KBR PRIME

By KBR HOMES INDIA PRIVATE LIMITED

RG-KA-94165 · RERA PRM/KA/RERA/1250/304/PR/031024/007112 · Last updated on RERA Karnataka portal: 15 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Mar 2029Possession promisedno revision filed
5 of 17Construction stages donefurthest along: RCC or MS Framed structure, 95%
120 of 124Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 126 documents Report an error

KBR PRIME is a Residential/Group Housing project by KBR HOMES INDIA PRIVATE LIMITED in Bengaluru Rural, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1250/304/PR/031024/007112 on 3 Oct 2024. Possession is promised by 31 Mar 2029. 4 of the 124 units on this registration are recorded sold or booked, and 5 of 17 construction stages are filed complete.

At a glance

Project

  • NameKBR PRIME
  • TypeResidential/Group Housing
  • Location
    • Hosakote
    • Bengaluru Rural
  • PincodeNot stated
  • RERA no.PRM/KA/RERA/1250/304/PR/031024/007112
  • ReraGenie IDRG-KA-94165

Builder

  • NameKBR HOMES INDIA PRIVATE LIMITED
  • Entity typeCompany
  • CINU70102KA2012PTC064637
  • GSTIN29AAECK8215C1ZN
  • Authorized SignatoryKONDURU BABU RAJU
  • DirectorKONDURU BABU RAJU
  • DirectorsKONDURU BABU RAJU, KONDURU RAJESWARI
  • Project HeadKONDURU BABU RAJU
  • Other registrations1 more →
  • Declared earlier projects2 →

Key dates

this monthRegisteredOct 2024PromisedMar 2029

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on3 Oct 2024
  • Promised completion31 Mar 2029
  • Revised completionNone
  • Buildings1 building record
  • Documents filed126 files

Current status

3%4 of 124 units booked
3.5%Of the estimated cost spent so far

Figures as on 15 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
KBR PRIME---1240124

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 15 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 17 construction stages are filed complete. The stage furthest along is RCC or MS Framed structure, at 95%.

Building: 56% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Upto Plinth Level100%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)100%
Retaining wall (All types)100%
RCC or MS Framed structure95%
Masonry Construction85%
Plastering inside , outside & Ceiling75%
Joinery: Doors, Windows, Ventilators etc65%
Basic work of Water supply, Sanitary and Electrification55%
Dadoing, Skirting, Flooring, Tiles work (All types)45%
Railing and Grill fixing35%
Electrification, Water supply and Sanitary Finishing0%
Painting0%
Fire prevention and fire fighting fitting and fixture with network0%
Weather Proof work(tile,concrete)Not applicable
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work0%
Internal and External work including landscapes as per sanctioned drawings0%

Progress on shared amenities40

As on 15 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes90%
Sewage and Drainage SystemYes90%
Water conservation/rain water harvesting/recharge of ground waterYes90%
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Solid waste management and disposalNoNot applicable
Emergency Evacuation servicesNoNot applicable
Electricity supply transformer and substationYes90%
Internal Roads & FootpathsNoNot applicable
Storm water drainsNoNot applicable
Use of renewable energyNoNot applicable
Sewage Treatment Plant (STP)NoNot applicable
Parks & Tree plantingNoNot applicable
Street LightingNoNot applicable
ElectricityYes90%
Smart Home AutomationNoNot applicable
CCTV SurveillanceNoNot applicable
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolNoNot applicable
GymNoNot applicable
ParksNoNot applicable
Power BackupNoNot applicable
Piped GasNoNot applicable
Water and SanitationYes90%
Air ConditioningNoNot applicable
StaircasesYes100%
LiftsYes80%
Corridor/LobbiesYes100%
Fire escapesYes100%
Common entrance and exit for the building/common portico/foyer/verandahYes100%
BasementNoNot applicable
TerraceYes0%
Outer WallNoNot applicable
Open parking areasNoNot applicable
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable
Common storage spacesNoNot applicable

Land and ownership1

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Named landowners1
LandownerVillageDistrict
Mr. V CHANDRASHEKAR (Authorized Signatory of M/s. V R HOLDINGS PRIVATE LIMITED)--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 29.29 cr
Cost incurredRs 1.02 cr
Spent of the estimate3.49%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 29.29 crRs 1.02 cr

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVENKATESH R
EngineerRACHAN G
Chartered AccountantSUPRIYA B

