Home / Browse projects / Bengaluru Urban, Karnataka / JR GARDEN RETREAT PHASE 3
JR GARDEN RETREAT PHASE 3
By JR Housing Developers Pvt Ltd
RG-KA-98847 · RERA PRM/KA/RERA/1251/308/PR/061222/005505 · Last updated on RERA Karnataka portal: 24 Nov 2022
Source: official RERA Karnataka filing
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
Saved.
JR GARDEN RETREAT PHASE 3 is a Plotted Development project by JR Housing Developers Pvt Ltd in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/308/PR/061222/005505 on 6 Dec 2022. Possession is promised by 2 Sep 2024.
At a glance
Project
- NameJR GARDEN RETREAT PHASE 3
- TypePlotted Development
- Location
- Anekal
- Bengaluru Urban
- 562106
- Pincode562106
- MapView location on Google Maps (as filed on RERA)
- RERA no.PRM/KA/RERA/1251/308/PR/061222/005505
- ReraGenie IDRG-KA-98847
Builder
- NameJR Housing Developers Pvt Ltd
- Entity typeCompany
- CINU07010KA2004PTC035108
- Authorized SignatoryS. Niranjan Kumar Reddy
- Managing DirectorS Jagadeeswara Reddy
- DirectorsS Prasanna Lakshmi, S Niranjan Kumar Reddy, Srilekha Singasani
- Project HeadNIRANJAN KUMAR REDDY
- Other registrations13 more →
- Declared earlier projects5 →
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on6 Dec 2022
- Promised completion2 Sep 2024
- Revised completionNone
- BuildingsNot stated in filing
- Documents filed119 files
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Land and ownership4
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| CHIKKA YELLAMMA | - | - |
| L JAGADEESH | - | - |
| BUGGANA PREETAM REDDY | - | - |
| JR URBAN INFRACON PVT LTD | - | - |
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Cost line | Estimated | Incurred |
|---|---|---|
| Estimated Cost of Construction as certified by Engineer | Rs 1.82 cr | - |
Certifying professionals and partners2
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Engineer | Arunachalam |
| Chartered Accountant | Jogi and Co |
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed119
As listed on the registration, under the names the promoter filed them with; the newest 80 of 119 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/308/PR/061222/005505 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Water supply NOC from local authorityFile: TMC NOC RETREAT-3.pdf | 24 Nov 2022 |
| Bescom NOC and SanctionFile: BESCOM NOC RETREAT-3.pdf | 24 Nov 2022 |
| Proforma Allotment LetterFile: PROFORMA ALLOTMENT LETTER Retreat-3.pdf | 24 Nov 2022 |
| Proforma Sale AgreementFile: Proforma Sale Agreement JR Garden Retreat-III.pdf | 24 Nov 2022 |
| JDA dated 24-12-2021File: JDA Sy No 62-6 Complete.pdf | 24 Nov 2022 |
| No litigation affidavitFile: Affidavit JR Garden Retreat-III.pdf | 24 Nov 2022 |
| Profit and Loss Statement 2021-22File: P AND L 2021-22 JRH.pdf | 24 Nov 2022 |
| Auditor's Report 2021-22File: Auditors Report 21-22.pdf | 24 Nov 2022 |
| Cash flow statement 2021-22File: Cash Flow Statement 21-22.pdf | 24 Nov 2022 |
| Balance Sheet 2021-22File: Balance Sheet 2021-22.pdf | 24 Nov 2022 |
| RERA Bank Statement - NIL TRANSACTIONSFile: Bank ac Statement Retreat-3.jpg | 24 Nov 2022 |
| Quarterly update clarificationFile: QuarterlyClarification.jpg | 6 Nov 2022 |
| CA Details (Updated available details)File: CARegistrationCertificate.jpg | 6 Nov 2022 |
| Balance Sheet 2020-21File: Balance Sheet F-Y 2020-21.pdf | 6 Nov 2022 |
| Auditors Report 2020-21File: Audritors Report F-Y 2020-21.pdf | 6 Nov 2022 |
| Profit and Loss 2020-21File: Profit and Loss F-Y 2020-21.pdf | 6 Nov 2022 |
| Cash flow 2020-21File: Cash Flow Statement F-Y 2020-21.pdf | 6 Nov 2022 |
| ITR 2020-21File: IT Acknowledgement F-Y 2020-21.pdf | 6 Nov 2022 |
| Bank Passbook Not availableFile: passbook_bank.jpg | 6 Nov 2022 |
| JDA 24-12-2021File: JDA 62-6.pdf | 6 Nov 2022 |
| JDA JR URBAN INFRACONFile: JDA JR Urban Infracon Pvt Ltd.pdf | 6 Nov 2022 |
| Title JDA Owner - InheritanceFile: MR-RTC-EC.pdf | 6 Nov 2022 |
| FORM B NotarizedFile: JR Garden Retreat Phase-III Form -B.pdf | 6 Nov 2022 |
| Notarized Affidavit Signed by Land Owners and DeveloperFile: JR Garden Retreat Phase-III Affidavit Cum Declaration.pdf | 6 Nov 2022 |
| Engineer certificateFile: Estimation Cost (1).pdf | 6 Nov 2022 |
| SURVEY SKETCH-PHODIFile: ADLR-SKETCH-RETREAT3.pdf | 6 Nov 2022 |
| Village MapFile: Village-Map-Iggalur.jpg | 6 Nov 2022 |
| STP CLARIFICATIONFile: STP-Clarification-Retreat3.jpg | 6 Nov 2022 |
| Site Dimensions ClarificationFile: Site-Dimensions-Clarification.jpg | 6 Nov 2022 |
| Project Cost ClarificationFile: project-cost-clarification.jpg | 6 Nov 2022 |
| Bank Passbook ClarificationFile: passbook_bank.jpg | 6 Nov 2022 |
