JARE ROYAL HOME
RG-MH-97288 · RERA P52100048303 · Last updated on MahaRERA portal: 25 Apr 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 10 months past the filed date
- Completion date moved by 12 months
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
JARE ROYAL HOME is a Residential / Group Housing project by SACHIN VASANT JARE in Pune, Maharashtra, registered with MahaRERA as P52100048303 on 26 Dec 2022. Possession was promised by 30 Dec 2025 and is now 10 months past that date. The completion date has moved by 12 months from the original filing. 11 of the 14 units on this registration are recorded sold or booked, and 8 of 11 construction stages are filed complete.
At a glance
Project
- NameJARE ROYAL HOME
- TypeResidential / Group Housing
- Location
- MOSHI
- Haveli
- Pune
- 412105
- Pincode412105
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100048303
- ReraGenie IDRG-MH-97288
Builder
- NameSACHIN VASANT JARE
- Entity typeIndividual
- Other registrations3 more →
- Completed1 of 4
- No longer live2 lapsed, de-registered or revoked
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on26 Dec 2022
- Promised completion30 Dec 2025
- Revised completionRevised to 30 Dec 2025 (originally 31 Dec 2024)
- Buildings1 building record
- Documents filed64 files
Current status
Figures as on 25 Apr 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| JARE ROYAL HOME | NA | 8 | 7 | 14 | 0 | 14 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 25 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
8 of 11 construction stages are filed complete. The stage furthest along is Basement (if any), at 0%.
JARE ROYAL HOME: 73% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 25 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed28
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership5
MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
| Landowner | Village | District |
|---|---|---|
| Kishor Bandu Khuspe | Nidhal | Satara |
| Pravin Narayan Patil | Navi Mumbai (M Corp.) | Thane |
| Hemant Ganpat Shedge | Rajewadi | Satara |
| Suyog Baban Ghuge | Andur | Osmanabad |
| Anand Sukhdeo Bhagat | Bhamb | Yavatmal |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| JARE ROYAL HOME | NA | Rs 4.00 cr | Rs 3.35 cr |
| - | NA | Rs 70.00 lakh | Rs 39.41 lakh |
Certifying professionals and partners8
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Aadi Associates |
| Architect | Umesh Subrao Namde |
| Engineer | Suraj Namdev Adagale |
| Engineer | Santosh Mahalingappa Padsalge |
| Engineer | Shriram Ramesh Nagargoje |
| Chartered Accountant | VIVEK N LAHOTI |
| Chartered Accountant | NPSR & Associates |
| Chartered Accountant | PMRD & Associates LLP |
| Partner | Role in project |
|---|---|
| SACHIN VASANT JARE | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoter1. We mentioned date of completion of the project as 31.12.2024, we would like to correct it as 30.12.2025. Hence we are applying for making suitable changes to our project details. Hence I am applying for making suitable changes to my project details. Kindly grant permission to change any other typographical mistakes which may have happened also.
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 14 Dec 2022 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 2 Nov 2022 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 30 Dec 2025 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 1 Mar 2024Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed64
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Form 1 Jare Royal Home.pdf | 25 Apr 2026 |
| Withdrawal Update Form 2File: Form 2 Jare Royal Home.pdf | 25 Apr 2026 |
| Withdrawal Update Form 3File: Form 3 Jare Royal Home.pdf | 25 Apr 2026 |
| Building plan approvalFile: 1 OF 2_11zon.pdf | 30 Dec 2025 |
| Building plan approvalFile: 2 OF 2.pdf | 30 Dec 2025 |
| Withdrawal Update Form 1File: From 1.pdf | 4 Dec 2025 |
| Withdrawal Update Form 2File: Form 2 with sign.pdf | 4 Dec 2025 |
| Withdrawal Update Form 3File: Form 3 with sign.pdf | 4 Dec 2025 |
| Form 5 (FY 2024-2025)File: form 5 with sign.pdf | 3 Oct 2025 |
| Form 5 (FY 2023-2024)File: Jare Royal Homes Form 5.pdf | 3 Oct 2025 |
| Withdrawal Update Form 1File: From 1.pdf | 8 Sep 2025 |
| Withdrawal Update Form 2File: Form 2.pdf | 8 Sep 2025 |
| Withdrawal Update Form 3File: Form 3.pdf | 8 Sep 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Jare Royal Home Form 3 31-03-25.pdf | 15 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate 31-03-25 Jare Royal Home.pdf | 15 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Jare Royal Home 31-03-25.pdf | 14 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Sold Unsold.pdf | 15 Feb 2025 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A.pdf | 15 Feb 2025 |
| Disclosure for secured/unsecured finance availed for the projectFile: Secured_Unsecured finance.pdf | 15 Feb 2025 |
