Home / Browse projects / Bengaluru Rural, Karnataka / Jasper and Iridium at Brigade El Dorado
Jasper and Iridium at Brigade El Dorado
By Brigade Tetrarch Private Limited
RG-KA-25880 · RERA PRM/KA/RERA/1250/303/PR/200618/003458 · Last updated on RERA Karnataka portal: 1 Jun 2020
Source: official RERA Karnataka filing
Red flags
- 1 complaint at RERA Karnataka
- Completion date moved by 9 months
- 1 extension taken
Clear
- Separate project account declared
Saved.
Jasper and Iridium at Brigade El Dorado is a Mixed Development project by Brigade Tetrarch Private Limited in Bengaluru Rural, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1250/303/PR/200618/003458 on 18 Jun 2020. Possession is promised by 30 Sep 2025. The completion date has moved by 9 months from the original filing. 1 complaint is on record with the regulator.
At a glance
Project
- NameJasper and Iridium at Brigade El Dorado
- TypeMixed Development
- Location
- Devanahalli
- Bengaluru Rural
- PincodeNot stated
- MapView location on Google Maps (as filed on RERA)
- RERA no.PRM/KA/RERA/1250/303/PR/200618/003458
- ReraGenie IDRG-KA-25880
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on18 Jun 2020
- Promised completion30 Sep 2025
- Revised completionRevised to 30 Sep 2025 (originally 31 Dec 2024)
- Buildings2 building records
- Documents filed131 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Jasper at Brigade El Dorado | - | - | - | 474 | 0 | 474 |
| Iridium at Brigade El Dorado | - | - | - | 556 | 0 | 556 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
As on 1 Jun 2020, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
Building:
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | - |
| Foundation footing work | - |
| Retaining wall (All types) | - |
| Plinth level Beam | Not applicable |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | - |
| RCC or MS Framed structure | - |
| Masonry construction: Bricks, Concrete blocks etc | Not applicable |
| Plastering inside , outside & Ceiling | Not applicable |
| Joinery: Doors, Windows, Ventilators etc | - |
| Basic work of Water supply, Sanitary and Electrification | - |
| Dadoing, Skirting, Flooring, Tiles work (All types) | - |
| Railing and Grill fixing | - |
| Electrification, Water supply and Sanitary Finishing | - |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | Not applicable |
| Fire prevention and fire fighting fitting and fixture with network | - |
| Weather Proof work(tile,concrete) | Not applicable |
| Painting | - |
| Elevation work | Not applicable |
| Internal and External work including landscapes as per santioned drawings | - |
Progress on shared amenities41
As on 1 Jun 2020, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | - |
| Internal Roads & Footpaths | Yes | - |
| Sewage and Drainage System | Yes | - |
| Parks & Tree planting | Yes | - |
| Street Lighting | Yes | - |
| Provision for community buildings and for treatment and disposal of sewage and sullage water | Yes | - |
| Solid waste management and disposal | Yes | - |
| Water conservation | No | Not applicable |
| Energy management | Yes | - |
| Fire protection and fire safety requirements | Yes | - |
| Education/Health/Other public amenities | Yes | - |
| Electricity supply transformer and substation | Yes | - |
| Emergency Evacuation services | No | Not applicable |
| Storm water drains | Yes | - |
| Use of renewable energy | No | Not applicable |
| Water conservation/rain water harvesting/recharge of ground water | Yes | - |
| Electricity | Yes | - |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | Yes | - |
| Club House | Yes | - |
| Community Hall | No | Not applicable |
| Outdoor Sports facility | Yes | - |
| Indoor Sports facility | Yes | - |
| Swimming Pool | Yes | - |
| Gym | Yes | - |
| Parks | Yes | - |
| Power Backup | Yes | - |
| Gas | Yes | - |
| Water and Sanitation | No | Not applicable |
| Air Conditioning And incerntion | Yes | - |
| Staircases | Yes | - |
| Lifts | Yes | - |
| Staircases and Lift lobbies, corridor,lobbies, corridor | Yes | - |
| Fire escapes | Yes | - |
| Common entrance and exit for the building / common portico/foyer/verandah | Yes | - |
| Basement | Yes | - |
| Terrace | Yes | - |
| Outer Wall | Yes | - |
| Open parking areas and common storage spaces | Yes | - |
| Provision for lodging of management staff and security staff | Yes | - |
| Water conservation and renewable energy | Yes | - |
Land and ownership
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners2
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Abhay Itty Zachariah |
| Engineer | N.N.Nagendra Kumar |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
No reason recorded in the filing
Complaints filed with RERA Karnataka1
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| 00178/2025 | - | Brigade Tetrarch Private Limited | 23/01/2025 |
Documents filed131
As listed on the registration, under the names the promoter filed them with; the newest 80 of 131 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1250/303/PR/200618/003458 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Cancelled Cheque for RERA Bank AccountFile: Cancelled Cheque.pdf | 1 Jun 2020 |
| Site Plan with Blown up - SignedFile: Site Plan & Blown Up - Signed.pdf | 1 Jun 2020 |
| Typical Floor Plans - J BlockFile: J Block - Typical Floors Plans.pdf | 1 Jun 2020 |
| Typical Floor Plans - I BlockFile: I Block - Typical Floors Plans.pdf | 1 Jun 2020 |
| Development Details signed by ArchitectFile: Development Details - Signed by Architect.pdf | 1 Jun 2020 |
| Project Head DetailsFile: Company member details - BTPL.xlsx | 1 Jun 2020 |
| SEIAA NOCFile: Brigade El Dorado - Revised Environmental Clearance.pdf | 1 Jun 2020 |
| Reply to RERA QueryFile: Reply to RERA query.pdf | 1 Jun 2020 |
| CertificateFile: Certificate of Incorporation BTPL.pdf | - |
| Already registered project ongoing detailsFile: List of Ongoing Registered Projects.xlsx | - |
| Modified plan details site plan, floor plans, Plan Licence LetterFile: Brigade El Dorado - Revision Certificate.pdf | - |
| Elevation, Sections, Specifications ( If changes are there )File: BUILDING 05 Tower I Section and Elevation.pdf | - |
| List Of AllotteesFile: List of Allottess - Jasper & Iridium.xlsx | - |
| Consent LetterFile: Iridium - Consent Letters - Part 1.pdf | - |
| Chartered Accountant CertificateFile: Jasper and lridium at Brigade EI Dorado - Form 4_compressed.pdf | - |
| Notarized AffidavitFile: Jasper & Iridium - Affidavit.pdf | - |
| Engineer CertificateFile: Jasper and lridium at Brigade EI Dorado - Form 6.pdf | - |
| Architect CertificateFile: Jasper and lridium at Brigade EI Dorado - Form 5 - Com.pdf | - |
| Structural Engineer Certificate for stability of structureFile: Jasper & Iridium - Stability Certificate.pdf | - |
| Modification of Plan DetailsFile: Site Plan.pdf | - |
| Modification of Plan DetailsFile: Brigade El Dorado -Revised Site Plan.pdf | - |
| Modification of Plan DetailsFile: Commencement Certificate - I, J & Community Bldg - 2 - Com.pdf | - |
| Modification of Plan DetailsFile: Commencement Certificate - I, J & Community Bldg - 2 - Com.pdf | - |
| Modification of Plan DetailsFile: Jasper and lridium at Brigade EI Dorado - Sold & Unsold Details - Reg Plan.pdf | - |
| Modification of Plan DetailsFile: Jasper and lridium at Brigade EI Dorado - Sold & Unsold Details_compressed.pdf | - |
| Modifiied Sanction LetterFile: Brigade El Dorado - Revision Certificate.pdf | - |
| Revised Site PlanFile: Brigade El Dorado -Revised Site Plan.pdf | - |
| Tower I 2nd to 19th Typical Floor PlanFile: Tower I 2nd to 19th Typical Floor Plan.pdf | - |
| Tower I 20th Floor Plan (Refuge area plan)File: Tower I 20th Floor Plan (Refuge area plan).pdf | - |
| Tower I Ground Floor PlanFile: Tower I Ground Floor Plan.pdf | - |
| Tower I Lower Basement Floor PlanFile: Tower I Lower Basement Floor Plan.pdf | - |
| Tower I Section and ElevationFile: Tower I Section and Elevation.pdf | - |
| Tower I Terrace Floor PlanFile: Tower I Terrace Floor Plan.pdf | - |
| Tower I Upper Basement Floor PlanFile: Tower I Upper Basement Floor Plan.pdf | - |
| Tower J 1st and 2nd Floor PlanFile: Tower J 1st and 2nd Floor Plan.pdf | - |
| Tower J 3rd to 19th Typical Floor PlanFile: Tower J 3rd to 19th Typical Floor Plan.pdf | - |
| Tower J 20th Floor Plan (Refuge area)File: Tower J 20th Floor Plan (Refuge area).pdf | - |
| Tower J ElevationFile: Tower J Elevation.pdf | - |
| Tower J Ground Floor PlanFile: Tower J Ground Floor Plan.pdf | - |
| Tower J Lower Basement Floor PlanFile: Tower J Lower Basement Floor Plan.pdf | - |
| Tower J SectionFile: Tower J Section.pdf | - |
| Tower J Terrace Floor PlanFile: Tower J Terrace Floor Plan.pdf | - |
| Tower J Upper Basement Floor PlanFile: Tower J Upper Basement Floor Plan.pdf | - |
| Community Building-02-First FloorFile: Community Building-02-First Floor.pdf | - |
| Community Building-02-Ground floorFile: Community Building-02-Ground floor.pdf | - |
| Community Building-02-Master planFile: Community Building-02-Master plan.pdf | - |
| Community Building-02-Second FloorFile: Community Building-02-Second Floor.pdf | - |
| Community Building-02-Section And ElevationFile: Community Building-02-Section And Elevation.pdf | - |
| Community Building-02-Site planFile: Community Building-02-Site plan.pdf | - |
| Community Building-02-Terrace FloorFile: Community Building-02-Terrace Floor.pdf | - |
| Area Statement 1File: Area Statement - 1.pdf | - |
| Area Statement 2File: Area Statement - 2.pdf | - |
| SpecificationsFile: Specifications.pdf | - |
| Iridium - Consent Letters - Part 1File: Iridium - Consent Letters - Part 1.pdf | - |
| Iridium - Consent Letters - Part 2File: Iridium - Consent Letters - Part 2.pdf | - |
| Iridium - Consent Letters - Part 3File: Iridium - Consent Letters - Part 3.pdf | - |
| Iridium - Consent Letters - Part 4File: Iridium - Consent Letters - Part 4.pdf | - |
| Iridium - Consent Letters - Part 5File: Iridium - Consent Letters - Part 5.pdf | - |
| Iridium - Consent Letters - Part 6File: Iridium - Consent Letters - Part 6.pdf | - |
| Iridium - Consent Letters - Part 7File: Iridium - Consent Letters - Part 7.pdf | - |
| Iridium - Consent Letters - Part 8File: Iridium - Consent Letters - Part 8.pdf | - |
| Iridium - Consent Letters - Part 9File: Iridium - Consent Letters - Part 9.pdf | - |
| Jasper - Consent Letters - Part 1File: Jasper - Consent Letters - Part 1.pdf | - |
| Jasper - Consent Letters - Part 2File: Jasper - Consent Letters - Part 2.pdf | - |
| Jasper - Consent Letters - Part 3File: Jasper - Consent Letters - Part 3.pdf | - |
| Jasper - Consent Letters - Part 4File: Jasper - Consent Letters - Part 4.pdf | - |
| Jasper - Consent Letters - Part 5File: Jasper - Consent Letters - Part 5.pdf | - |
| Jasper - Consent Letters - Part 6File: Jasper - Consent Letters - Part 6.pdf | - |
| Reason for ModificationsFile: Reason for Modifications.pdf | - |
| Letter for Change of Project TypeFile: Request to Change of Project Type.pdf | - |
| Plan Sanction Letter | - |
| Site Plan and Blown up Plan | - |
| Sale Deed- RERA | - |
| Proforma Agreement to Sell- J and I El Dorado | - |
| Sale Deed and RTC (Allotmnent Letters) | - |
| Section and Elevation - I and J Block | - |
| Site Plan | - |
| Allotment Letter - J and I at Brigade El Dorado | - |
| Jasper & Iridium At El-Dorado Rera Brochure | - |
| Specifications | - |
Promoter's earlier projects2
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Status | Promised | Delivered |
|---|---|---|---|---|
| Helio at Brigade El Dorado | - | Ongoing | Dec 2023 | Not delivered |
| Gallium at Brigade El Dorado | - | Ongoing | Dec 2023 | Not delivered |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Bengaluru Rural
Computed across the 650+ Bengaluru Rural projects on ReraGenie, from their own filings.
Keep Jasper and Iridium at Brigade El Dorado on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Bengaluru Rural650+ in Bengaluru Rural
BARCA AT GODREJ MSR CITY
M S RAMAIAH VENTURES LLP
Ozone Urbana
Ozone Urbana Infra Developers Pvt Ltd
Pashmina Brookwoods
Shashwati Realty Pvt Ltd
Godrej Royale Woods
Godrej Projects North Star LLP
Prestige Jindal City-Phase II
PRESTIGE SOUTHCITY HOLDINGS
Provident Botanico
Provident Housing Limited
See every Bengaluru Rural project, with the district possession charts
Builder: Brigade Tetrarch Private Limited
Brigade Tetrarch Private Limited has 10 registrations on RERA Karnataka, including Jasper and Iridium at Brigade El Dorado and Aurum at Brigade El Dorado. Its filings declare 4 earlier projects, none of them declared completed. Read the full track record. See more projects on the Bengaluru Rural district page.
Frequently asked questions
What are my rights if Jasper and Iridium at Brigade El Dorado is delayed beyond 30 Sep 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of Jasper and Iridium at Brigade El Dorado?
The registered promoter entity is Brigade Tetrarch Private Limited, a company as per the filing. Its CIN U70100KA1995PTC018247 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in Jasper and Iridium at Brigade El Dorado?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against Jasper and Iridium at Brigade El Dorado?
Each case number above is a complaint filed with RERA Karnataka. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
Who certifies construction progress at Jasper and Iridium at Brigade El Dorado?
The professionals named in the filing: Architect: Abhay Itty Zachariah; Engineer: N.N.Nagendra Kumar. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Jasper and Iridium at Brigade El Dorado?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.