Krushna Skyline
RG-MH-19340 · RERA P50000078469 · Last updated on MahaRERA portal: 8 May 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Possession 1 months past the filed date
- Completion date moved by 6 months
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Buldana registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Krushna Skyline is a Residential / Group Housing project by Renucorp Private Limited in Buldana, Maharashtra, registered with MahaRERA as P50000078469 on 12 Dec 2024. Possession was promised by 30 Sep 2026 and is now 1 months past that date. The completion date has moved by 6 months from the original filing. 9 of the 15 units on this registration are recorded sold or booked, and 7 of 11 construction stages are filed complete.
At a glance
Project
- NameKrushna Skyline
- TypeResidential / Group Housing
- Location
- Off Jalna Road
- Anand Nagar
- Chikhli
- Buldana
- 443201
- Pincode443201
- MapView location on Google Maps (as filed on RERA)
- RERA no.P50000078469
- ReraGenie IDRG-MH-19340
Builder
- NameRenucorp Private Limited
- Entity typeCompany
- CINU65999MH2023PTC397364
- GSTIN27AAECI4063Q1Z2
- DirectorsVaibhav Diliprao Wankhade, Poonam Vaibhav Wankhade
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on12 Dec 2024
- Promised completion30 Sep 2026
- Revised completionRevised to 30 Sep 2026 (originally 31 Mar 2026)
- Buildings1 building record
- Documents filed48 files
Current status
Figures as on 8 May 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Krushna Skyline | NA | 6 | 5 | 15 | 0 | 15 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 8 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
7 of 11 construction stages are filed complete. The stage furthest along is Staircases, at 90%.
Krushna Skyline: 80% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 90% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 85% |
Progress on shared amenities15
As on 8 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed1
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| Krushna Skyline | NA | Rs 3.07 cr | Rs 2.89 cr |
| - | NA | Rs 5.00 lakh | Rs 2.50 lakh |
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | AR Architect Rajput |
| Engineer | Er Akash Gaikwad Home Point Gaikwad |
| Chartered Accountant | M R K S & Company Mahore |
| Chartered Accountant | A B S K And Associates |
| Partner | Role in project |
|---|---|
| Renucorp Private Limited | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterAs certified by the Architect in Form-1 for last quarter, submitted as part of Quarterly Progress Reports, majority of the construction work of the project is completed and balance finishing work is in progress. We are hopeful that the balance work will get completed in couple of months and few months thereafter are required for obtaining various NOCS as well as Occupation Certificate for the project. In view of the above, we request this Hon’ble Authority to grant extension to the project registration until 30/09/2025
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 10 Jul 2024 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 10 Jul 2024 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 10 Jul 2024 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 10 Jul 2024Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed48
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 2A (FY 2024-2025)File: Form 2A 2025.pdf | 8 May 2026 |
| Form 2A (FY 2025-2026)File: Form 2A 2026.pdf | 8 May 2026 |
| Withdrawal Update Form 1File: Krushna Skyline Form-1 March 2026.pdf | 5 May 2026 |
| Withdrawal Update Form 2File: Krushna Skyline Form-2 March 2026.pdf | 5 May 2026 |
| Withdrawal Update Form 3File: Krushna Skyline Form-3 March 2026.pdf | 5 May 2026 |
| Withdrawal Update Form 1File: Krushna Skyline Form-1 Dec 2025.pdf | 11 Feb 2026 |
| Withdrawal Update Form 2File: Krushna Skyline Form-2 Dec 2025.pdf | 11 Feb 2026 |
| Withdrawal Update Form 3File: Krushna Skyline Form-3 Dec 2025.pdf | 11 Feb 2026 |
| Form 5 (FY 2024-2025)File: Form 5 Signed.pdf | 12 Dec 2025 |
| Withdrawal Update Form 1File: Krushna Skyline Form-1 Sep 2025.pdf | 22 Nov 2025 |
| Withdrawal Update Form 2File: Krushna Skyline Form-2 Sep 2025.pdf | 22 Nov 2025 |
| Withdrawal Update Form 3File: Krushna Skyline Form-3 Sep 2025.pdf | 22 Nov 2025 |
| Form 1File: Form 1 Krushna Skyline.pdf | 11 Jun 2025 |
| Form 2File: Form 2 Krushna Skyline.pdf | 11 Jun 2025 |
