Kartikya Paradise - Building No.1
RG-MH-59694 · RERA P52000017158 · Last updated on MahaRERA portal: 11 Oct 2025
Source: official MahaRERA filing
Red flags
- Completion date moved by 20 months
- 3 extensions taken
Clear
- No litigation declared
- No complaints on record
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Kartikya Paradise - Building No.1 is a Residential / Group Housing project by Kartikya Spaces in Raigarh, Maharashtra, registered with MahaRERA as P52000017158 on 17 Jul 2018. The registration is recorded completed; possession was promised by 5 Aug 2024. The completion date has moved by 20 months from the original filing. 70 of the 70 units on this registration are recorded sold or booked, and 6 of 11 construction stages are filed complete.
At a glance
Project
- NameKartikya Paradise - Building No.1
- TypeResidential / Group Housing
- Location
- Village Gundge
- Karjat
- Raigarh
- 401201
- Pincode401201
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52000017158
- ReraGenie IDRG-MH-59694
Builder
- NameKartikya Spaces
- Entity typePartnership
- PartnerSUNIL CHAMANANLAL GUPTA
- Declared earlier projects1 →
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on17 Jul 2018
- Promised completion5 Aug 2024
- Revised completionRevised to 5 Aug 2024 (originally 30 Dec 2022)
- Buildings1 building record
- Documents filed91 files
Current status
Figures as on 11 Oct 2025, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Kartikya Paradise - Building No 1 | NA | 9 | 7 | 70 | 0 | 70 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 11 Oct 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
6 of 11 construction stages are filed complete. The stage furthest along is Sanitary Fittings within the flats / premises, at 95%.
Kartikya Paradise - Building No 1: 85% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 95% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 95% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 95% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 50% |
Progress on shared amenities16
As on 11 Oct 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 80% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 50% |
| Street Lighting | Yes | 50% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | Yes | 0% |
| Arrangement area and recreational open space | Yes | 0% |
Parking filed27
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Shri Satish Manohar (M/s Vastukalp) |
| Engineer | Mr. Yateesh Tare (M/S Vastukalp) |
| Chartered Accountant | Shah & Vejani |
| Chartered Accountant | Darshan Kishor Shah |
| Partner | Role in project |
|---|---|
| Kartikya Spaces | - |
Extensions applied for3
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterDue to Covid 19 pandemic, the project construction got delayed and we seek extension of 4 months to complete the project.
Reason as filed by the promoterDue to covid related pandemic, there is a delay in the construction of project
Reason as filed by the promoterThe project got delayed due to delayed completion of certain part of the project by the appointed civil contractor.
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 12 May 2018 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 1 Jun 2018 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 12 May 2018 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 12 May 2018Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 24 Feb 2025
Documents filed91
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 91 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Occupational CertificateFile: oc verification kartikya.pdf | 11 Oct 2025 |
| Occupational CertificateFile: Plans gray.pdf | 10 Oct 2025 |
| Occupational CertificateFile: OC AND LETTER HIGHLIGHTED.pdf | 7 Oct 2025 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: karjat municipal council paper.pdf | 24 Feb 2025 |
| Architect’s Certificate on Completion of Project (Form 4)File: FORM 4 Signed New.pdf | 23 Dec 2024 |
| Other - TechnicalFile: Email Proof OC.pdf | 23 Dec 2024 |
| Architect’s Certificate on Completion of Project (Form 4)File: FORM 4 Signed New.pdf | 20 Nov 2024 |
| Architect’s Certificate on Completion of Project (Form 4)File: FORM 4 Signed New.pdf | 20 Nov 2024 |
| Architect’s Certificate on Completion of Project (Form 4)File: FORM 4.pdf | 6 Nov 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Rera.pdf | 8 Oct 2024 |
| Certificates of CA (Form 3)File: Form 3 Final Signed.pdf | 8 Oct 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER Certificate Rera.pdf | 8 Oct 2024 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC.pdf | 8 Oct 2024 |
| Other - TechnicalFile: FORM 4.pdf | 8 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 Kartikya Paradise_2023-24 Signed.pdf | 8 Oct 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 OF KARJAT (KARTIKYA PARADISE) (1).pdf | 2 May 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 OF KARJAT (KARTIKYA PARADISE).pdf | 2 May 2024 |
| Certificates of CA (Form 3)File: Form 3 Q4 Final Signed.pdf | 2 May 2024 |
| Proforma of Agreement for saleFile: AFS.pdf | 19 Apr 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Rera- 30-12-23.pdf | 31 Jan 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER Certificate Rera - 30-12-23.pdf | 31 Jan 2024 |
| Certificates of CA (Form 3)File: Form 3 Final Q3.pdf | 31 Jan 2024 |
| Declaration in FORM BFile: Form B Extension.pdf | 20 Dec 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A 2022.pdf | 20 Dec 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A 2022 Final.pdf | 20 Dec 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A 2023.pdf | 20 Dec 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A 2023 Final.pdf | 20 Dec 2023 |
| Disclosure of sold/ booked inventoryFile: Circular No 29_Paradise Signed.pdf | 20 Dec 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 KS.pdf | 20 Dec 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf | 10 Nov 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf | 10 Nov 2023 |
