Home / Browse projects / Thane, Maharashtra / Jijai Apartment

Registration lapsed No litigation declared Residential / Group Housing project

Jijai Apartment

By Shree Balaji Developers

RG-MH-46864 · RERA P51700032174 · Last updated on MahaRERA portal: 23 May 2026

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 13 months past the filed date
  • Completion date moved by 15 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Sep 2025Possession promised13 months past this date
6 of 22Construction stages doneacross 2 buildings; furthest along: Slabs of Super Structure, 85%
0Complaints at MahaRERAon this registration
Jump to the 130 documents Report an error

Jijai Apartment is a Residential / Group Housing project by Shree Balaji Developers in Thane, Maharashtra, registered with MahaRERA as P51700032174 on 14 Dec 2021. Possession was promised by 30 Sep 2025 and is now 13 months past that date. The completion date has moved by 15 months from the original filing.

At a glance

Project

  • NameJijai Apartment
  • TypeResidential / Group Housing
  • Location
    • Sector-9
    • Dive Gaon Airoli
    • Navi Mumbai (M Corp.)
    • Thane
    • 400708
  • Pincode400708
  • RERA no.P51700032174
  • ReraGenie IDRG-MH-46864

Builder

  • NameShree Balaji Developers
  • Entity typePartnership
  • PartnersSantosh Vasant Keni, Pushpendra Babulalji Jain
  • Other registrations21 more →
  • Completed6 of 22
  • No longer live12 lapsed, de-registered or revoked
  • Past their filed date1
  • Declared earlier projects4 →

Key dates

13 months past promisethis monthRegisteredDec 2021First promiseJun 2024Revised toSep 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on14 Dec 2021
  • Promised completion30 Sep 2025
  • Revised completionRevised to 30 Sep 2025 (originally 30 Jun 2024)
  • Buildings2 building records
  • Documents filed130 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Wing ANA70000
Wing BNA70000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 23 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

6 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Slabs of Super Structure, at 85%.

Wing A41%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure85%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises65%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Wing B41%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure85%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises65%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 23 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed6

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots6
Closed/Covered6
BuildingClosed/CoveredTotal
Wing A33
Wing B33

Land and ownership7

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area797 sq m
Land owned byThe promoter, with other names on the file
Named landowners7
LandownerVillageDistrict
Smt.Girijabai Kisan MadhaviNavi Mumbai (M Corp.)Thane
Shri.Pandurang Kisan MadhaviNavi Mumbai (M Corp.)Thane
Shri.Rajaram Kisan MadhaviNavi Mumbai (M Corp.)Thane
Shri.Sadanand Kisan MadhaviNavi Mumbai (M Corp.)Thane
Shri.Shyam Kisan MadhaviNavi Mumbai (M Corp.)Thane
Shri.Ravindra Kisan MadhaviNavi Mumbai (M Corp.)Thane
Mrs.Manorama Ramakant KoliNavi Mumbai (M Corp.)Thane

Approvals and building plan

Sanctioning authorityNAVI MUMBAI MUMNCIPAL CORPORATION
Permissible FSI1274.92
Proposed, not sanctioned1,275 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchShop No 1 to 6, Sanjeevani Vrundavan Plot No -38, Sector -19, Airoli Navi Mumbai -400708

Certifying professionals and partners1

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
Chartered AccountantSachin Chandrashekar Bhate
PartnerRole in project
Shree Balaji Developers-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51700025480Jun 2024 → Sep 2025

Reason as filed by the promoterThe project is carried on local residents' sanad property at Diva Gaon, Airoli, Navi Mumbai & the developer duly obtain the required permission for construction. As mentioned the land is situated in Diva Gaon & hence developer has to overcome many difficulties to do construction like nearby vicinity residential resident's objection for construction noise their safety provision etc, further lack of place for storing material at site, providing accommodation to the laborer etc. And also the developer got the permission for additional floor & hence construction work is increase. This fact may als

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 7 Dec 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 10 Dec 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 10 Dec 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 1 Dec 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed130

