Registration lapsed No litigation declared Residential / Group Housing project

LAMOR

By SANKALP SIDDHI DEVELOPERS PVT LTD

RG-MH-26337 · RERA P51800007725 · Last updated on MahaRERA portal: 20 Apr 2024

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 40 months past the filed date
  • 71 complaints at MahaRERA
  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Jun 2023Possession promised40 months past this date
4 of 11Construction stages donefurthest along: Slabs of Super Structure, 97%
71Complaints at MahaRERAon this registration
Jump to the 143 documents Report an error

LAMOR is a Residential / Group Housing project by SANKALP SIDDHI DEVELOPERS PVT LTD in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800007725 on 17 Aug 2017. Possession was promised by 29 Jun 2023 and is now 40 months past that date. The completion date has moved by 12 months from the original filing. 71 complaints are on record with the regulator.

At a glance

Project

  • NameLAMOR
  • TypeResidential / Group Housing
  • Location
    • OSHIWARA
    • Borivali
    • Mumbai Suburban
    • 400102
  • Pincode400102
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800007725
  • ReraGenie IDRG-MH-26337

Builder

  • NameSANKALP SIDDHI DEVELOPERS PVT LTD
  • Entity typeCompany
  • DirectorJia Zhuowen Wei

Key dates

40 months past promisethis monthRegisteredAug 2017First promiseJun 2022Revised toJun 2023

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on17 Aug 2017
  • Promised completion29 Jun 2023
  • Revised completionRevised to 29 Jun 2023 (originally 30 Jun 2022)
  • Buildings1 building record
  • Documents filed143 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
LAMOR Wing A BNA420000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 20 Apr 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 97%.

LAMOR Wing A B: 53% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure97%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises43%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks45%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 20 Apr 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed370

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots370
Closed/Covered370

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area3,381 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
Sahyog Homes LimitedAndheriMumbai Suburban

Approvals and building plan

Permissible FSI26130.06
Proposed, not sanctioned18,153 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchINDRAPRASTHA LINKINKING ROAD SANTACRUZ WEST MUMBAI 400054

Certifying professionals and partners1

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSHYAM HEMRAJANI
PartnerRole in project
SANKALP SIDDHI DEVELOPERS PVT LTD-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800011746Jun 2022 → Jun 2023

Reason as filed by the promoterDue to lock down all contractors and workers are not available to work.

Complaints filed with MahaRERA71

Case no.ComplainantRespondentFiled
CC006000000000782Prapti MalhotraSankalp Siddhi Developers Pvt ltd29/09/2017
CC006000000192416Prapti Malhotrasankalp Siddhi developers pvt. ltd03/02/2020
CC006000000044080SEEMA TIWARISAHYOG HOMES LTD.11/04/2018
CC006000000196971G.G.Photo Ltd. through its Director Gaurav GuptaSankalp Siddhi Developers Pvt. Ltd.11/05/2021
CC006000000055864Mrs. Tejal Umang MehtaM/s Sankalp Siddhi Developers Pvt. Ltd.21/08/2018
CC006000000057189DEEPA AMAR LARAI & AMAR RAMCHAND LARAISANKALP SIDDHI DEVELOPERS PVT LTD06/12/2018
CC006000000057258Neetu JagwaniSankalp Siddhi Developers Pvt. Ltd. & Sahyog Homes Ltd.11/12/2018
CC006000000057960RAWANI JIKAR MUSA BHAI & ANRsankalp siddhi developers pvt ltd05/02/2019
CC006000000171481oni ismailbhai baluwala & Farzana Oni BaluwalaM/s. Sankalp Siddhi Developers Pvt. Ltd.09/11/2019
CC006000000397284Oni baluwala ismailbhai baluwalaM/S. SANKALP SIDDHI DEVELOPERS PVT. LTD.29/08/2023
CC006000000182095SUNIL PARMANAND KEWALRAMANISANKALP SIDDHI DEVELOPERS PVT. LTD.07/01/2020
CC006000000182097MANOJ PARMANAND KEWALRAMANISANKALP SIDDHI DEVELOPERS PVT. LTD.07/01/2020
CC006000000193381Salim Abdullah Patel and Saumiya Salim PatelSankalp Siddhi Developers Pvt Ltd14/07/2020
CC006000000193577Kedar RathSankalp Siddhi Developers Pvt Ltd23/12/2020
CC006000000198654Mohammed Ali Mohammed YunusSankalp Siddhi Developers Pvt Ltd21/10/2021
CC006000000195725Anil Madhyan and Nita A MadhyanSankalp Siddhi Developers Pvt Ltd22/01/2021
CC006000000195948Aziz ChakkiwalaSankalp Siddhi Developers Pvt Ltd08/02/2021
CC006000000196087Ms. Prachi Hemant SanghaiM/s. Sankalp Siddhi Developers Private Limited18/02/2021
CC006000000375074Ms Prachi Hemant SanghaiM/s Sankalp Siddhi Developer Pvt Ltd03/04/2023
CC006000000198141Reena NegandhiSANKALP SIDDHI DEVELOPERS PVT LTD30/08/2021
CC006000000220984SURESH RAMCHAND MADHYANSANKALP SIDDHI DEVELOPERS PVT LTD29/04/2022
CC006000000251388Jameer Husen MullaSankalp Siddhi Developers Private Limited11/06/2022
CC006000000251782Ramesh PremaneySankalp Siddhi Developers Pvt Ltd07/07/2022
CC006000000251783Suresh PremaneySankalp Siddhi Developers Pvt Ltd08/07/2022
CC006000000251789Mohan PremaneySankalp Siddhi Developers Pvt Ltd08/07/2022
CC006000000251795Harish AwtaneySankalp Siddhi Developers Pvt Ltd08/07/2022
CC006000000251801Deepak SajnaniSankalp Siddhi Developers Pvt Ltd08/07/2022
CC006000000251830Naresh LakhwaniSankalp Siddhi Developers Pvt Ltd09/07/2022
CC006000000251838Vijay AwtaneySankalp Siddhi Developers Pvt Ltd09/07/2022
CC006000000292802SANJEEDA SHAIKHM/S.SANKALP SIDDHI DEVELOPERS PVT LTD24/09/2022
CC006000000302973Mr Naresh Kumar Omprakash HiranandaniSankalp Siddhi Developers Pvt Ltd07/10/2022
CC006000000303393Ms Mumtaz Ibrahim KhanSankalp Siddhi Developers Pvt Ltd21/11/2022
CC006000000303504Mr Gehimal Aidasani Mrs Sunita AidasaniSankalp Siddhi Developers Pvt Ltd29/11/2022
CC006000000303505Mr Dilip Kumar OdhraniSankalp Siddhi Developers Pvt Ltd29/11/2022
CC006000000303506Mr Mohit D OdhraniSankalp Siddhi Developers Pvt Ltd29/11/2022
CC006000000303676Mr Chander Prakash Kewlani and Mrs Meena KewlaniSankalp Siddhi Developers Pvt Ltd14/12/2022
CC006000000303710Mr Bhojraj Kewlani and Mrs Nisha KewlaniSankalp Siddhi Developers Pvt Ltd16/12/2022
CC006000000334000Vissa InvestmentsSankalp Siddhi Developers Pvt Ltd18/01/2023
CC006000000334140Flora SainiSankalp Sidhi Developers29/01/2023
CC006000000344258Mr Murli Pursumal Bhatia and Dr ( Mrs ) Champa Murli BhatiaSankalp Siddhi Developers Pvt Ltd08/02/2023
CC006000000344259Mr Prakash Bhatia and Mrs Simran BhatiaSankalp Siddhi Developers Pvt Ltd08/02/2023
CC006000000375082Hemant Prakash SanghaiM/s. Sankalp Siddhi Developers Private Limited03/04/2023
CC006000000375174Mr Devraj Lalwani and Mr Manish LalwaniSankalp Siddhi Developers Pvt Ltd08/04/2023
CC006000000375182Chandru BhojwaniSankalp Siddhi Developers Pvt Ltd09/05/2023
CC006000000375185Dilip Bharat ManghnaniSankalp Siddhi Developers22/04/2023
CC006000000375184Mahender Hiranand BhojwaniSankalp Siddhi Developers Pvt Ltd09/05/2023
CC006000000375186SARIKA CHAWLASankalp Siddhi Developers22/04/2023
CC006000000375233Mr Ram Priyani MoolchandSankalp Siddhi Developers Pvt Ltd12/04/2023
CC006000000396124Dipak Kailash DevnaniSankalp Siddhi Developers Pvt Ltd07/06/2023
CC006000000396207NARENDRA KANAYALAL HEMDEVSANKALP SIDDHI DEVELOPERS PVT LTD13/07/2023
CC006000000396205MAHENDRA KANAYALAL HEMDEVSANKALP SIDDHI DEVELOPERS PVT LTD13/07/2023
CC006000000397162VINOD THUKRAL HUFSankalp Siddhi Developers Pvt. Ltd.21/08/2023
CC006000000397163SHEETAL DINESH THUKRALSankalp Siddhi Developers Pvt. Ltd21/08/2023
CC006000000397164NEELU SATYAN THUKRALSankalp Siddhi Developers Pvt. Ltd.21/08/2023
CC006000000397414Akash Ashok BhagiaBhalchandra Trading Pvt Ltd08/09/2023
CC006000000397627Sumesh Ashok Patel and Dharali Suresh PatelSankalp Sidhhi Developers Pvt Ltd28/09/2023
CC006000000397635Mrs Anju Yogesh Singhvi & Mr Yogesh Manchand SinghviSankalp Siddhi Developers Pvt Ltd28/09/2023
CC006000000397638Abhinay Rao PenugondaSankalp Siddhi Developers Pvt Ltd28/09/2023
CC006000000397641Shreya Mitra and Partha Sarathi MitraSankalp Siddhi Developers Pvt Ltd28/09/2023
CC006000000397649Aashi AroraSankalp Siddhi Developers Pvt Ltd28/09/2023

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 30 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 28 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 5 Jan 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 5 Jan 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed143

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 143 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate - L'Amor - Mar 24.pdf20 Apr 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate - Verona - Mar 24.pdf20 Apr 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate - L'Amor - Dec 23.pdf6 Jan 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate - Verona - Dec 23.pdf6 Jan 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate - LAmor - Sep 23.pdf7 Oct 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate - Verona - Sep 23.pdf7 Oct 2023
Certificates of CA (Form 3)File: Form 3 CA Certificate for RERA Compliance - LAmor Sept 23.pdf7 Oct 2023
Certificates of CA (Form 5)File: RERA Certificate Form no 5 of FY 2022-23 - LAmor Project.pdf29 Sep 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: RERA Certificate Form no 5 of FY 2022-23 - LAmor Project.pdf29 Sep 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate - LAmor - Jun 23.pdf7 Jul 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate - Verona - Jun 23.pdf7 Jul 2023
Certificates of CA (Form 3)File: Form 3 CA Certificate for RERA Compliance - LAmor Project Jun 23.pdf7 Jul 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Lamor.pdf17 Apr 2023
Certificates of CA (Form 3)File: Form 3 CA Certificate for RERA Compliance - LAmor Project Mar 23.pdf7 Apr 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate - LAmor - Mar 23.pdf6 Apr 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate - Verona - Mar 23.pdf6 Apr 2023
Proforma of Allotment letterFile: Revised RERA Proposed Allotment Letter LAmor.pdf21 Mar 2023
Deviation Report with respect to Allotment letterFile: Revised Deviation Sheet Allotment Letter LAmor.pdf21 Mar 2023
Proforma of Allotment letterFile: RERA Allotment Letter New - LAmor.pdf10 Mar 2023
Deviation Report with respect to Allotment letterFile: Deviation Sheet Allotment Letter - LAmor.pdf10 Mar 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate - L'Amor - Dec 22.pdf7 Jan 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate - Verona - Dec 22.pdf7 Jan 2023
Certificates of CA (Form 3)File: Form 3 CA Certificate for RERA Compliance - LAmor Project Dec 22.pdf7 Jan 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: L'amor- RERA Architect Certifcate.pdf6 Jan 2023
Building plan approvalFile: 20220505102113.pdf5 Jan 2023
Building Plan Approval (IOD)File: 20220505102113.pdf5 Jan 2023
Commencement Certificates / NA Order for plotted developmentFile: S -1 37 to 40 FCC 10th Jun 2022.pdf5 Jan 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate - L'amor - Sep 22.pdf7 Oct 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate - Verona - Sep 22.pdf7 Oct 2022
Certificates of CA (Form 3)File: Form 3 CA Certificate for RERA Compliance - LAmor Project Sept 22.pdf7 Oct 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Lamor.pdf6 Oct 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: RERA Certificate Form no 5 of FY 2021-22 - LAmor.pdf30 Sep 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: 6 (1).pdf29 Sep 2022
Certificates of CA (Form 5)File: RERA Certificate Form no 5 of FY 2021-22 - LAmor.pdf28 Sep 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Lamor - Architect Certificate.pdf7 Jul 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate - L'amor - June 22.pdf7 Jul 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate - Verona - June 22.pdf7 Jul 2022
Certificates of CA (Form 3)File: Form 3 CA Certificate for RERA Compliance - LAmor Project June 22.pdf7 Jul 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Lamor - 123.pdf17 Jun 2022
Declaration about Commencement CertificateFile: Lamor - Declaration about Commenncement Certificate.pdf18 Apr 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Quality Certificate .pdf12 Apr 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Quality Certificate .pdf12 Apr 2022
Declaration about Commencement CertificateFile: Lamor - Declaration about Commenncement Certificate.pdf11 Apr 2022
CERSAI detailsFile: CERSAI_Search_Report_200234840143_For_Asset_Based_Search_08_04_2022_16_31_50_000.pdf11 Apr 2022
Disclosure of sold/ booked inventoryFile: Lamor - Sold and unsold data_compressed-compressed.pdf11 Apr 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: CA.pdf11 Apr 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: CA.pdf11 Apr 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate - L'Amor - Mar 22.pdf7 Apr 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate - Verona - Mar 22.pdf7 Apr 2022
Certificates of CA (Form 3)File: Form 3 CA Certificate for RERA Compliance - LAmor Project March 22.pdf7 Apr 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Lamor - RERA Architect Certificate.pdf6 Apr 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Lamor- RERA Architect Certificate.pdf6 Apr 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate - L'Amor - Dec-21.pdf7 Jan 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate - Verona - Dec-21.pdf7 Jan 2022
Certificates of CA (Form 3)File: Form 3 CA Certificate for RERA Compliance - LAmor Project December 21.pdf7 Jan 2022
Certificates of CA (Form 3)File: Form 3 CA Certificate for RERA Compliance - LAmor Project September 21.pdf7 Oct 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Lamor - RERA Architect Certificate.pdf6 Oct 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate - L'Amor - Sep-21.pdf6 Oct 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate - Verona - Sep-21.pdf6 Oct 2021
Certificates of CA (Form 5)File: FORM 5 LAmor.pdf21 Sep 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate - L'Amor - June-21.pdf13 Aug 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate - Verona - June-21.pdf13 Aug 2021
Certificates of CA (Form 3)File: Form 3 CA Certificate for RERA Compliance - LAmor Project - June 21.pdf13 Aug 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 3_LAMOR - RERA Architect Certificate.pdf10 Aug 2021
Details of encumbrancesFile: Lamor Details of Encumbrance-3.pdf1 Jul 2021
Certificates of CA (Form 3)File: LAmor FORM 3.pdf25 Jun 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: L'amor .pdf21 Jun 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Verona.pdf21 Jun 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 3_LAMOR - RERA Architect Certificate March21.pdf25 May 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: FORM 5- L'Amor PROJECT.pdf2 Apr 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: L'amor Sept 20.pdf30 Mar 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Verona Sept 20.pdf30 Mar 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: L'mor Dec 20.pdf30 Mar 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: verona Dec 20.pdf30 Mar 2021
Certificates of CA (Form 3)File: LAMORE SEP 2020.pdf16 Mar 2021
Certificates of CA (Form 3)File: LMORE DEC 2020.pdf16 Mar 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: LAMOR - RERA Architect Certificate - Dec20.pdf25 Feb 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: LAMOR - March20.pdf16 Feb 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: verona - March 20.pdf16 Feb 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: LAMOR - June 20.pdf16 Feb 2021

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one moved by 12 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is among them

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep LAMOR on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near OSHIWARA6,700+ in Mumbai Suburban

2 kmLAMORCompleted 86Lapsed / revoked 54Abeyance 1Other 127Dot size: filed unitsN

Filed coordinates, straight-line distance. 268 registered projects within 2 km.

Builder: SANKALP SIDDHI DEVELOPERS PVT LTD

SANKALP SIDDHI DEVELOPERS PVT LTD has 1 registration on MahaRERA, including LAMOR. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What does it mean that LAMOR shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if LAMOR is delayed beyond 29 Jun 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of LAMOR?

The registered promoter entity is SANKALP SIDDHI DEVELOPERS PVT LTD, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in LAMOR?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against LAMOR?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for LAMOR?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at LAMOR?

The professionals named in the filing: Architect: SHYAM HEMRAJANI. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in LAMOR?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About LAMOR. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save LAMOR to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.