Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form
  • All 1 earlier projects delivered on promise

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 10 other registrations and every project registered within 2 km.

See what the report covers Free either way: or have every new Buldana registration emailed to you, free during the pilot beta.
Dec 2029Possession promisedno revision filed
204 of 312Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 90 documents Report an error

Chhoriya Future City - Malkapur Plotting is a Plotted project by Dhariwal And Chhoriya Developers LLP in Buldana, Maharashtra, registered with MahaRERA as P50000030840 on 20 Sep 2021. Possession is promised by 31 Dec 2029. 108 of the 312 units on this registration are recorded sold or booked.

At a glance

Project

  • NameChhoriya Future City - Malkapur Plotting
  • TypePlotted
  • Location
    • Kapakeda Malkapur Shiv Road
    • At/Post - Malkapur
    • Buldana
    • Malkapur (Rural)
    • Malkapur
    • Buldana
    • 443101
  • Pincode443101
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P50000030840
  • ReraGenie IDRG-MH-99368

Builder

  • NameDhariwal And Chhoriya Developers LLP
  • Entity typePartnership
  • PartnerAnmol Kanhaiyalal Chhoriya
  • Other registrations10 more →
  • Completed2 of 11
  • No longer live2 lapsed, de-registered or revoked
  • Declared earlier projects1 →

Key dates

this monthRegisteredSep 2021PromisedDec 2029

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on20 Sep 2021
  • Promised completion31 Dec 2029
  • Revised completionNone
  • BuildingsNot stated in filing
  • Documents filed90 files

Current status

35%108 of 312 units booked
77.7%Work done, per cost certificate

Figures as on 11 Jul 2026, this project's latest MahaRERA filing.

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 11 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

NA Plot Without Structure:

ActivityProgress
ExcavationNot applicable
Basement (if any)Not applicable
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/PremisesNot applicable
Sanitary Fittings within the flats / premisesNot applicable
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water TanksNot applicable
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.Not applicable
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.Not applicable

Progress on shared amenities16

As on 11 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes50%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes80%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes0%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes30%
Open ParkingNoNot applicable
Entrance GateYes100%

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area45,677 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on14 Jun 2025

Approvals and building plan

Sanctioning authorityTown Planning, Buldhana
Permissible FSI29888.45
Proposed, not sanctioned29,888 sq m

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchYavatmal
Estimated costRs 3.52 cr
Cost incurredRs 2.74 cr
Work done77.65%
BuildingWingEstimatedIncurred
-NARs 3.52 crRs 2.74 cr

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMr Kunal P Patil Patil
EngineerIMPower Projects - Mr Manish Pande
EngineerAvinash Wadgaonkar
Chartered AccountantAyush S. Kankariya
PartnerRole in project
Dhariwal And Chhoriya Developers LLP-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 18 Sep 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 24 Aug 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 24 Aug 2021
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 24 Aug 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2029

