Home / Browse projects / Bengaluru Urban, Karnataka / Cielo at Brigade Valencia
Cielo at Brigade Valencia
RG-KA-84008 · RERA PRM/KA/RERA/1251/308/PR/120123/005613 · Last updated on RERA Karnataka portal: 15 Oct 2026
Source: official RERA Karnataka filing
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
Saved.
Cielo at Brigade Valencia is a Residential/Group Housing project by Brigade Enterprises Ltd in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/308/PR/120123/005613 on 12 Jan 2023. Possession is promised by 31 Dec 2027. 661 of the 662 units on this registration are recorded sold or booked, and 6 of 18 construction stages are filed complete.
At a glance
Project
- NameCielo at Brigade Valencia
- TypeResidential/Group Housing
- Location
- Anekal
- Bengaluru Urban
- 562106
- Pincode562106
- MapView location on Google Maps (as filed on RERA)
- RERA no.PRM/KA/RERA/1251/308/PR/120123/005613
- ReraGenie IDRG-KA-84008
Builder
- NameBrigade Enterprises Ltd
- Entity typeCompany
- CINL85110KA1995PLC019126
- GSTIN29AAACB7459F1ZI
- Authorized SignatoryMr. Viswa Prathap Desu
- Managing DirectorMs. Pavitra Shankar
- DirectorsMr. M. R. Jaishankar, Mr. Bijou Kurien, Mr. Aroon Raman, Ms. Lakshmi Venkatachalam, Mr. Pradeep Kumar Panja, Dr. Venkatesh Panchapagesan, Mr. Amar Mysore, Ms. Pavitra Shankar, Ms. Nirupa Shankar, Mr. Roshin Mathew, Mr. Velloor Venkatakrishnan Ranganathan
- Project HeadNataraj M
- Other registrations45 more →
- No longer live1 withdrawn or revoked
- Declared earlier projects67 →
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on12 Jan 2023
- Promised completion31 Dec 2027
- Revised completionNone
- Buildings1 building record
- Documents filed181 files
Current status
Figures as on 15 Oct 2026, this project's latest RERA Karnataka filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Cielo at Brigade Valencia | - | - | - | 662 | 0 | 662 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
As on 15 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
6 of 18 construction stages are filed complete. The stage furthest along is Sub-structure flooring (Parking Floor, at 98%.
Building: 95% average across the applicable activities
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | 100% |
| Foundation footing work | 100% |
| Upto Plinth Level | 100% |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | 98% |
| Retaining wall (All types) | 100% |
| RCC or MS Framed structure | 100% |
| Masonry Construction | 100% |
| Plastering inside , outside & Ceiling | 85% |
| Joinery: Doors, Windows, Ventilators etc | 98% |
| Basic work of Water supply, Sanitary and Electrification | 90% |
| Dadoing, Skirting, Flooring, Tiles work (All types) | 98% |
| Railing and Grill fixing | 98% |
| Electrification, Water supply and Sanitary Finishing | 85% |
| Painting | 90% |
| Fire prevention and fire fighting fitting and fixture with network | 98% |
| Weather Proof work(tile,concrete) | 98% |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | Not applicable |
| Elevation work | 90% |
| Internal and External work including landscapes as per sanctioned drawings | 85% |
Progress on shared amenities40
As on 15 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | 85% |
| Sewage and Drainage System | Yes | 85% |
| Water conservation/rain water harvesting/recharge of ground water | Yes | 85% |
| Energy management | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 95% |
