Dec 19.pdf24 Oct 2025
Form 3File: Dec 19.pdf24 Oct 2025
Disclosure of Sold and Booked InventoryFile: Dec 19.pdf24 Oct 2025
Form 1File: Jun 22.pdf24 Oct 2025
Form 2File: Jun 22.pdf24 Oct 2025
Form 3File: Jun 22.pdf24 Oct 2025
Disclosure of Sold and Booked InventoryFile: Jun 22.pdf24 Oct 2025
Form 1File: Sep 22.pdf24 Oct 2025
Form 2File: Sep 22.pdf24 Oct 2025
Form 3File: Sep 22.pdf24 Oct 2025
Disclosure of Sold and Booked InventoryFile: Sep 22.pdf24 Oct 2025
Form 1File: Mar 23.pdf24 Oct 2025
Form 2File: Mar 23.pdf24 Oct 2025
Form 3File: Mar 23.pdf24 Oct 2025
Disclosure of Sold and Booked InventoryFile: Mar 23.pdf24 Oct 2025
Form 1File: Sep 23.pdf24 Oct 2025
Form 2File: Sep 23.pdf24 Oct 2025
Form 3File: Form 3 Sep 2023.pdf24 Oct 2025
Disclosure of Sold and Booked InventoryFile: Sep 23.pdf24 Oct 2025
Form 1File: Dec 23.pdf24 Oct 2025
Form 2File: Dec 23.pdf24 Oct 2025
Form 3File: Dec 23.pdf24 Oct 2025
Disclosure of Sold and Booked InventoryFile: Dec 23.pdf24 Oct 2025
Form 1File: Mar 24.pdf24 Oct 2025
Form 2File: Mar 24.pdf24 Oct 2025
Form 3File: Mar 24.pdf24 Oct 2025
Disclosure of Sold and Booked InventoryFile: Mar 24.pdf24 Oct 2025
Form 1File: Yash Associates Form 1 March 25.pdf24 Oct 2025
Form 2File: Yash Associates Form 2 March 25.pdf24 Oct 2025
Form 3File: Yash Associates 31 march 2025.pdf24 Oct 2025
Disclosure of Sold and Booked InventoryFile: Mar 25.pdf24 Oct 2025
Withdrawal Update Form 1File: Yash Associates Form 1 JUNE 25.pdf24 Oct 2025
Withdrawal Update Form 2File: Yash Associates Form 2 June 25.pdf24 Oct 2025
Withdrawal Update Form 3File: Yash Associates June 25.pdf24 Oct 2025
Form 1File: Form 1 march 2020.pdf17 Oct 2025
Form 2File: Form 2 march 2020.pdf17 Oct 2025
Form 3File: Form 3 March 2020.pdf17 Oct 2025
Disclosure of Sold and Booked InventoryFile: Sold disclosure march 2020.pdf17 Oct 2025
Form 1File: Form 1 june 2020.pdf17 Oct 2025
Form 2File: Form 2 june 2020.pdf17 Oct 2025
Form 3File: Form 3 June 2020 (2).pdf17 Oct 2025
Disclosure of Sold and Booked InventoryFile: Sold disclosure june 2020.pdf17 Oct 2025
Form 1File: Form 1 Sep 2020.pdf17 Oct 2025
Form 2File: Form 2 Sep 2020.pdf17 Oct 2025
Form 3File: Form 3 Sep 2020 (2).pdf17 Oct 2025
Disclosure of Sold and Booked InventoryFile: Sold disclosure sep 2020.pdf17 Oct 2025
Form 1File: Form 1 Dec 2020.pdf17 Oct 2025
Form 2File: Form 2 Dec 2020.pdf17 Oct 2025
Form 3File: Form 3 Dec 2020 (2).pdf17 Oct 2025
Disclosure of Sold and Booked InventoryFile: Sold disclosure dec 2020.pdf17 Oct 2025
Form 1File: Form 1 march 2021.pdf17 Oct 2025
Form 2File: Form 2 march 2021.pdf17 Oct 2025
Form 3File: Form March 2021.pdf17 Oct 2025
Disclosure of Sold and Booked InventoryFile: Sold disclosure march 2021.pdf17 Oct 2025
Form 1File: Form 1 june 2021.pdf17 Oct 2025
Form 2File: Form 2 june 2021.pdf17 Oct 2025
Form 3File: Form 3 June 2021 (2).pdf17 Oct 2025
Disclosure of Sold and Booked InventoryFile: Sold disclosure june 2021.pdf17 Oct 2025
Form 1File: Form 1 Sep 2021.pdf17 Oct 2025
Form 2File: Form 2 Sep 2021.pdf17 Oct 2025
Form 3File: Form 3 Sep 2021 (2).pdf17 Oct 2025
Disclosure of Sold and Booked InventoryFile: Sold disclosure sep 2021.pdf17 Oct 2025
Form 1File: Form 1 Dec 2021.pdf17 Oct 2025
Form 2File: Form 2 Dec 2021.pdf17 Oct 2025
Form 3File: Form 3 Dec 2021 (2).pdf17 Oct 2025

How this compares with Pune

45%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 24 months
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Laxmi Heights on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Ambegaon Khurd13,700+ in Pune

2 kmLaxmi HeightsCompleted 84Lapsed / revoked 32Other 80Dot size: filed unitsN

Filed coordinates, straight-line distance. 196 registered projects within 2 km.

Builder: Yash Associates

Yash Associates has 3 registrations on MahaRERA, including AISHWARYA CLASSIC and Laxmi Heights. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that Laxmi Heights shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Laxmi Heights is delayed beyond 29 Oct 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Laxmi Heights?

The registered promoter entity is Yash Associates, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Laxmi Heights?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Laxmi Heights?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Laxmi Heights?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Laxmi Heights?

The professionals named in the filing: Architect: Aviva Concept & Planning; Engineer: Shriram Chandrakant; Engineer: A.K. Structural Consultants; Engineer: Laxmi Enterprises; Chartered Accountant: Spak & Co; Chartered Accountant: Bogati & Co.. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Laxmi Heights?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Laxmi Heights. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Laxmi Heights to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.