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed126

As listed on the registration, under the names the promoter filed them with; the newest 80 of 126 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1250/304/PR/031024/007112 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: FORM 4 CA KBR PRIME - QU - SEP 26_signed copy.pdf15 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: FORM 5 ARCH KBR PRIME - QU - SEP 26_signed copy.pdf15 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: FORM 6 ENGR KBR PRIME - QU - SEP 26_signed copy.pdf15 Oct 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: FORM 4 CA KBR PRIME - QU - JUNE 26_signed copy.pdf15 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: FORM 5 ARCH KBR PRIME - QU - JUNE 26_signed copy.pdf15 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: FORM 6 ENGR KBR PRIME - QU - JUNE 26_signed copy.pdf15 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: FORM 4 CA KBR PRIME - QU - MARCH 26_signed copy.pdf15 Apr 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: FORM 5 ARCH KBR PRIME - QU - MARCH 26_signed copy.pdf15 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: FORM 6 ENGR KBR PRIME - QU - MARCH 26_signed copy.pdf15 Apr 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: FORM 4 CA KBR PRIME - QU - DEC 25_signed copy.pdf31 Mar 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: FORM 5 ARCH KBR PRIME - QU - DEC 25_signed copy.pdf31 Mar 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: FORM 6 ENGR KBR PRIME - QU - DEC 25_signed copy.pdf31 Mar 2026
KBR ELITE OC DATED 23-10-2020 (previous project)File: KBR ELITE OC DATED 23-10-2020 (previous project).pdf20 Sep 2024
KBR NAVARATHNA RESIDENCY OC DATED 14-08-2023 (previous project)File: KBR NAVARATHNA RESIDENCY OC DATED 14-08-2023 (previous project).pdf20 Sep 2024
KONDURU BABU RAJU ITRFile: KONDURU BABU RAJU ITR.pdf20 Sep 2024
KONDURU RAJESWARI ITRFile: KONDURU RAJESWARI ITR.pdf20 Sep 2024
Annual Audit & QU Declaration - KBR PRIMEFile: Annual Audit & QU Declaration - KBR PRIME.jpg20 Sep 2024
Source of Funds Declaration - KBR PRIMEFile: Source of Funds Declaration - KBR PRIME.jpg20 Sep 2024
Auditor & Director Reports for 3 Years - FINANCIALS OF THE COMPANYFile: Auditor & Director Reports for 3 Years.pdf20 Sep 2024
BS & PL & ITR for 3 Years - FINANCIALS OF THE COMPANYFile: BS & PL & ITR for 3 Years.pdf20 Sep 2024
CA REG Self Attested CopyFile: CA REG Self Attested Copy.jpeg23 Jul 2024
CA F1 CA - KBR PRIME signed copyFile: CA F1 CA - KBR PRIME signed copy.pdf29 Jun 2024
ARCH F2 Architect - KBR PRIME signed copyFile: ARCH F2 Architect - KBR PRIME signed copy.pdf29 Jun 2024
CDP PLAN DemarcatedFile: CDP PLAN Demarcated.jpg29 Jun 2024
Google DemarcatedFile: Google Demarcated.jpg29 Jun 2024
KBR PRIME AREA STATEMENT signed copyFile: KBR PRIME AREA STATEMENT signed copy.pdf29 Jun 2024
KBR PRIME PLAN APPROVAL AND CCFile: KBR PRIME PLAN APPROVAL AND CC.pdf29 Jun 2024
KBR PRIME SINGLE SITE APPROVALFile: KBR PRIME SINGLE SITE APPROVAL.pdf29 Jun 2024
KBR PRIME SINGLE SITE PLAN APPROVALFile: KBR PRIME SINGLE SITE PLAN APPROVAL.pdf29 Jun 2024
KHATHA - V R HOLDINGSFile: KHATHA - V R HOLDINGS.pdf29 Jun 2024
Village Map DemarcatedFile: Village Map Demarcated.jpg29 Jun 2024
AGREEMENT FOR SALE - KBR PRIMEFile: AGREEMENT FOR SALE - KBR PRIME.pdf13 Jun 2024
ALLOTMENT LETTER - KBR PRIMEFile: ALLOTMENT LETTER - KBR PRIME.pdf13 Jun 2024
Auditor & Director Reports for 3 YearsFile: Auditor & Director Reports for 3 Years.pdf13 Jun 2024
BS & PL & ITR for 3 YearsFile: BS & PL & ITR for 3 Years.pdf13 Jun 2024
Common Areas details Engineer signed copyFile: Common Areas details Engineer signed copy.pdf13 Jun 2024
EC till DateFile: EC till Date.pdf13 Jun 2024
F6 Engineer - KBR PRIME signed copyFile: F6 Engineer - KBR PRIME signed copy.pdf13 Jun 2024
KBR PRIME - GUIDELINE VALUE CALCULATION signed copyFile: KBR PRIME - GUIDELINE VALUE CALCULATION signed copy.pdf13 Jun 2024
KBR PRIME AREA STATEMENT signed copyFile: KBR PRIME AREA STATEMENT signed copy.pdf13 Jun 2024
KBR PRIME ESTIMATIONFile: KBR PRIME ESTIMATION.pdf13 Jun 2024
KBR PRIME NOC FOR WATER SUPPYFile: KBR PRIME NOC FOR WATER SUPPY.pdf13 Jun 2024
KBR PRIME PLAN APPROVAL AND CCFile: KBR PRIME PLAN APPROVAL AND CC.pdf13 Jun 2024
KBR PRIME PRE STRUCTURAL STABILITY CERTIFICATEFile: KBR PRIME PRE STRUCTURAL STABILITY CERTIFICATE.pdf13 Jun 2024
KBR PRIME RTC 2023-24File: KBR PRIME RTC 2023-24.pdf13 Jun 2024
KHATHA - V R HOLDINGSFile: KHATHA - V R HOLDINGS.pdf13 Jun 2024
KOLATHUR MASTER CDPFile: KOLATHUR MASTER CDP.pdf13 Jun 2024
KOLATHUR VILLAGE MAPFile: KOLATHUR VILLAGE MAP.pdf13 Jun 2024
RTC, survey 121/2-
Mutation, survey 121/2-
Encumbrance Certificate, survey 121/2-
Conversion/Alienation Order, survey 121/2-
Sale/Title/Gift Deed, survey 121/2-
JDA, survey 121/2-
Khatha, survey 121/2-
Registration CertificateFile: KBR HOMES Certificate of Incorporation-290612.pdf-
Memorandum of AssociationFile: KBR HOMES - MoA.pdf-
Article of AssociationFile: KBR HOMES - AoA.pdf-
Organization StructureFile: Organisation chart of KBR HIPL.pdf-
Certificate issued by CA Form 1File: CA F1 CA - KBR PRIME signed copy.pdf-
Certificate issued by Architect Form 2File: ARCH F2 Architect - KBR PRIME signed copy.pdf-
Certificate issued by Engineer Form 3File: ENGR F3 Engineer - KBR PRIME signed copy.pdf-
Project Chartered Accountant-
Project Engineer-
Project Architect-
AffidavitFile: AFFIDAVIT NON LITIGATION.pdf-
Certificate from Chartered AccountFile: CA F1 CA - KBR PRIME signed copy.pdf-
Balance Sheet 2022 - 2023File: Bal Sheet P&L 2022-23.pdf-
Balance Sheet 2021 - 2022File: Bal Sheet P&L 2021-22.pdf-
Balance Sheet 2020 - 2021File: Bal Sheet P&L 2020-21.pdf-
Audited Profit and Loss Statement 2022 - 2023File: Bal Sheet P&L 2022-23.pdf-
Audited Profit and Loss Statement 2021 - 2022File: Bal Sheet P&L 2021-22.pdf-
Audited Profit and Loss Statement 2020 - 2021File: Bal Sheet P&L 2020-21.pdf-
Director's Report 2022 - 2023File: Directors Report 2022-23.pdf-
Director's Report 2021 - 2022File: Directors Report 2021-22.pdf-
Director's Report 2020 - 2021File: Directors Report 2020-21.pdf-
Cash Flow Statement 2022 - 2023File: Auditors Report 2022-23.pdf-
Cash Flow Statement 2021 - 2022File: Auditors Report 2021-22.pdf-
Auditor's Report 2022 - 2023File: Auditors Report 2022-23.pdf-
Auditor's Report 2021 - 2022File: Auditors Report 2021-22.pdf-