| Certificates of CA (Form 3)File: Form 3 Signed.pdf | 10 Nov 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architects Certificate 30-06-23.pdf | 23 Aug 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Certificate 30-06-23.pdf | 23 Aug 2023 |
| Certificates of CA (Form 3)File: Form 3 Signed.pdf | 23 Aug 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate 31-03-20.pdf | 5 Aug 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate 31-03-19.pdf | 5 Aug 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate 31-03-21.pdf | 5 Aug 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate 31-12-21.pdf | 5 Aug 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate 31-03-22.pdf | 5 Aug 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate 30-06-22.pdf | 5 Aug 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate 30-09-2022.pdf | 5 Aug 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate 31-12-22.pdf | 5 Aug 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate 31-03-23.pdf | 5 Aug 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate 31-03-2019.pdf | 5 Aug 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate 31-03-2020.pdf | 5 Aug 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate 31-03-2021.pdf | 5 Aug 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate 31-12-2021.pdf | 5 Aug 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate 31-03-2022.pdf | 5 Aug 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate 30-06-2022.pdf | 5 Aug 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate 30-09-22.pdf | 5 Aug 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate 31-12-2022.pdf | 5 Aug 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate 31-03-2023.pdf | 5 Aug 2023 |
| Certificates of CA (Form 3)File: Form 3 Signed.pdf | 5 Aug 2023 |
| Certificates of CA (Form 3)File: Form 3 Signed.pdf | 5 Aug 2023 |
| Certificates of CA (Form 3)File: Form 3 Signed.pdf | 5 Aug 2023 |
| Certificates of CA (Form 3)File: Form 3 (Q3) Signed.pdf | 5 Aug 2023 |
| Certificates of CA (Form 3)File: Form 3 (Q4) Signed.pdf | 5 Aug 2023 |
| Certificates of CA (Form 3)File: Form 3 (Q1) Signed.pdf | 5 Aug 2023 |
| Certificates of CA (Form 3)File: Form 3 Signed Final.pdf | 5 Aug 2023 |
| Certificates of CA (Form 3)File: Form 3 (Q3) Signed.pdf | 5 Aug 2023 |
| Certificates of CA (Form 3)File: Form 3 (Q4) Signed.pdf | 5 Aug 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: 3 Other.pdf | 19 Oct 2022 |
| OtherFile: Form 5 Kartikya Paradise.pdf | 29 Sep 2022 |
| Proforma of Allotment letterFile: Final and latest Agreement for Sale.pdf | 7 Apr 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A.pdf | 16 Feb 2022 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Sold and Unsold Units.pdf | 16 Feb 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5_18-19.pdf | 11 Feb 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5_19-20.pdf | 11 Feb 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form-5.pdf | 30 Sep 2021 |
| Annual Audit Report of Statutory CA (Form 5)File: CA Certificate - FY 20-21 (E-signed).pdf | 28 Sep 2021 |
| Declaration about Commencement CertificateFile: Declaration about CC_Kartikya Paradise.pdf | 3 Aug 2021 |
| Annual Audit Report of Statutory CA (Form 5)File: CA Cerficate Kartikya Paradise.pdf | 30 Sep 2020 |
| Annual Audit Report of Statutory CA (Form 5)File: Form5 _Kartikya Paradise_compressed.pdf | 28 Sep 2019 |
| Proforma of Allotment letterFile: Final Agreement for Sale for RERA.pdf | 9 Jul 2018 |
| OtherFile: Vastukalp Certiificate for Plot area FSI.pdf | 4 Jul 2018 |
| Certificates of CA (Form 3)File: Form 3.pdf | 12 Jun 2018 |
| Layout approvalFile: LAYOUT PLAN 2.pdf | 1 Jun 2018 |
| Layout approvalFile: Layout 1 .pdf | 1 Jun 2018 |
| Copy of Layout Approval (in case of layout)File: LAYOUT PLAN 2.pdf | 1 Jun 2018 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| Kartikya Kunj | Plot No.8 Sector 3 Karanjade Panvel | 22 | Completed | Jan 2015 | Late, Jul 2016 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Raigarh
Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.
Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 91 filed documents as one ZIP, foldered, with a manifest
Keep Kartikya Paradise - Building No.1 on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Karjat5,900+ in Raigarh
Filed coordinates, straight-line distance. 153 registered projects within 2 km.
ARIANA
Mansarovar Estate Builders LLP
Sunteck Beach Residences 2
SUNTECK REAL ESTATES PRIVATE LIMITED
SHRIPAL SATTVA BLDG. 2
SHRIPAL SATTVA LLP
Sunteck Beach Residences 1
SUNTECK REAL ESTATES PRIVATE LIMITED
Sunteck Beach Residences 4
SUNTECK REAL ESTATES PRIVATE LIMITED
Milagrace Aura
Milagrace Developers
See every Raigarh project, with the district possession charts
Builder: Kartikya Spaces
Kartikya Spaces has 1 registration on MahaRERA, including Kartikya Paradise - Building No.1. Its filings disclose 1 earlier MahaRERA project: declares 0 of 1 past projects completed on time. Read the full track record. See more projects on the Raigarh district page.
Frequently asked questions
What are my rights if Kartikya Paradise - Building No.1 is delayed beyond 5 Aug 2024?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Kartikya Paradise - Building No.1?
The registered promoter entity is Kartikya Spaces, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Kartikya Paradise - Building No.1?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Kartikya Paradise - Building No.1?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Kartikya Paradise - Building No.1?
The professionals named in the filing: Architect: Shri Satish Manohar (M/s Vastukalp); Engineer: Mr. Yateesh Tare (M/S Vastukalp); Chartered Accountant: Shah & Vejani; Chartered Accountant: Darshan Kishor Shah. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Kartikya Paradise - Building No.1?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback