Home / Browse projects / Pune, Maharashtra / IVORY HEIGHTS
IVORY HEIGHTS
RG-MH-40809 · RERA P52100053447 · Last updated on MahaRERA portal: 13 Jul 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 2 other registrations and every project registered within 2 km.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
IVORY HEIGHTS is a Others project by CHAURANG VENTURES in Pune, Maharashtra, registered with MahaRERA as P52100053447 on 1 Nov 2023. Possession is promised by 31 Dec 2027. 246 of the 390 units on this registration are recorded sold or booked, and 14 of 55 construction stages are filed complete.
At a glance
Project
- NameIVORY HEIGHTS
- TypeOthers
- Location
- Dighi Alandi Road Next to AAKAR INDIGO
- CHINCHAWAD
- CHARHOLI
- Haveli
- Pune
- 412105
- Pincode412105
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100053447
- ReraGenie IDRG-MH-40809
Builder
- NameCHAURANG VENTURES
- Entity typePartnership
- PartnersABHIJIT SHIRISH BHAMRE, CHIRAYU KISHORE JAIN, BHAVIN PARAS BAMBOLI
- Other registrations2 more →
- Completed2 of 3
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on1 Nov 2023
- Promised completion31 Dec 2027
- Revised completionNone
- Buildings5 building records
- Documents filed98 files
Current status
Figures as on 13 Jul 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Wing A | NA | 4 | 4 | 114 | 8 | 122 |
| Wing B | NA | 17 | 15 | 88 | 2 | 90 |
| Wing C | NA | 18 | 15 | 178 | 0 | 178 |
| Wing D | NA | 0 | 0 | 0 | 0 | 0 |
| Row House | NA | 0 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building5
As on 13 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
14 of 55 construction stages are filed complete across 5 buildings. The stage furthest along is Internal walls, at 95%.
Wing A47%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 80% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 65% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 45% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 25% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Wing B54%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 95% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 60% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 40% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Wing C60%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 45% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 20% |
Wing D14%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 50% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Row House0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 13 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 0% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | No | Not applicable |
Land and ownership19
MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
| Landowner | Village | District |
|---|---|---|
| KANTABAI TUKARAM TAPKIR | CHARHOLI | Pune |
| SUKHARAM TUKARAM TAPKIR | CHARHOLI | Pune |
| ASHA SAKHARAM TAPKIR | CHARHOLI | Pune |
| SUJIT SUKHARAM TAPKIR | CHARHOLI | Pune |
| SUMIT SAKHARAM TAPKIR | CHARHOLI | Pune |
| GAJARABAI LAXMI SURESHAMBALE | CHARHOLI | Pune |
| Vaishali SomnathWalke | CHARHOLI | Pune |
| Kaluram Sakharam Tapkir | CHARHOLI | Pune |
| Indumati Kaluram Tapkir | CHARHOLI | Pune |
| Sandeep Kaluram Tapkir | CHARHOLI | Pune |
| Manisha Sandeep Tapkir | CHARHOLI | Pune |
| Sahil Sandeep Tapkir | CHARHOLI | Pune |
| Shravani Sandeep Tapkir | CHARHOLI | Pune |
| Madhuri Anuradha Thopte | CHARHOLI | Pune |
| Medha Subhash Tapkir | CHARHOLI | Pune |
| Subhash Annasaheb Tapkir | CHARHOLI | Pune |
| Harshad Subhash Tapkir | CHARHOLI | Pune |
| Supriya Harshad Tapkir | CHARHOLI | Pune |
| Pradnya Abhijeet Taware | CHARHOLI | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| Wing C | NA | Rs 14.71 cr | Rs 14.65 cr |
