Home / Browse projects / Pune, Maharashtra / K K SUNDARBAN BUILDING H

Registered No litigation declared Residential / Group Housing project

K K SUNDARBAN BUILDING H

By K K DEVELOPERS

RG-MH-21136 · RERA P52100004320 · Last updated on MahaRERA portal: 20 Nov 2025

Source: official MahaRERA filing

Red flags

  • Completion date moved by 96 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedmoved 96 months from the original
7 of 11Construction stages donefurthest along: Sanitary Fittings within the flats /..., 65%
0Complaints at MahaRERAon this registration
Jump to the 104 documents Report an error

K K SUNDARBAN BUILDING H is a Residential / Group Housing project by K K DEVELOPERS in Pune, Maharashtra, registered with MahaRERA as P52100004320 on 9 Aug 2017. Possession is promised by 31 Dec 2026. The completion date has moved by 96 months from the original filing.

At a glance

Project

  • NameK K SUNDARBAN BUILDING H
  • TypeResidential / Group Housing
  • Location
    • Girim
    • Daund
    • Pune
    • 413801
  • Pincode413801
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100004320
  • ReraGenie IDRG-MH-21136

Builder

  • NameK K DEVELOPERS
  • Entity typePartnership
  • PartnerSHRIKANT LAXMAN KADAM
  • Other registrations8 more →
  • Completed2 of 9
  • No longer live2 lapsed, de-registered or revoked
  • Declared earlier projects1 →

Key dates

this monthRegisteredAug 2017First promiseDec 2018Revised toDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on9 Aug 2017
  • Promised completion31 Dec 2026
  • Revised completionRevised to 31 Dec 2026 (originally 31 Dec 2018)
  • Buildings1 building record
  • Documents filed104 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
HNA66000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 20 Nov 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

7 of 11 construction stages are filed complete. The stage furthest along is Sanitary Fittings within the flats / premises, at 65%.

H: 70% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises65%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 20 Nov 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes50%
Open ParkingYes0%

Parking filed9

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots9
Closed/Covered1
Open Space8

Land and ownership3

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area21,200 sq m
Land owned byThe promoter, with other names on the file
Named landowners3
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on5 Sep 2025
LandownerVillageDistrict
SUNIL ASHOK GHULEMANJARI BkPune
CHANDRAKANT SHIVAJIRAO GHULEPune (M Corp.)Pune
KISHOR GANDHIPune (M Corp.)Pune

Approvals and building plan

Permissible FSI2264.98
Proposed, not sanctioned2,265 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchTHITE WASTI, MUNDHAVA BYPASS, KHARADI PUNE 411014

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMANOHAR YERAWAR YERAWAR
EngineerRajesh Munot
PartnerRole in project
K K DEVELOPERS-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100024464Dec 2018 → Dec 2026

Reason as filed by the promoterAt the time of application there was typographical error occurred in the field of column proposed date of completion and revised proposed date of completion mentioned as 31/12/2018 instead it should be read as 3l/12/2021.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 31 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 31 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 31 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 16 Nov 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2026

Documents filed104

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 104 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 1File: Form1 - Architect Certificate dated 30-09-2025.pdf20 Nov 2025
Form 2File: FORM 2 - ENGINEER CERTIFICATE DATED 30-09-2025.pdf20 Nov 2025
Form 3File: Form3 CA Certificate 30-09-2025.pdf20 Nov 2025
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD 30-09-2025.pdf20 Nov 2025
Form 1File: Form1 Architect Certificate dated 30-06-2025.pdf20 Nov 2025
Form 2File: form 2- Engineer Crtificate dated 30-06-2025.pdf20 Nov 2025
Form 3File: Form3-CA Certificate dated 30-06-2025.pdf20 Nov 2025
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD 30-06-2025.pdf20 Nov 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCH CERT SEPT.pdf19 Oct 2024
Certificates of CA (Form 3)File: CA CERT SEPT.pdf19 Oct 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENG CERT SEPT.pdf19 Oct 2024
Disclosure of sold/ booked inventoryFile: Booking Inventory K K Developers (1).pdf19 Oct 2024
Declaration in FORM BFile: FORM B Extension.pdf6 Aug 2024
Disclosure of sold/ booked inventoryFile: 31March23 -Sold -Unsold Inventory.pdf29 Jul 2024
Disclosure of sold/ booked inventoryFile: 30June23 -Sold Unsold Inventory.pdf29 Jul 2024
Disclosure of sold/ booked inventoryFile: 30Sept23 - Sold Unsold inventory.pdf29 Jul 2024
Disclosure of sold/ booked inventoryFile: 31Dec23 Sold- Unsold Inventory.pdf29 Jul 2024
Disclosure of sold/ booked inventoryFile: 31Mar24 - Sold Unsold Inventory.pdf29 Jul 2024
Disclosure of sold/ booked inventoryFile: 30June24 -Sold unsold inventory.pdf29 Jul 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 Dec 21.pdf26 Jul 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM - 1 Dec.pdf26 Jul 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 MAR.pdf26 Jul 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 JUN 22.pdf26 Jul 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 Sept 22.pdf26 Jul 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 DEC.pdf26 Jul 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM - 1 MAR 2023.pdf26 Jul 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM - 1 JUN 2023.pdf26 Jul 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM - 1 SEPT 2023.pdf26 Jul 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM - 1 MAR 2023.pdf26 Jul 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM - 1 MAR 2024.pdf26 Jul 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form1 JUN 2024_compressed.pdf26 Jul 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM - 2 31-03-2020.pdf26 Jul 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM - 2 31-12-2020.pdf26 Jul 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM - 2 31-03-2021.pdf26 Jul 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM - 2 31-12-2021.pdf26 Jul 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM - 2 31-03-2022.pdf26 Jul 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM - 2 30-06-2022.pdf26 Jul 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM - 2 30-09-2022.pdf26 Jul 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM - 2 31-12-2022.pdf26 Jul 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM - 2 31-03-2023.pdf26 Jul 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM - 2 30-06-2023.pdf26 Jul 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM - 2 30-09-2023.pdf26 Jul 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM - 2 31-12-2023.pdf26 Jul 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM - 2 31-03-2024.pdf26 Jul 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 30June24 Form2 Engineer Certificate.pdf26 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: FORM - 2A 2017 - 2018.pdf26 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: FORM - 2A 2018 - 2019.pdf26 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: FORM - 2A 2019 - 2020.pdf26 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FORM - 2A 2020 -2021.pdf26 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FORM - 2A 2021 - 2022.pdf26 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM - 2A 2022 -2023.pdf26 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM - 2A 2023 -2024.pdf26 Jul 2024
Certificates of CA (Form 3)File: FORM - 3 DEC 2020.pdf26 Jul 2024
Certificates of CA (Form 3)File: FORM - 3 MAR 201.pdf26 Jul 2024
Certificates of CA (Form 3)File: FORM - 3 DEC.pdf26 Jul 2024
Certificates of CA (Form 3)File: FORM - 3 MAR 2022.pdf26 Jul 2024
Certificates of CA (Form 3)File: FORM - 3 JUN 2022.pdf26 Jul 2024
Certificates of CA (Form 3)File: FORM - 3 Sept 2022.pdf26 Jul 2024
Certificates of CA (Form 3)File: FORM - 3 DEC 2022.pdf26 Jul 2024
Certificates of CA (Form 3)File: FORM - 3 MAR 2023.pdf26 Jul 2024
Certificates of CA (Form 3)File: FORM - 3 JUN 2023.pdf26 Jul 2024
Certificates of CA (Form 3)File: FORM - 3 SEPT 2023.pdf26 Jul 2024
Certificates of CA (Form 3)File: FORM - 3 DEC 2020.pdf26 Jul 2024
Certificates of CA (Form 3)File: FORM - 3 DEC 2023.pdf26 Jul 2024
Certificates of CA (Form 3)File: FORM - 3 MAR 2024.pdf26 Jul 2024
Certificates of CA (Form 3)File: FORM-3JUN 2024_compressed.pdf26 Jul 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: FORM - 5 2019 to 2020.pdf26 Jul 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM - 5 2020 to 2021.pdf26 Jul 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM - 5 2021 to 2022.pdf26 Jul 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM - 5 2022 to 2023.pdf26 Jul 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM - 5 2021 to 2022.pdf26 Jul 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM - 5 2023 to 2024.pdf26 Jul 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect's Certificate ( Form 1) 21-05-2018-1.pdf20 Sep 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect's Certificate ( Form 1) 20-05-2019-2.pdf20 Sep 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect's Certificate ( Form 1) 28-01-2020-3.pdf20 Sep 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: FORM 5 (ANNUAL REPORT ON STATEMENT OF ACCOUNTS) 12-02-2020-1.pdf20 Sep 2023
Certificates of CA (Form 3)File: H 17-18.pdf26 Feb 2020
Certificates of CA (Form 3)File: H 18-19.pdf26 Feb 2020
Certificates of CA (Form 3)File: H 19-20 till Decemeber.pdf26 Feb 2020
Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: H 17-18 Form 5.pdf26 Feb 2020

How this compares with Pune

26%of Pune projects moved their completion datethis one moved by 96 months
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep K K SUNDARBAN BUILDING H on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Girim13,700+ in Pune

2 kmK K SUNDARBAN BUILDING HCompleted 12Lapsed / revoked 12Other 2Dot size: filed unitsN

Filed coordinates, straight-line distance. 26 registered projects within 2 km.

Builder: K K DEVELOPERS

K K DEVELOPERS has 9 registrations on MahaRERA, including K K HEIGHTS and MORAYA HEIGHTS. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if K K SUNDARBAN BUILDING H is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of K K SUNDARBAN BUILDING H?

The registered promoter entity is K K DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in K K SUNDARBAN BUILDING H?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for K K SUNDARBAN BUILDING H?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at K K SUNDARBAN BUILDING H?

The professionals named in the filing: Architect: MANOHAR YERAWAR YERAWAR; Engineer: Rajesh Munot. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in K K SUNDARBAN BUILDING H?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About K K SUNDARBAN BUILDING H. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save K K SUNDARBAN BUILDING H to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.