Home / Browse projects / Mumbai Suburban, Maharashtra / JMS BUSINESS CENTRE

Registration lapsed No litigation declared Commercial project

JMS BUSINESS CENTRE

By JMS REALTY

RG-MH-25981 · RERA P51800009537 · Last updated on MahaRERA portal: 14 Apr 2023

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 34 months past the filed date
  • 1 complaint at MahaRERA
  • Completion date moved by 24 months
  • 2 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Dec 2023Possession promised34 months past this date
11 of 11Construction stages doneevery applicable stage filed complete
1Complaints at MahaRERAon this registration
Jump to the 29 documents Report an error

JMS BUSINESS CENTRE is a Commercial project by JMS REALTY in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800009537 on 22 Aug 2017. Possession was promised by 31 Dec 2023 and is now 34 months past that date. The completion date has moved by 24 months from the original filing. 1 complaint is on record with the regulator.

At a glance

Project

  • NameJMS BUSINESS CENTRE
  • TypeCommercial
  • Location
    • Andheri
    • Mumbai Suburban
    • 400102
  • Pincode400102
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800009537
  • ReraGenie IDRG-MH-25981

Builder

  • NameJMS REALTY
  • Entity typePartnership
  • PartnersMOHIDDIN A K CHERUVATTAM, MAQSOOD A JETHWA

Key dates

34 months past promisethis monthRegisteredAug 2017First promiseDec 2021Revised toDec 2023

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on22 Aug 2017
  • Promised completion31 Dec 2023
  • Revised completionRevised to 31 Dec 2023 (originally 30 Dec 2021)
  • Buildings1 building record
  • Documents filed29 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
JMS BUSINESS CENTRENA190000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 14 Apr 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

11 of 11 construction stages are filed complete.

JMS BUSINESS CENTRE: 100% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 14 Apr 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingNoNot applicable
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed1

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots1
Closed/Covered1

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,405 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI2809.71
Proposed, not sanctioned2,810 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchOSHIWARA BRANCH, MUMBAI-400102

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectDUBERIA & ASSOCIATES
EngineerFRAMES
PartnerRole in project
JMS REALTY-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800011981Dec 2021 → Dec 2022

Reason as filed by the promoterDear Sir, This is to bring into your kind information that the completion date of the Project ‘JMS Business Centre’ situated at JOGESHWARI WEST has been mentioned as 31/12/2021 during registration of the said Project at the RERA Site. There is some delay in completion of our project due to harsh impact of Covid 19 on real estate sector. Second wave has caused a lot of stress and trouble as our labour left for their hometown. Now things have regain momentum and we will ensure that we will be able to complete project with in the timeline. It is kindly requested to accord an extension till 31/12/

EXT51800014033Dec 2021 → Dec 2023

Reason as filed by the promoterDear RERA Authority, TWe are on the verge of completing this project. Even most of the units are even delivered and possession has been given to the respective buyer. There was a small delay in the project due to COVID-19 due to which there was a shortage of labor and manpower and which resulted in a slight delay in the project.

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC006000000171547Zafar A. MunshiSirajuddin A. Shaikh & 2 others16/11/2019

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 29 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 29 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 29 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 29 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed29

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Declaration about Commencement CertificateFile: Declaration about commencement Certificate (1).pdf14 Apr 2023
Declaration in FORM BFile: AFFIDAVIT (3).pdf14 Apr 2023
Certificates of CA (Form 5)File: CA Certificate 17-18 (1).pdf14 Apr 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: CA Certificate 18-19.pdf14 Apr 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: CA Certificate 19-20 (1).pdf14 Apr 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: CA Certificate_compressed.pdf25 Nov 2022
Disclosure of sold/ booked inventoryFile: Disclosure Of Sold b0oked_compressed.pdf25 Nov 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: CA Certificate_compressed.pdf25 Nov 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: CA Certificate_compressed.pdf25 Nov 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: CA Certificate_compressed.pdf25 Nov 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: CA Certificate_compressed.pdf25 Nov 2022
Certificates of CA (Form 5)File: Form 5 _ JMS.pdf19 Apr 2019
Layout approvalFile: LAYOUT.pdf29 Jul 2017
Building plan approvalFile: IOD.pdf29 Jul 2017
Building plan approvalFile: BUILDING LAYOUT.pdf29 Jul 2017
PAN CardFile: JMS PAN.pdf29 Jul 2017
Copy of the legal title reportFile: TITLE CERTIFICATE.pdf29 Jul 2017
Details of encumbrancesFile: NON ENCUMBRANCE.pdf29 Jul 2017
Copy of Layout Approval (in case of layout)File: LAYOUT.pdf29 Jul 2017
Building Plan Approval (IOD)File: IOD.pdf29 Jul 2017
Building Plan Approval (IOD)File: BUILDING LAYOUT.pdf29 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: CC COPY.pdf29 Jul 2017
Declaration in FORM BFile: FORM-B.pdf29 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: compressed_ARCHITECT CERTIFICATE JMS (1).pdf29 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER CERTIFICATE.pdf29 Jul 2017
Certificates of CA (Form 3)File: CA CERTIFICATE.pdf29 Jul 2017
Proforma of Allotment letterFile: ALLOTMENT LETTER.pdf29 Jul 2017
Proforma of Allotment letterFile: AGRREMENT TO SALE-1.pdf29 Jul 2017
Proforma of Allotment letterFile: AGRREMENT TO SALE-2.pdf29 Jul 2017

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one moved by 24 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is among them

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep JMS BUSINESS CENTRE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Andheri6,700+ in Mumbai Suburban

2 kmJMS BUSINESS CENTRECompleted 105Lapsed / revoked 59Abeyance 1Other 127Dot size: filed unitsN

Filed coordinates, straight-line distance. 292 registered projects within 2 km.

Builder: JMS REALTY

JMS REALTY has 1 registration on MahaRERA, including JMS BUSINESS CENTRE. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What does it mean that JMS BUSINESS CENTRE shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if JMS BUSINESS CENTRE is delayed beyond 31 Dec 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of JMS BUSINESS CENTRE?

The registered promoter entity is JMS REALTY, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in JMS BUSINESS CENTRE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against JMS BUSINESS CENTRE?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for JMS BUSINESS CENTRE?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at JMS BUSINESS CENTRE?

The professionals named in the filing: Architect: DUBERIA & ASSOCIATES; Engineer: FRAMES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in JMS BUSINESS CENTRE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About JMS BUSINESS CENTRE. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save JMS BUSINESS CENTRE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.