| Form 3File: Form-3 Krushna skyline updated.pdf | 11 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: Renucorp Sold Inventory Disclosure.pdf | 11 Jun 2025 |
| Self-declaration of Quarterly ProgressFile: Krushna Skyline QPR Declaration draft.pdf | 11 Jun 2025 |
| Other - LegalFile: 15_Sale Deed Part 3.pdf | 12 Aug 2024 |
| Other - LegalFile: 15_Sale Deed Part 1.pdf | 12 Aug 2024 |
| Other - LegalFile: 15_Sale Deed Part 2.pdf | 12 Aug 2024 |
| Other - LegalFile: 15A_7-12.pdf | 12 Aug 2024 |
| Other - TechnicalFile: 20 Registration Declaration.pdf | 27 Jul 2024 |
| Disclosure for secured/unsecured finance availed for the projectFile: 12B_Loan Declaration.pdf | 11 Jul 2024 |
| Building plan approvalFile: 5_IoD Letter.pdf | 10 Jul 2024 |
| Layout approvalFile: 4_IoD Drawing.pdf | 10 Jul 2024 |
| PAN CardFile: 1_PAN.pdf | 10 Jul 2024 |
| Copy of the legal title reportFile: 2A_Title New.pdf | 10 Jul 2024 |
| Details of encumbrances concerned to FinanceFile: 3A_Encumbrance Declaration.pdf | 10 Jul 2024 |
| Details of encumbrances concerned to FinanceFile: 3B_Legal Encumbrance.pdf | 10 Jul 2024 |
| Copy of Layout Approval (in case of layout)File: 4_IoD Drawing.pdf | 10 Jul 2024 |
| Proforma of Allotment letterFile: 13_Allotment Letter.pdf | 10 Jul 2024 |
| Declaration in FORM BFile: 8_Form-B.pdf | 10 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 9_Ar New.pdf | 10 Jul 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 11_CA New.pdf | 10 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 10_Er New.pdf | 10 Jul 2024 |
| Commencement Certificates / NA Order for plotted developmentFile: 6_CC.pdf | 10 Jul 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: 5_IoD Letter.pdf | 10 Jul 2024 |
| Declaration about Commencement CertificateFile: 7_CC Declaration.pdf | 10 Jul 2024 |
| CERSAI detailsFile: Krushna Skyline CERSAI Latest.pdf | 10 Jul 2024 |
| Declaration about all RERA Designated Bank Accounts (Format A)File: 18A_Format A.pdf | 10 Jul 2024 |
| Deviation Report with respect to Allotment letterFile: 13A_Allotment Deviation.pdf | 10 Jul 2024 |
| Details of encumbrances concerned to LegalFile: 3A_Encumbrance Declaration.pdf | 10 Jul 2024 |
| Details of encumbrances concerned to LegalFile: 3B_Legal Encumbrance.pdf | 10 Jul 2024 |
| Deviation Report with respect to model copy of AgreementFile: 14A_AfS Deviation.pdf | 10 Jul 2024 |
| Proforma of Agreement for saleFile: 14_AfS.pdf | 10 Jul 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: 17A_OREO_VDW.pdf | 10 Jul 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: 17B_OREO_PVW.pdf | 10 Jul 2024 |
| Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: HDFC Bank Declaration final.pdf | 10 Jul 2024 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Buldana
Computed across the 58 Buldana projects on ReraGenie, from their own filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 3 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 48 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep Krushna Skyline on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Anand Nagar58 in Buldana
Anilbhau Properties
Nitin Vasantrao Padghan
Ayodhya Residency
Shree Infra
Chintamani Tower
Nitin Vasantrao Padghan
SWAPNAPURTI APARTMENT
SAI BUILDERS AND DEVELOPERS
GURUPRASAD DEVELOPERS
SUVARNA ANANTRAO DESHMUKH
Chhoriya Future City - Malkapur Plotting
Dhariwal And Chhoriya Developers LLP
See every Buldana project, with the district possession charts
Builder: Renucorp Private Limited
Renucorp Private Limited has 1 registration on MahaRERA, including Krushna Skyline. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Buldana district page.
Frequently asked questions
What are my rights if Krushna Skyline is delayed beyond 30 Sep 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Krushna Skyline?
The registered promoter entity is Renucorp Private Limited, a company as per the filing. Its CIN U65999MH2023PTC397364 and GSTIN 27AAECI4063Q1Z2 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Krushna Skyline?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Krushna Skyline?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Krushna Skyline?
The professionals named in the filing: Architect: AR Architect Rajput; Engineer: Er Akash Gaikwad Home Point Gaikwad; Chartered Accountant: M R K S & Company Mahore; Chartered Accountant: A B S K And Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Krushna Skyline?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback