ReraGenieLog inGet a buyer report

Home / Browse projects / Gandhinagar, Gujarat / LABH NIRANT

Valid until 30 Sep 2022 Residential/Group Housing project

LABH NIRANT

By LABH BUILDCON

RG-GJ-83273 · RERA PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/RAA06701/290120 · Last updated on GujRERA portal: 6 Aug 2022

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
Sep 2022Possession promisedno revision filed
25 of 35Construction stages doneacross 5 buildings; furthest along: Sanitary fittings within the flats, 90%
0 of 10Units unsoldnot recorded sold or booked
Jump to the 45 documents Report an error

LABH NIRANT is a Residential/Group Housing project by LABH BUILDCON in Gandhinagar, Gujarat, registered with GujRERA as PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/RAA06701/290120 on 29 Jan 2020. Possession is promised by 30 Sep 2022. 10 of the 10 units on this registration are recorded sold or booked, and 25 of 35 construction stages are filed complete.

At a glance

Project

  • NameLABH NIRANT
  • TypeResidential/Group Housing
  • Location
    • LABH NIRANT
    • NEAR SWARA HOMES
    • KUDASAN
    • GANDHINAGAR
    • Kudasan
    • Gandhinagar
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/RAA06701/290120
  • ReraGenie IDRG-GJ-83273

Builder

  • NameLABH BUILDCON
  • Entity typePARTNERSHIP FIRM

Key dates

this monthRegisteredJan 2020PromisedSep 2022

Key facts

Registration and timeline

  • StatusValid until 30 Sep 2022
  • Registered on29 Jan 2020
  • Promised completion30 Sep 2022
  • Revised completionNone
  • Buildings5 building records
  • Documents filed45 files

Current status

100%10 of 10 units booked
100.0%Of the estimated cost spent so far

Figures as on 6 Aug 2022, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
B---202
C---202
D---202
D1---202
A---202

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building5

As on 6 Aug 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

25 of 35 construction stages are filed complete across 5 buildings. The stage furthest along is Sanitary fittings within the flats, at 90%.

B97%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats90%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing90%
C97%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats90%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing90%
D97%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats90%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing90%
D197%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats90%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing90%
A97%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats90%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing90%

Progress on shared amenities19

As on 6 Aug 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes80%
Water supplyYes95%
Sewerage (chamber, lines, septic tank, STP)Yes95%
Storm water drainsNoNot applicable
Landscaping and tree plantingYes95%
Street lightingYes95%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingNoNot applicable
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationNoNot applicable
Fire fightingNoNot applicable
Drinking water facilitiesNoNot applicable
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityNoNot applicable
Letter boxNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area3,567 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 3.48 cr
Cost incurredRs 3.48 cr
Spent of the estimate100.0%
BuildingWingEstimatedIncurred
ANARs 69.54 lakhRs 69.54 lakh
BNARs 69.54 lakhRs 69.54 lakh
CNARs 69.54 lakhRs 69.54 lakh
DNARs 69.54 lakhRs 69.54 lakh
D1NARs 69.54 lakhRs 69.54 lakh

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectPRAGNA P MACHHAR
EngineerAMIT. M. KA. PATEL

Documents filed45

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/RAA06701/290120 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Accountant's certificate (Form 3)6 Aug 2022
Architect's certificate (Form 1)5 Aug 2022
Engineer's certificate (Form 2)5 Aug 2022
Engineer's certificate annexure5 Aug 2022
Site photograph, B5 Aug 2022
Site photograph, C5 Aug 2022
Site photograph, D5 Aug 2022
Site photograph, D15 Aug 2022
Site photograph, A5 Aug 2022
RERA registration certificate29 Jan 2020
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Gandhinagar

100%of this project is bookeddistrict median 53%
16%of Gandhinagar projects moved their completion datethis one has not

Computed across the 1,600+ Gandhinagar projects on ReraGenie, from their own filings.

Keep LABH NIRANT on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Kudasan1,600+ in Gandhinagar

2 kmLABH NIRANTOther 218Dot size: filed unitsN

Filed coordinates, straight-line distance. 218 registered projects within 2 km.

Builder: LABH BUILDCON

LABH BUILDCON has 1 registration on GujRERA, including LABH NIRANT. Read the full track record. See more projects on the Gandhinagar district page.

Frequently asked questions

What are my rights if LABH NIRANT is delayed beyond 30 Sep 2022?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of LABH NIRANT?

The registered promoter entity is LABH BUILDCON, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in LABH NIRANT?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at LABH NIRANT?

The professionals named in the filing: Architect: PRAGNA P MACHHAR; Engineer: AMIT. M. KA. PATEL. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in LABH NIRANT?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About LABH NIRANT. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save LABH NIRANT to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.