| Advocate Search ReportFile: Advocate Search Report Clarification.jpg | 6 Nov 2022 |
| Village map extract with Site area IndicatedFile: Village-Map-Iggalur.jpg | 6 Nov 2022 |
| Agreement Allotment ClarificationFile: Agreement-Allotment-Clarification.jpg | 6 Nov 2022 |
| Water Supply NOC ClarificationFile: Watersupply-NOC-Clarification.jpg | 6 Nov 2022 |
| Relinquishment Deed ClarificationFile: RelinuishmentDeedClarification.jpg | 6 Nov 2022 |
| Guidance Value ClarificationFile: GuidanceValue-Clarification.jpg | 6 Nov 2022 |
| RTC, survey 62/6 | - |
| Mutation, survey 62/6 | - |
| Encumbrance Certificate, survey 62/6 | - |
| Conversion/Alienation Order, survey 62/6 | - |
| JDA, survey 62/6 | - |
| Khatha, survey 62/6 | - |
| RTC, survey 62/7 | - |
| Mutation, survey 62/7 | - |
| Encumbrance Certificate, survey 62/7 | - |
| Conversion/Alienation Order, survey 62/7 | - |
| JDA, survey 62/7 | - |
| Khatha, survey 62/7 | - |
| Registration CertificateFile: Registration.jpg | - |
| Organization StructureFile: ORG_STRUCTURE.jpg | - |
| Certificate issued by CA Form 1File: JR Housing RERA Certificate (2).pdf | - |
| Certificate issued by Engineer Form 3File: Estimation Cost.pdf | - |
| Project Chartered Accountant | - |
| Project Engineer | - |
| AffidavitFile: JR Garden Retreat Phase-III Affidavit.pdf | - |
| Certificate from Chartered AccountFile: JR Housing RERA Certificate (2).pdf | - |
| Certificate issued by ArchitectFile: Document (6).pdf | - |
| Balance Sheet 2021 - 2022File: Balance Sheet F-Y 2020-21.pdf | - |
| Balance Sheet 2020 - 2021File: BalanceSheet-201920.jpg | - |
| Balance Sheet 2019 - 2020File: BalanceSheet-201819.jpg | - |
| Audited Profit and Loss Statement 2021 - 2022File: Profit & Loss Statement F-Y 2020-21.pdf | - |
| Audited Profit and Loss Statement 2020 - 2021File: PandL201920.jpg | - |
| Audited Profit and Loss Statement 2019 - 2020File: PandL2018-19.jpg | - |
| Director's Report 2021 - 2022File: Audritors Report F-Y 2020-21.pdf | - |
| Director's Report 2020 - 2021File: TOBEUPLOADED.jpg | - |
| Director's Report 2019 - 2020File: TOBEUPLOADED.jpg | - |
| Cash Flow Statement 2021 - 2022File: Cash Flow Statement F-Y 2020-21.pdf | - |
| Cash Flow Statement 2020 - 2021File: TOBEUPLOADED.jpg | - |
| Auditor's Report 2021 - 2022File: Audritors Report F-Y 2020-21.pdf | - |
| Auditor's Report 2020 - 2021File: TOBEUPLOADED.jpg | - |
| Auditor's Report 2019 - 2020File: TOBEUPLOADED.jpg | - |
| Income Tax Return Acknowledgement 2021 - 2022File: IT Acknowledgement F-Y 2020-21.pdf | - |
| Income Tax Return Acknowledgement 2020 - 2021File: ITR-201920.jpg | - |
| Income Tax Return Acknowledgement 2019 - 2020File: ITR-201819.jpg | - |
| Retreat3Approval | - |
| NA_DOC | - |
| NA_DOC | - |
| Retreat3Layout | - |
| Retreat3Layout | - |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Status | Promised | Delivered |
|---|---|---|---|---|
| JR GREENWICH PHASE 4 | Sy No.79/1A1, Kodathi Village, Varthur Hobli, Bangalore East | Ongoing | Nov 2024 | Not delivered |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Bengaluru Urban
Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.
Keep JR GARDEN RETREAT PHASE 3 on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Bengaluru Urban4,100+ in Bengaluru Urban
Filed coordinates, straight-line distance. 20 registered projects within 2 km.
Cielo at Brigade Valencia
Brigade Enterprises Ltd
SIGNATURE REGAL
SIGNATURE DWELLINGS PRIVATE LIMITED
SOWPARNIKA OLIVIA NEST
SOWPARNIKA INFRACON PRIVATE LIMITED
RRL NATURE WOODS
RRL BUILDERS AND DEVELOPERS PRIVATE LIMITE
SPARKLE ATMOS
BARMECHA PROPERTIES
SIGNATURE CNR MARVEL
SIGNATURE DWELLINGS PRIVATE LIMITED
See every Bengaluru Urban project, with the district possession charts
Builder: JR Housing Developers Pvt Ltd
JR Housing Developers Pvt Ltd has 14 registrations on RERA Karnataka, including JR STRR ENCLAVE and JR ONE EAST. Its filings declare 5 earlier projects, 3 of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.
Frequently asked questions
What are my rights if JR GARDEN RETREAT PHASE 3 is delayed beyond 2 Sep 2024?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of JR GARDEN RETREAT PHASE 3?
The registered promoter entity is JR Housing Developers Pvt Ltd, a company as per the filing. Its CIN U07010KA2004PTC035108 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in JR GARDEN RETREAT PHASE 3?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at JR GARDEN RETREAT PHASE 3?
The professionals named in the filing: Engineer: Arunachalam; Chartered Accountant: Jogi and Co. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in JR GARDEN RETREAT PHASE 3?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.