| Declaration in FORM BFile: Form B Notary.pdf | 11 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Q1.pdf | 11 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Q2.pdf | 11 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Q3.pdf | 11 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Q2.pdf | 11 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Q3.pdf | 11 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engg Certificate Q1.pdf | 11 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engg Certificate Q2.pdf | 11 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engg Certificate Q3.pdf | 11 Jan 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Jare Royal Homes Form 5.pdf | 23 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Image 1 (2).pdf | 9 Oct 2024 |
| Building plan approvalFile: SCAN 01-8-2024_compressed.pdf | 5 Aug 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: SCAN 01-8-2024_compressed.pdf | 5 Aug 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form_2.pdf | 20 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form_2.pdf | 20 Jul 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form_2A.pdf | 20 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 30 June 2023 (1).pdf | 2 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 30 Sept 2023.pdf | 2 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 31 Dec 2023 (1).pdf | 2 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 31 March 2024.pdf | 2 Jul 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 with sign_compressed.pdf | 2 Jul 2024 |
| Building plan approvalFile: pdf 1_compressed.pdf | 1 Mar 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: pdf 1_compressed.pdf | 1 Mar 2024 |
| Commencement Certificates / NA Order for plotted developmentFile: SKMBT_C22024013101310_compressed.pdf | 1 Mar 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE RERA.pdf | 12 Feb 2024 |
| Proforma of Agreement for saleFile: Draft Agreement- Sector 4- Jare.pdf | 19 Dec 2022 |
| Deviation Report with respect to model copy of AgreementFile: CameraScan.pdf | 19 Dec 2022 |
| Copy of the legal title reportFile: RERA Search Title Report Latest.pdf | 14 Dec 2022 |
| CERSAI detailsFile: CERSAI_Search_Report_200251417770_For_Asset_Based_Search_05_11_2022_11_19_59_027.pdf | 18 Nov 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate_compressed.pdf | 8 Nov 2022 |
| Layout approvalFile: Sanction Plan.PDF | 2 Nov 2022 |
| Building plan approvalFile: SETTING OUT PLAN.pdf | 2 Nov 2022 |
| Building plan approvalFile: Center line Model.pdf | 2 Nov 2022 |
| PAN CardFile: PAN Card.pdf | 2 Nov 2022 |
| Details of encumbrances concerned to FinanceFile: FinanceDeclaration.pdf | 2 Nov 2022 |
| Details of encumbrances concerned to LegalFile: FinanceDeclaration.pdf | 2 Nov 2022 |
| Copy of Layout Approval (in case of layout)File: Sanction Plan.PDF | 2 Nov 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: SETTING OUT PLAN.pdf | 2 Nov 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: Center line Model.pdf | 2 Nov 2022 |
| Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate_compressed.pdf | 2 Nov 2022 |
| Declaration about Commencement CertificateFile: Form D_compressed.pdf | 2 Nov 2022 |
| Declaration in FORM BFile: Form B Firm_compressed.pdf | 2 Nov 2022 |
| Proforma of Allotment letterFile: model form of allotment letter_compressed.pdf | 2 Nov 2022 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Bank Declaration_compressed.pdf | 2 Nov 2022 |
| Deviation Report with respect to Allotment letterFile: deviation report with respect to allotment letter 1.pdf | 2 Nov 2022 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 4 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 3 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 64 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep JARE ROYAL HOME on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near MOSHI13,700+ in Pune
Filed coordinates, straight-line distance. 76 registered projects within 2 km.
TANISH PARK
TANISH DEVELOPERS
Ajinkya Towers
APAK Bussiness Innovation Pvt Ltd
SILVER GARDENIA
SILVER PROMOTERS AND DEVELOPERS
Mangalam Life Park
Mangalam Buildcorp
SingaPune Ph 3
Xrbia Mirth Properties LLP
SingaPune Ph 2
Xrbia Mirth Properties LLP
Builder: SACHIN VASANT JARE
Sachin Vasant Jare has 4 registrations on MahaRERA, including Shridhar Heights and Jare Shrusti. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What does it mean that JARE ROYAL HOME shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if JARE ROYAL HOME is delayed beyond 30 Dec 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of JARE ROYAL HOME?
The registered promoter entity is SACHIN VASANT JARE, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in JARE ROYAL HOME?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for JARE ROYAL HOME?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at JARE ROYAL HOME?
The professionals named in the filing: Architect: Aadi Associates; Architect: Umesh Subrao Namde; Engineer: Suraj Namdev Adagale; Engineer: Santosh Mahalingappa Padsalge; Engineer: Shriram Ramesh Nagargoje; Chartered Accountant: VIVEK N LAHOTI. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in JARE ROYAL HOME?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.