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 130 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 1File: 01-Architect-s Certificate-Oct to Dec 2021.pdf23 May 2026
Form 2File: 02-Engineer-s Certificate - Oct to Dec 2021.pdf23 May 2026
Form 3File: 03-CA Certificate - Oct to Dec 2021.pdf23 May 2026
Disclosure of Sold and Booked InventoryFile: 04-Inventory - 31-12-2021.pdf23 May 2026
Form 1File: 01-Architect-s Certificate - Jan to Mar 2022.pdf23 May 2026
Form 2File: 02-Engineer-s Certificate - Jan to Mar 2022.pdf23 May 2026
Form 3File: 03-CA Certificate - Jan to Mar 2022.pdf23 May 2026
Disclosure of Sold and Booked InventoryFile: 04-Inventory-31-12-22.pdf23 May 2026
Form 1File: 01-Architect-s Certificate - Apr to Jun 2022.pdf23 May 2026
Form 2File: 02-Engineer-s Certificate - Apr ot Jun 2022.pdf23 May 2026
Form 3File: 03-CA Certificate - Apr to Jun 2022.pdf23 May 2026
Disclosure of Sold and Booked InventoryFile: 04-Inventory-30-06-2022.pdf23 May 2026
Form 1File: 01-Architect-s Certificate - Jul to Sep 2022.pdf23 May 2026
Form 2File: 02-Engineer-s Certificate - Jul to Sep 2022.pdf23 May 2026
Form 3File: 03-CA Certificate - Jul to Sep 2022.pdf23 May 2026
Disclosure of Sold and Booked InventoryFile: 04-Inventory-30-09-2022.pdf23 May 2026
Form 1File: 01-Architect-s Certificate - Oct to Dec 2022.pdf23 May 2026
Form 2File: 02-Engineer-s Certificate - Oct to Dec 2022.pdf23 May 2026
Form 3File: 03-CA Certificate - Oct to Dec 2022.pdf23 May 2026
Disclosure of Sold and Booked InventoryFile: 04-Inventory - 31-12-2022.pdf23 May 2026
Form 1File: 01-Architect-s Certificate - Jan to Mar 2023_11zon.pdf23 May 2026
Form 2File: 02-Engineer-s Certificate - Jan to Mar 2023_11zon.pdf23 May 2026
Form 3File: 03-CA Certificate - Jan to Mar 2023_11zon.pdf23 May 2026
Disclosure of Sold and Booked InventoryFile: 04-Inventory-31-03-2023.pdf23 May 2026
Form 1File: 01-Architect-s Certificate - Apr to Jun 2023.pdf23 May 2026
Form 2File: 02-Engineer Certificate - Apr to Jun 2023.pdf23 May 2026
Form 3File: 03-CA Certificate - Apr to Jun 2023.pdf23 May 2026
Disclosure of Sold and Booked InventoryFile: 04-Inventory-30-06-2023.pdf23 May 2026
Form 1File: 01-Architect-s Certificate - Jul to Sep 2023.pdf23 May 2026
Form 2File: 02-Engineer-s Certificate - Jul to Sep 2023.pdf23 May 2026
Form 3File: 03-CA Certificate - Jul to Sep 2023.pdf23 May 2026
Disclosure of Sold and Booked InventoryFile: 04-Inventory-30-09-2023.pdf23 May 2026
Form 1File: 01-Architect certificate - Oct to Dec 2023.pdf23 May 2026
Form 2File: 02-Engineer-s Certificate - Oct to Dec 2023.pdf23 May 2026
Form 3File: 03-CA Certificate - Oct to Dec 2023.pdf23 May 2026
Disclosure of Sold and Booked InventoryFile: 04-Inventory-31-12-2023.pdf23 May 2026
Form 1File: 01-Architect-s Certificate - Jan to Mar 2024.pdf23 May 2026
Form 2File: 02-Engineer-s Certificate - Jan to Mar 2024.pdf23 May 2026
Form 3File: 03-CA Certificate - Jan to Mar 2024.pdf23 May 2026
Disclosure of Sold and Booked InventoryFile: 04-Inventory-31-03-2024.pdf23 May 2026
Form 1File: 01-Architect-s Certificate - Apr to Jun 2024.pdf23 May 2026
Form 2File: 02-Engineer-s Certificate - Apr to Jun 2024.pdf23 May 2026
Form 3File: 03-CA Certificate - Apr to Jun 2024.pdf23 May 2026
Disclosure of Sold and Booked InventoryFile: 04-Inventory-30-06-2024.pdf23 May 2026
Form 1File: 01-Architect-s Certificate - Jul to Sep 2024.pdf23 May 2026
Form 2File: 02-Engineer-s Certificate - Jul to Sep 2024.pdf23 May 2026
Form 3File: 03-CA Certificate - Jul to Sep 2024.pdf23 May 2026
Disclosure of Sold and Booked InventoryFile: 04-Inventory-30-09-2024.pdf23 May 2026
Form 1File: 01-Architect Certificate - Oct to Dec 2024.pdf23 May 2026
Form 2File: 02-Engineer-s Certificate - Oct to Dec 2024.pdf23 May 2026
Form 3File: 03-CA Certificate - Oct to Dec 2024.pdf23 May 2026
Disclosure of Sold and Booked InventoryFile: 04-Inventory-31-12-2024.pdf23 May 2026
Form 1File: 01-Architect Certificate - Jan to Mar 2025.pdf23 May 2026
Form 2File: 02-Engineers Certificate - Jan to Mar 2025.pdf23 May 2026