| Solid waste management and disposal | Yes | 65% |
| Emergency Evacuation services | Yes | 0% |
| Internal Roads & Footpaths | No | Not applicable |
| Electricity supply transformer and substation | Yes | 75% |
| Storm water drains | Yes | 95% |
| Use of renewable energy | Yes | 0% |
| Sewage Treatment Plant (STP) | Yes | 0% |
| Parks & Tree planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Electricity | Yes | 70% |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | No | Not applicable |
| Club House | Yes | 75% |
| Community Hall | No | Not applicable |
| Outdoor Sports facility | No | Not applicable |
| Indoor Sports facility | No | Not applicable |
| Swimming Pool | Yes | 65% |
| Gym | No | Not applicable |
| Parks | Yes | 50% |
| Power Backup | No | Not applicable |
| Piped Gas | No | Not applicable |
| Water and Sanitation | No | Not applicable |
| Air Conditioning | No | Not applicable |
| Staircases | Yes | 85% |
| Lifts | Yes | 90% |
| Corridor/Lobbies | Yes | 90% |
| Fire escapes | Yes | 90% |
| Common entrance and exit for the building/common portico/foyer/verandah | Yes | 85% |
| Basement | Yes | 85% |
| Terrace | Yes | 90% |
| Outer Wall | No | Not applicable |
| Open parking areas | Yes | 65% |
| Provision for lodging of management staff and security staff | No | Not applicable |
| Water conservation and renewable energy | No | Not applicable |
| Common storage spaces | No | Not applicable |
Land and ownership9
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| M/s. Anish Maple Reality and M/s. Veerabhadra Associates (Goa) | - | - |
| M/s. Anish Maple Reality and M/s. Veerabhadra Associates (Goa) | - | - |
| M/s. Anish Maple Reality and M/s. Veerabhadra Associates (Goa) | - | - |
| M/s. Anish Maple Reality and M/s. Veerabhadra Associates (Goa) | - | - |
| M/s. Anish Maple Reality and M/s. Veerabhadra Associates (Goa) | - | - |
| M/s. Anish Maple Reality and M/s. Veerabhadra Associates (Goa) | - | - |
| M/s. Anish Maple Reality and M/s. Veerabhadra Associates (Goa) | - | - |
| M/s. Anish Maple Reality and M/s. Veerabhadra Associates (Goa) | - | - |
| M/s. Anish Maple Reality and M/s. Veerabhadra Associates (Goa) | - | - |
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Cost line | Estimated | Incurred |
|---|---|---|
| Estimated Cost of Construction as certified by Engineer | Rs 209.94 cr | Rs 2.62 cr |
| Payment of taxes | Rs 37.96 cr | Rs 28.46 lakh |
| Principal sum and interest payable to financial institutions-Scheduled Banks | Rs 12.02 cr | Rs 5.43 cr |
| On-site expenditure-Site Overhead | Rs 11.73 cr | Rs 24.55 cr |
| On-site expenditure-Salaries of workers | Rs 50.80 lakh | Rs 1.06 cr |
| On-site expenditure-Consultants Fees | Rs 20.37 lakh | Rs 42.63 lakh |
| Payment of Premiums | Rs 88,214 | Rs 1.85 lakh |
| Payment of cess | Rs 77,729 | Rs 1.63 lakh |
Certifying professionals and partners3
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Paul Manoharan Moses |
| Engineer | RENUKA PRASAD H N [PROPRIETOR OF PRASAD CONSULTANTS] |
| Chartered Accountant | R. Srinivasan |
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed181
As listed on the registration, under the names the promoter filed them with; the newest 80 of 181 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/308/PR/120123/005613 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Cielo at Brigade Valencia - Form 4 - Q2.pdf | 15 Oct 2026 |
| Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Cielo at Brigade Valencia - Form 5 - Q2.pdf | 15 Oct 2026 |
| Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Cileo - Form 6 - Q2.pdf | 15 Oct 2026 |
| Q2 2026-27 Water supply and sewage board | 15 Oct 2026 |
| Q2 2026-27 KSPCB- PCB (10 Acres to 125 Acres) | 15 Oct 2026 |
| Q2 2026-27 KSPCB- MOEF (Above 50 Acres) | 15 Oct 2026 |
| Q2 2026-27 KPTCL- BESCOM | 15 Oct 2026 |
| Q2 2026-27 Fire and Safety | 15 Oct 2026 |
| Q2 2026-27 Airport Authority of India | 15 Oct 2026 |
| Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Cielo at Brigade Valencia - Form 4 - Q1.pdf | 15 Jul 2026 |
| Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Ceilo at Brigade Valencia - Form 5 - Q1.pdf | 15 Jul 2026 |
| Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Cielo - Form 6 - Q1.pdf | 15 Jul 2026 |
| Q1 2026-27 Water supply and sewage board | 15 Jul 2026 |
| Q1 2026-27 KSPCB- PCB (10 Acres to 125 Acres) | 15 Jul 2026 |
| Q1 2026-27 KSPCB- MOEF (Above 50 Acres) | 15 Jul 2026 |
| Q1 2026-27 KPTCL- BESCOM | 15 Jul 2026 |
| Q1 2026-27 Fire and Safety | 15 Jul 2026 |
| Q1 2026-27 Airport Authority of India | 15 Jul 2026 |
| Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Cielo At Brigade Valencia - Form 4 - Q4.pdf | 15 Apr 2026 |
| Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Ceilo - Form 5 - Q4.pdf | 15 Apr 2026 |
| Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Cileo - Form 6 - Q4.pdf | 15 Apr 2026 |
| Q4 2025-26 Water supply and sewage board | 15 Apr 2026 |
| Q4 2025-26 KSPCB- PCB (10 Acres to 125 Acres) | 15 Apr 2026 |
| Q4 2025-26 KSPCB- MOEF (Above 50 Acres) | 15 Apr 2026 |
| Q4 2025-26 KPTCL- BESCOM | 15 Apr 2026 |
| Q4 2025-26 Fire and Safety | 15 Apr 2026 |
| Q4 2025-26 Airport Authority of India | 15 Apr 2026 |
| Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Ceilo - Form 4 - Q3.pdf | 14 Jan 2026 |
| Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Cielo - Form 5 - Q3.pdf | 14 Jan 2026 |
| Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Cielo - Form 6 - Q3.pdf | 14 Jan 2026 |
| Q3 2025-26 Water supply and sewage board | 14 Jan 2026 |
| Q3 2025-26 KSPCB- PCB (10 Acres to 125 Acres) | 14 Jan 2026 |
| Q3 2025-26 KSPCB- MOEF (Above 50 Acres) | 14 Jan 2026 |
| Q3 2025-26 KPTCL- BESCOM | 14 Jan 2026 |
| Q3 2025-26 Fire and Safety | 14 Jan 2026 |
| Q3 2025-26 Airport Authority of India | 14 Jan 2026 |
| Title Deeds for all survey numbersFile: Cielo at Brigade Valencai - Title Documents.pdf | 6 Jan 2023 |
| Khata for Full ExtentFile: Khata - Acknowledgment.pdf | 6 Jan 2023 |
| MR for Sy No. 85/1File: MR No 1 -Sy No 85-1.pdf | 6 Jan 2023 |
| Conversion Order for Sy No. 54/2File: Conversion Order Sy No 54-2.pdf | 6 Jan 2023 |
| ZR showing Nala and HT line BufferFile: Anekal Planning Authority - Zonal Regulations.pdf | 6 Jan 2023 |
| Development Plan OrderFile: Brigade Valencia - Development Plan Order.pdf | 6 Jan 2023 |
| Carpet Area CalculationFile: Cielo at Brigade Valencia - Carpet details.pdf | 6 Jan 2023 |
| CDP MapFile: Cielo at Brigade Valencia - CDP Plan.pdf | 6 Jan 2023 |
| Village MapFile: Cielo at Brigade Valencia - Village Map.pdf | 6 Jan 2023 |
| Demarcation PlanFile: Ceilo at Brigade Valencia - RERA Demaraction Plan for Cluster C & D with Area.pdf | 6 Jan 2023 |
| Brief Estimated Cost of ConstructionFile: Ceilo - Brief Estimated Cost of Construction.pdf | 6 Jan 2023 |
