ReraGenieLog inGet a buyer report

Home / Browse projects / Raigarh, Maharashtra / JAI HERITAGE

Registered No litigation declared Others project

JAI HERITAGE

By WINGS BUILDCON

RG-MH-75752 · RERA P52000031967 · Last updated on MahaRERA portal: 27 Apr 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 24 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedmoved 24 months from the original
5 of 11Construction stages donefurthest along: External plumbing and external plaster, 95%
30 of 73Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 54 documents Report an error

JAI HERITAGE is a Others project by WINGS BUILDCON in Raigarh, Maharashtra, registered with MahaRERA as P52000031967 on 29 Nov 2021. Possession is promised by 31 Dec 2026. The completion date has moved by 24 months from the original filing. 43 of the 73 units on this registration are recorded sold or booked, and 5 of 11 construction stages are filed complete.

At a glance

Project

  • NameJAI HERITAGE
  • TypeOthers
  • Location
    • CHAMBARKHIND
    • Chambharkhind
    • Mahad
    • Raigarh
    • 402301
  • Pincode402301
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52000031967
  • ReraGenie IDRG-MH-75752

Builder

  • NameWINGS BUILDCON
  • Entity typePartnership
  • PartnersRAJENDRA KRISHNA MEHETAR, DILIP BASTIMAL JAIN
  • Other registrations1 more →

Key dates

this monthRegisteredNov 2021First promiseDec 2024Revised toDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on29 Nov 2021
  • Promised completion31 Dec 2026
  • Revised completionRevised to 31 Dec 2026 (originally 31 Dec 2024)
  • Buildings1 building record
  • Documents filed54 files

Current status

59%43 of 73 units booked
82.9%Work done, per cost certificate

Figures as on 27 Apr 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
JAI HERITAGENA7767673

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 27 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 11 construction stages are filed complete. The stage furthest along is External plumbing and external plaster, at 95%.

JAI HERITAGE: 74% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises85%
Sanitary Fittings within the flats / premises50%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks85%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.95%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 27 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed1

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots1
Closed/Covered1

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area1,244 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on27 Apr 2026

Approvals and building plan

Sanctioning authorityMAHAD MUNICIPAL COUNCIL
Permissible FSI2629.86
Proposed, not sanctioned2,630 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSHOP NUMBER 9, 10, 11 MAHAD TRADE CENTER M G ROAD MAHAD
Estimated costRs 7.48 cr
Cost incurredRs 6.20 cr
Work done82.87%
BuildingWingEstimatedIncurred
JAI HERITAGENARs 7.48 crRs 6.20 cr

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectKISHORE SHINDE V
EngineerU D CHANDE CHANDE
EngineerVASTUKALP
Chartered AccountantCA RAJASHRI SACHIN GUJAR
PartnerRole in project
WINGS BUILDCON-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52000028034Dec 2024 → Dec 2026

Reason as filed by the promoterthe promoter hereby applyies for extension as in the year 2021 and 2022 there was flood and covid pandemic after that there was situation of cyclone in last year as this is flood prone area and in kokan it is continously raining hence from last 3 years the promoter is facing issues of flood hence extension is required flood cyclone these are all natural calamities and extension required is for one year only and not for one year ceratin force majesure conditions had occured then only promoter goes for section 6 flood prone area is been declared by goverment of maharashtra for mahad and authorit

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 24 Oct 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 28 Mar 2025
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 28 Mar 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 27 Jan 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2026

Documents filed54

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 1File: FORM 1.pdf27 Apr 2026
Form 2File: FORM 2.pdf27 Apr 2026
Form 3File: FORM 3.pdf27 Apr 2026
Disclosure of Sold and Booked InventoryFile: SOLD AND UNSOLD INVENTORY.pdf27 Apr 2026
Form 1File: FORM 1.pdf27 Apr 2026
Form 2File: FORM 2.pdf27 Apr 2026
Form 3File: FORM 3.pdf27 Apr 2026
Disclosure of Sold and Booked InventoryFile: SOLD AND UNSOLD INVENTORY.pdf27 Apr 2026
Withdrawal Update Form 1File: FORM 1.pdf27 Apr 2026
Withdrawal Update Form 2File: FORM 2.pdf27 Apr 2026
Withdrawal Update Form 3File: FORM 3.pdf27 Apr 2026
Form 1File: ARCHITECT CERTIFICATE.pdf20 Jan 2026
Form 2File: ENGINEER CERTIFICATE.pdf20 Jan 2026
Form 3File: CA CERTIFICATE.pdf20 Jan 2026
Disclosure of Sold and Booked InventoryFile: SOLD AND UNSOLD INVENTORY.pdf20 Jan 2026
Other - LegalFile: WORK COMPLETION.pdf1 Jul 2025
Other - FinanceFile: WORK COMPLETION.pdf1 Jul 2025
Other - TechnicalFile: WORK COMPLETION.pdf1 Jul 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5 (2022-23).pdf4 Apr 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5 (2023-24).pdf4 Apr 2025
Layout approvalFile: PLAN1.pdf28 Mar 2025
Building plan approvalFile: PLAN1.pdf28 Mar 2025
Copy of Layout Approval (in case of layout)File: PLAN1.pdf28 Mar 2025
Building Plan Approval / NA Order for plotted developmentFile: PLAN1.pdf28 Mar 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FORM 2A (21-22).pdf28 Mar 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A (22-23).pdf28 Mar 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A (23-24).pdf28 Mar 2025
Declaration in FORM BFile: DECLARATION FORM B.pdf27 Mar 2025
Disclosure of sold/ booked inventoryFile: SOLD UNSOLD INVENTORY.pdf27 Mar 2025
Declaration about Commencement CertificateFile: DECLARATION ABOUT COMMENCEMENT CERTIFICATE.pdf27 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf20 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3.pdf20 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf20 Feb 2025
Layout approvalFile: PLAN - converted.pdf27 Jan 2025
Building plan approvalFile: PLAN - converted.pdf27 Jan 2025
Copy of Layout Approval (in case of layout)File: PLAN - converted.pdf27 Jan 2025
Commencement Certificates / NA Order for plotted developmentFile: ORDER.pdf27 Jan 2025
Building Plan Approval / NA Order for plotted developmentFile: PLAN - converted.pdf27 Jan 2025
Declaration about Commencement CertificateFile: ORDER.pdf27 Jan 2025
Proforma of Allotment letterFile: PROFORMA OF ALLOTMENT LETTER.pdf16 Nov 2021
Proforma of Allotment letterFile: AGREEMENT.pdf16 Nov 2021
Copy of the legal title reportFile: TITLE SEARCH REPORT_compressed.pdf24 Oct 2021
Layout approvalFile: COPY OF LAYOUT PLAN.pdf14 Oct 2021
Building plan approvalFile: LAYOUT PLAN.pdf14 Oct 2021
PAN CardFile: PAN AND AADHAR CARD1.pdf14 Oct 2021
Details of encumbrancesFile: DETAILS OF EMCUMBRANCES.pdf14 Oct 2021
Copy of Layout Approval (in case of layout)File: COPY OF LAYOUT PLAN.pdf14 Oct 2021
Building Plan Approval / NA Order for plotted developmentFile: LAYOUT PLAN.pdf14 Oct 2021
Commencement Certificates / NA Order for plotted developmentFile: COMMENCEMENT CERTIFICATE1.pdf14 Oct 2021
Declaration about Commencement CertificateFile: DECLARATION REGARDING COMMENCEMENT CERTIFICATE.pdf14 Oct 2021
Declaration in FORM BFile: DECLARATION IN FORM B1.pdf14 Oct 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT CERTIFICATE1.pdf14 Oct 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER CERTIFICATE1.pdf14 Oct 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE1.pdf14 Oct 2021

How this compares with Raigarh

59%of this project is bookeddistrict median 29%
20%of Raigarh projects moved their completion datethis one moved by 24 months
26%of Raigarh registrations have lapsed or been cancelledthis one is on the register

Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.

Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep JAI HERITAGE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near CHAMBARKHIND5,900+ in Raigarh

2 kmJAI HERITAGECompleted 1Lapsed / revoked 1Other 1Dot size: filed unitsN

Filed coordinates, straight-line distance. 3 registered projects within 2 km.

Builder: WINGS BUILDCON

WINGS BUILDCON has 2 registrations on MahaRERA, including JAI HERITAGE and TULIP PALACE. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Raigarh district page.

Frequently asked questions

What are my rights if JAI HERITAGE is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of JAI HERITAGE?

The registered promoter entity is WINGS BUILDCON, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in JAI HERITAGE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for JAI HERITAGE?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at JAI HERITAGE?

The professionals named in the filing: Architect: KISHORE SHINDE V; Engineer: U D CHANDE CHANDE; Engineer: VASTUKALP; Chartered Accountant: CA RAJASHRI SACHIN GUJAR. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in JAI HERITAGE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About JAI HERITAGE. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save JAI HERITAGE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.