Form 3File: 03-CA Certificate - Jan to Mar 2025.pdf23 May 2026
Disclosure of Sold and Booked InventoryFile: 04-Inventory-31-03-2025.pdf23 May 2026
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 01-Architect'S Certificate - Jan to Mar 2025.pdf24 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 03-CA Certificate - Jan to Mar 2025.pdf24 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 01-Architect'S Certificate - Oct to Dec 2024.pdf22 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 03-CA Certificate - Oct to Dec 2024.pdf22 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 02-Engineer-s Certificate - Oct to Dec 2024.pdf22 Jan 2025
Disclosure of sold/ booked inventoryFile: Disclosure of Sold-Unsold Inventory.pdf9 Jan 2025
Declaration in FORM BFile: Form - B.pdf19 Dec 2024
Details of encumbrances concerned to FinanceFile: 01-Declaration of Encumbrances - Legal.pdf11 Dec 2024
Declaration about all RERA Designated Bank Accounts (Format A)File: Declaration about Separate Bank Account (2 files merged).pdf11 Dec 2024
Deviation Report with respect to Allotment letterFile: Declaration of Deviation Report for Allotment Letter.pdf11 Dec 2024
Details of encumbrances concerned to LegalFile: 01-Declaration of Encumbrances - Legal.pdf11 Dec 2024
Deviation Report with respect to model copy of AgreementFile: Declaration for Deviation Report to Model copy of Agreeemtn.pdf11 Dec 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Declaration of Interest of Other Real Estate Organization.pdf11 Dec 2024
Layout approvalFile: 6th Floor Plan - Jijai Apartment.pdf10 Dec 2024
Building plan approvalFile: 6th Floor Plan - Jijai Apartment.pdf10 Dec 2024
Copy of Layout Approval (in case of layout)File: 6th Floor Plan - Jijai Apartment.pdf10 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 01-Architect-s Certificate - Jul to Sep 2023.pdf10 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 01-Architect-s Certificate - Jul to Sep 2024.pdf10 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 01-Architect-s Certificate - Apr to Jun 2024.pdf10 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 01-Architect-s Certificate - Jan to Mar 2024.pdf10 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 01-Architect certificate - Oct to Dec 2023.pdf10 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 01-Architect-s Certificate - Apr to Jun 2023.pdf10 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 01-Architect-s Certificate.pdf10 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 01-Architect-s Certificate - Oct to Dec 2022.pdf10 Dec 2024

How this compares with Thane

24%of Thane projects moved their completion datethis one moved by 15 months
23%of Thane registrations have lapsed or been cancelledthis one is among them

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Jijai Apartment on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Dive Gaon Airoli7,600+ in Thane

Builder: Shree Balaji Developers

SHREE BALAJI DEVELOPERS has 22 registrations on MahaRERA, including SHREE RESIDENCY and PNT SQUARE. Its filings disclose 4 earlier MahaRERA projects: declares 3 of 3 past projects completed on time. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What does it mean that Jijai Apartment shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Jijai Apartment is delayed beyond 30 Sep 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Jijai Apartment?

The registered promoter entity is Shree Balaji Developers, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Jijai Apartment?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Jijai Apartment?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Jijai Apartment?

The professionals named in the filing: Chartered Accountant: Sachin Chandrashekar Bhate. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Jijai Apartment?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Jijai Apartment. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Jijai Apartment to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.