| Structural Safety CertificateFile: Strl Stability Certificate.pdf | 6 Jan 2023 |
| Project SpecificationsFile: Cielo at Brigade Valencia - Specifications.pdf | 6 Jan 2023 |
| Proforma Agreement for SaleFile: Cielo at Brigade Valencia - Agreement to Sell.pdf | 6 Jan 2023 |
| Allotment LetterFile: Ceilo at Brigade Valencia - Proforma Allotment Letter.pdf | 6 Jan 2023 |
| Water NOCFile: Brigade Valencia - Water NOC.pdf | 6 Jan 2023 |
| BESCOM NOC Fee Paid ReceiptFile: BESCOM - Receipt.pdf | 6 Jan 2023 |
| Reply to the QueriesFile: Cielo at Brigade Valencia - List of Queries raised by RERA and BEL.pdf | 6 Jan 2023 |
| RTC, survey 54-1A | - |
| Mutation, survey 54-1A | - |
| Encumbrance Certificate, survey 54-1A | - |
| Conversion/Alienation Order, survey 54-1A | - |
| Sale/Title/Gift Deed, survey 54-1A | - |
| JDA, survey 54-1A | - |
| Khatha, survey 54-1A | - |
| RTC, survey 52 | - |
| Mutation, survey 52 | - |
| Encumbrance Certificate, survey 52 | - |
| Conversion/Alienation Order, survey 52 | - |
| Sale/Title/Gift Deed, survey 52 | - |
| JDA, survey 52 | - |
| Khatha, survey 52 | - |
| RTC, survey 54-2 | - |
| Mutation, survey 54-2 | - |
| Encumbrance Certificate, survey 54-2 | - |
| Conversion/Alienation Order, survey 54-2 | - |
| Sale/Title/Gift Deed, survey 54-2 | - |
| JDA, survey 54-2 | - |
| Khatha, survey 54-2 | - |
| RTC, survey 53 | - |
| Mutation, survey 53 | - |
| Encumbrance Certificate, survey 53 | - |
| Conversion/Alienation Order, survey 53 | - |
| Sale/Title/Gift Deed, survey 53 | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Bengaluru Urban
Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.
Keep Cielo at Brigade Valencia on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Bengaluru Urban4,100+ in Bengaluru Urban
Filed coordinates, straight-line distance. 11 registered projects within 2 km.
SIGNATURE REGAL
SIGNATURE DWELLINGS PRIVATE LIMITED
SOWPARNIKA OLIVIA NEST
SOWPARNIKA INFRACON PRIVATE LIMITED
RRL NATURE WOODS
RRL BUILDERS AND DEVELOPERS PRIVATE LIMITE
SPARKLE ATMOS
BARMECHA PROPERTIES
SIGNATURE CNR MARVEL
SIGNATURE DWELLINGS PRIVATE LIMITED
ABHEE PRIDE
ABHEE VENTURES PRIVATE LIMITED
See every Bengaluru Urban project, with the district possession charts
Builder: Brigade Enterprises Ltd
Brigade Enterprises Ltd has 46 registrations on RERA Karnataka, including Brigade Oasis - Phase 1 and Brigade Atmosphere- Phase 1. Its filings declare 67 earlier projects, 41 of them declared completed. Litigation is declared on 10 of its registrations. Read the full track record. See more projects on the Bengaluru Urban district page.
Frequently asked questions
What are my rights if Cielo at Brigade Valencia is delayed beyond 31 Dec 2027?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of Cielo at Brigade Valencia?
The registered promoter entity is Brigade Enterprises Ltd, a company as per the filing. Its CIN L85110KA1995PLC019126 and GSTIN 29AAACB7459F1ZI can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in Cielo at Brigade Valencia?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at Cielo at Brigade Valencia?
The professionals named in the filing: Architect: Paul Manoharan Moses; Engineer: RENUKA PRASAD H N [PROPRIETOR OF PRASAD CONSULTANTS]; Chartered Accountant: R. Srinivasan. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Cielo at Brigade Valencia?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.
Report an error Share feedback