How this compares with Bengaluru Rural

3%of this project is bookeddistrict median 45%
20%of Bengaluru Rural projects moved their completion datethis one has not
0%of Bengaluru Rural registrations are shown as withdrawn or revokedthis one is not

Computed across the 650+ Bengaluru Rural projects on ReraGenie, from their own filings.

Keep KBR PRIME on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Rural650+ in Bengaluru Rural

Builder: KBR HOMES INDIA PRIVATE LIMITED

KBR HOMES INDIA PRIVATE LIMITED has 2 registrations on RERA Karnataka, including KBR PRIME and KBR NAVARATHNA RESIDENCY. Its filings declare 2 earlier projects, 2 of them declared completed. Read the full track record. See more projects on the Bengaluru Rural district page.

Frequently asked questions

What are my rights if KBR PRIME is delayed beyond 31 Mar 2029?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of KBR PRIME?

The registered promoter entity is KBR HOMES INDIA PRIVATE LIMITED, a company as per the filing. Its CIN U70102KA2012PTC064637 and GSTIN 29AAECK8215C1ZN can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in KBR PRIME?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at KBR PRIME?

The professionals named in the filing: Architect: VENKATESH R; Engineer: RACHAN G; Chartered Accountant: SUPRIYA B. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in KBR PRIME?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About KBR PRIME. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save KBR PRIME to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.