ReraGenieLog inGet a buyer report

Home / Browse projects / Pune, Maharashtra / KAMBLE HEIGHTS

Registration lapsed No litigation declared Residential / Group Housing project

KAMBLE HEIGHTS

By SAMEER BASHIR JAMADAR

RG-MH-17389 · RERA P52100028939 · Last updated on MahaRERA portal: 7 Apr 2023

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 43 months past the filed date
  • 1 complaint at MahaRERA

Clear

  • No litigation declared
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Mar 2023Possession promised43 months past this date
4 of 11Construction stages donefurthest along: Staircases, 20%
1Complaints at MahaRERAon this registration
Jump to the 33 documents Report an error

KAMBLE HEIGHTS is a Residential / Group Housing project by SAMEER BASHIR JAMADAR in Pune, Maharashtra, registered with MahaRERA as P52100028939 on 15 Apr 2021. Possession was promised by 31 Mar 2023 and is now 43 months past that date. 1 complaint is on record with the regulator.

At a glance

Project

  • NameKAMBLE HEIGHTS
  • TypeResidential / Group Housing
  • Location
    • CTS NO 79/80/81/82 KAMBLE HEIGHTS YERWADA
    • YERWADA
    • Pune (M Corp.)
    • Pune City
    • Pune
    • 411006
  • Pincode411006
  • RERA no.P52100028939
  • ReraGenie IDRG-MH-17389

Builder

  • NameSAMEER BASHIR JAMADAR
  • Entity typeIndividual

Key dates

43 months past promisethis monthRegisteredApr 2021PromisedMar 2023

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on15 Apr 2021
  • Promised completion31 Mar 2023
  • Revised completionNone
  • Buildings1 building record
  • Documents filed33 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
KAMBLE HEIGHTSNA80000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 7 Apr 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 11 construction stages are filed complete. The stage furthest along is Staircases, at 20%.

KAMBLE HEIGHTS: 38% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks20%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 7 Apr 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingNoNot applicable
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed11

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots11
Closed/Covered1
Open Space10

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area318 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on19 Jun 2026

Approvals and building plan

Sanctioning authorityPune Muncipal Corporation
Permissible FSI778.33
Proposed, not sanctioned546 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branch270/2 NAVI KHADKI YERWADA 411006

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectRAHIIL SHAIKH
EngineerBHUSHAN JAIN
Chartered AccountantPRAKASH SUNEJA
PartnerRole in project
SAMEER BASHIR JAMADAR-

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC12503855shrikant subhash shindeDelay In Possession03/11/2025

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 8 Apr 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 8 Apr 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 5 Apr 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 5 Apr 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed33

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Disclosure of sold/ booked inventoryFile: Document 57.pdf7 Apr 2023
Building plan approvalFile: HPSCANNER6308_compressed.pdf5 Apr 2023
Building Plan Approval / NA Order for plotted developmentFile: HPSCANNER6308_compressed.pdf5 Apr 2023
Commencement Certificates / NA Order for plotted developmentFile: Document 56_compressed.pdf5 Apr 2023
Building plan approvalFile: Document 3.pdf27 Dec 2022
Building Plan Approval / NA Order for plotted developmentFile: Document 3.pdf27 Dec 2022
OtherFile: property card_compressed.pdf9 Apr 2021
Layout approvalFile: declration.pdf8 Apr 2021
Copy of the legal title reportFile: sreportnew.pdf8 Apr 2021
Copy of Layout Approval (in case of layout)File: declration.pdf8 Apr 2021
Copy of the legal title reportFile: searchrepoert new.pdf7 Apr 2021
Layout approvalFile: BUILDING PLAN_compressed.pdf6 Apr 2021
Building plan approvalFile: HPSCANNER3278 (2)_compressed (1).pdf6 Apr 2021
Copy of Layout Approval (in case of layout)File: BUILDING PLAN_compressed.pdf6 Apr 2021
Building Plan Approval / NA Order for plotted developmentFile: HPSCANNER3278 (2)_compressed (1).pdf6 Apr 2021
Layout approvalFile: LAYOUT.pdf28 Mar 2021
Copy of the legal title reportFile: SEARCH REPORT.pdf28 Mar 2021
Copy of Layout Approval (in case of layout)File: LAYOUT.pdf28 Mar 2021
Commencement Certificates / NA Order for plotted developmentFile: commencement certificate Yerwada plan_compressed.pdf28 Mar 2021
Proforma of Allotment letterFile: SAMPLEAGREEMENT.pdf25 Mar 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM2.pdf24 Mar 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM3COMP.pdf24 Mar 2021
Layout approvalFile: 02-04-2018_79 Yerwada Sketch_Saleable-Model-merged.pdf16 Mar 2021
Details of encumbrancesFile: DECLARATION2.pdf16 Mar 2021
Copy of Layout Approval (in case of layout)File: 02-04-2018_79 Yerwada Sketch_Saleable-Model-merged.pdf16 Mar 2021
Declaration in FORM BFile: Annexure b.pdf16 Mar 2021
Building plan approvalFile: HPSCANNER3278 (2)_compressed.pdf13 Mar 2021
PAN CardFile: Pan Card Sameir Sir.pdf13 Mar 2021
Copy of the legal title reportFile: search and title report_compressed.pdf13 Mar 2021
Building Plan Approval / NA Order for plotted developmentFile: HPSCANNER3278 (2)_compressed.pdf13 Mar 2021
Commencement Certificates / NA Order for plotted developmentFile: commencement certificate Yerwada plan_compressed.pdf13 Mar 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM1 ARCH CERTIFICATE.pdf13 Mar 2021
OtherFile: yerewada agreement samir sir_compressed.pdf13 Mar 2021

How this compares with Pune

26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep KAMBLE HEIGHTS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near YERWADA13,700+ in Pune

Builder: SAMEER BASHIR JAMADAR

SAMEER BASHIR JAMADAR has 1 registration on MahaRERA, including KAMBLE HEIGHTS. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that KAMBLE HEIGHTS shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if KAMBLE HEIGHTS is delayed beyond 31 Mar 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of KAMBLE HEIGHTS?

The registered promoter entity is SAMEER BASHIR JAMADAR, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in KAMBLE HEIGHTS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against KAMBLE HEIGHTS?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for KAMBLE HEIGHTS?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at KAMBLE HEIGHTS?

The professionals named in the filing: Architect: RAHIIL SHAIKH; Engineer: BHUSHAN JAIN; Chartered Accountant: PRAKASH SUNEJA. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in KAMBLE HEIGHTS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About KAMBLE HEIGHTS. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save KAMBLE HEIGHTS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.