Documents filed90

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 90 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Malkapur Form 1 March 2026.pdf11 Jul 2026
Withdrawal Update Form 1File: Malkapur Form 1 March 2026.pdf11 Jul 2026
Withdrawal Update Form 2File: Malkapur Form 2 March 2026.pdf11 Jul 2026
Withdrawal Update Form 2File: Malkapur Form 2 March 2026.pdf11 Jul 2026
Withdrawal Update Form 3File: Malkapur Form 3 March 2026.pdf11 Jul 2026
Withdrawal Update Form 3File: Malkapur Form 3 March 2026.pdf11 Jul 2026
Form 1File: Malkapur Form 1 Dec 2025.pdf17 Mar 2026
Form 2File: Malkapur Form 2 Dec 2025.pdf17 Mar 2026
Form 3File: Malkapur Form 3 Dec 2025_compressed.pdf17 Mar 2026
Disclosure of Sold and Booked InventoryFile: Malkapur Sold-Unsold Dec 2025.pdf17 Mar 2026
Form 1File: Malkapur Form 1 Sept 2025.pdf16 Jan 2026
Form 2File: Malkapur Form 2 Sept 2025.pdf16 Jan 2026
Form 3File: Malkapur Form 3 Sept 2025.pdf16 Jan 2026
Disclosure of Sold and Booked InventoryFile: Malkapur.pdf16 Jan 2026
Form 1File: Malkapur Form 1 June 25.pdf28 Aug 2025
Form 2File: Malkapur Form 2 June 25.pdf28 Aug 2025
Form 3File: Malkapur Form 3 June 25.pdf28 Aug 2025
Disclosure of Sold and Booked InventoryFile: Malkapur Sold & Unsold June 2025.pdf28 Aug 2025
Form 1File: Malkapur Form 1 March 2025.pdf23 Jun 2025
Form 2File: Malkapur Form 2 March 2025.pdf23 Jun 2025
Form 3File: Malkapur Form 3 March 2025_compressed.pdf23 Jun 2025
Disclosure of Sold and Booked InventoryFile: Malkapur.pdf23 Jun 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Malkapur Form 3 Dec 2024.pdf7 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Malkapur Form 1 Dec 2024.pdf31 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Malkapur Form 2 Dec 2024.pdf31 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Malkapur Sept24.pdf26 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Malkapur Form 1.pdf25 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Malkapur Form 2.pdf25 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: AR Malkapur June24.pdf12 Aug 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ER Malkapur June24.pdf12 Aug 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Malkapur June24.pdf12 Aug 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: AR Malkapur March24.pdf5 Jun 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ER Malkapur March24.pdf5 Jun 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: F5 CA Malkapur Plotting 23-24.pdf5 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Malkapur March24_compressed.pdf5 Jun 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: F5 CA Malkapur Plotting 21-22.pdf5 Jun 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: F5 CA Malkapur Plotting 22-23.pdf5 Jun 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: F5 CA Malkapur Plotting 23-24.pdf5 Jun 2024
Disclosure of sold/ booked inventoryFile: Malkapur.pdf7 May 2024
Disclosure of sold/ booked inventoryFile: Malkapur.pdf17 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Malkapur Dec23_compressed.pdf14 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: AR Malkapur Dec23.pdf23 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ER Malkapur Dec23.pdf23 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Malkapur Sept 2023_compressed.pdf5 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: AR Malkapur Sept23.pdf29 Dec 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ER Malkapur Sept23.pdf29 Dec 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Malkapur June 2023.pdf29 Dec 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Malkapur plotting Architect's certificate 1.PDF15 Dec 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: AR Malkapur June 2023.pdf15 Dec 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Malkapur plotting Engineer's Certificate.pdf15 Dec 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ER Malkapur June 2023.pdf15 Dec 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Malkapur March 2023.pdf15 Dec 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Malkapur June 2023.pdf15 Dec 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Malkapur plotting Architect's certificate.PDF23 Aug 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Malkapur plotting Engineer's Certificate.PDF23 Aug 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Malkapur potting_compressed.pdf23 Aug 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Ar malakpur site.pdf30 Dec 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Er malkapur site.pdf30 Dec 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA malkapur_11zon.pdf30 Dec 2022
Disclosure of sold/ booked inventoryFile: Malkapur.pdf28 Dec 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Malkapur_11zon.pdf28 Sep 2022
Disclosure of sold/ booked inventoryFile: Malkapur 14A.pdf27 Sep 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ar malkapur.pdf23 Sep 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: er malkapur.pdf23 Sep 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Ar cert chhoriya future city Malkapur plotting.pdf6 Jul 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engg cert chhoriya fortune city Malkapur plotting.pdf6 Jul 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Cert Chhoriya future city malkapur plotting.pdf6 Jul 2022
CERSAI detailsFile: MALKHAPUR CERSAI.pdf13 May 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 JAN 22 MALKHAPUR.pdf31 Mar 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 JAN 22 MALKAPUR.pdf31 Mar 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 JAN 22 MALKAPUR_compressed.pdf31 Mar 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 JAN 22 MALKHAPUR.pdf22 Mar 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 JAN 22 MALKAPUR.pdf22 Mar 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 JAN 22 MALKAPUR_compressed.pdf22 Mar 2022
Copy of the legal title reportFile: Malkapur Legal Title Report.pdf18 Sep 2021
Copy of the legal title reportFile: Malkapur Flow Of title Report.pdf18 Sep 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Malkapur CA Certificate.pdf28 Aug 2021
Building plan approval or NA orderFile: Order.pdf24 Aug 2021
Layout approvalFile: layout For RERA.pdf24 Aug 2021
PAN CardFile: D C LLP Pan Card.pdf24 Aug 2021

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
R M Dhariwal Township Tembhurni PlottingPost - Tembhurni Tal - madha Dist - solapur193CompletedDec 2019Dec 2019

How this compares with Buldana

35%of this project is bookeddistrict median 0%
10%of Buldana projects moved their completion datethis one has not
46%of Buldana registrations have lapsed or been cancelledthis one is on the register

Computed across the 58 Buldana projects on ReraGenie, from their own filings.

Keep Chhoriya Future City - Malkapur Plotting on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near At/Post - Malkapur , Buldana58 in Buldana

Builder: Dhariwal And Chhoriya Developers LLP

Dhariwal And Chhoriya Developers LLP has 11 registrations on MahaRERA, including R M Dhariwal Greens Yavatmal Phase 1 and R M Dhariwal Greens Yavatmal Phase - 2. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Buldana district page.

Frequently asked questions

What are my rights if Chhoriya Future City - Malkapur Plotting is delayed beyond 31 Dec 2029?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Chhoriya Future City - Malkapur Plotting?

The registered promoter entity is Dhariwal And Chhoriya Developers LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Chhoriya Future City - Malkapur Plotting?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Chhoriya Future City - Malkapur Plotting?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Chhoriya Future City - Malkapur Plotting?

The professionals named in the filing: Architect: Mr Kunal P Patil Patil; Engineer: IMPower Projects - Mr Manish Pande; Engineer: Avinash Wadgaonkar; Chartered Accountant: Ayush S. Kankariya. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Chhoriya Future City - Malkapur Plotting?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Chhoriya Future City - Malkapur Plotting. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Chhoriya Future City - Malkapur Plotting to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.