| Wing A | NA | Rs 11.28 cr | Rs 11.23 cr |
| Wing B | NA | Rs 8.52 cr | Rs 8.48 cr |
| - | NA | Rs 2.45 cr | Rs 2.45 cr |
| Wing D | NA | Rs 25.73 lakh | Rs 25.61 lakh |
Certifying professionals and partners6
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Amit R Ekambe |
| Engineer | MaheshKumar Thombare |
| Engineer | Sushilkumar Dhande |
| Chartered Accountant | SHASHANK R JAIN AND ASSOCIATES |
| Chartered Accountant | A C V K and Associates LLP |
| Chartered Accountant | Paras Thakkar Associates |
| Partner | Role in project |
|---|---|
| CHAURANG VENTURES | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 4 Oct 2023 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 12 Dec 2024 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 11 Oct 2025 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 11 Dec 2024Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Dec 2027
Documents filed98
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 98 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Form 1.pdf | 13 Jul 2026 |
| Withdrawal Update Form 2File: Form 2.pdf | 13 Jul 2026 |
| Withdrawal Update Form 3File: Form 3-compressed.pdf | 13 Jul 2026 |
| Form 2A (FY 2025-2026)File: Form2A-Ivory Heights.pdf | 28 May 2026 |
| Withdrawal Update Form 1File: Ivory Heights-form1.pdf | 20 Apr 2026 |
| Withdrawal Update Form 2File: Ivory Heights-form2.pdf | 20 Apr 2026 |
| Withdrawal Update Form 3File: Ivory Heights-form 3.pdf | 20 Apr 2026 |
| Withdrawal Update Form 1File: Form 1 of Ivory Height 31122025.pdf | 7 Jan 2026 |
| Withdrawal Update Form 2File: FORM 2-IVORY HEIGHTS 31122025.pdf | 7 Jan 2026 |
| Withdrawal Update Form 3File: FORM 3 IVORY HEIGHTS 31122025.pdf | 7 Jan 2026 |
| Withdrawal Update Form 1File: Form 1_Architects Certificate_IVORY HEIGHTS_13-10-25.pdf | 18 Oct 2025 |
| Withdrawal Update Form 2File: Form 2_Engineer Certificate_IVORY HEIGHTS_30092025.pdf | 18 Oct 2025 |
| Withdrawal Update Form 3File: Form 3 CA Certificate IVORY HEIGHTS 30092025.pdf | 18 Oct 2025 |
| Building plan approvalFile: Plan 1 to 4.pdf | 11 Oct 2025 |
| Building plan approvalFile: Plan 5 to 8.pdf | 11 Oct 2025 |
| Building plan approvalFile: Plan 9 to 12.pdf | 11 Oct 2025 |
| Building plan approvalFile: Plan 13 to 14.pdf | 11 Oct 2025 |
| Form 5 (FY 2024-2025)File: Form 5 Ivory Heights Signed.pdf | 23 Sep 2025 |
| Form 2A (FY 2024-2025)File: FORM-2A IVORY HEIGHTS.pdf | 4 Aug 2025 |
| Form 1File: ARCHITECT CERTIFICATE_ IH AS ON 30062025.pdf | 18 Jul 2025 |
| Form 2File: ENGNEERS CERTIFICATE IVORY HEIGHTS AS ON 30062025.pdf | 18 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: IH Sold Unsold merged.pdf | 18 Jul 2025 |
| Form 3File: Form 3 Ivory Heights AS ON 30062025.pdf | 18 Jul 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT CERTIFICATE_CV.pdf | 19 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Ivory Heights Last page 31032025_compressed.pdf | 19 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: MAHESHKUMAR_CV.pdf | 19 Apr 2025 |
| Declaration about Commencement CertificateFile: DECLERATION CERTIFICATE.pdf | 1 Feb 2025 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Form 3 Final 31122024 to be uploaded_compressed.pdf | 1 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT CERTIFICATE_DEC 2024 _CHAURANG VENTURES -.pdf | 30 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: MAHESHKUMAR THOMBRE ENGINEER CERTIFICATE.pdf | 30 Jan 2025 |
| Layout approvalFile: 1 OF 10.pdf | 12 Dec 2024 |
| Building plan approvalFile: 1 -3_merged.pdf | 12 Dec 2024 |
| Building plan approvalFile: 4-6_merged.pdf | 12 Dec 2024 |
| Building plan approvalFile: 7 -8_merged.pdf | 12 Dec 2024 |
| Building plan approvalFile: 9-10_merged.pdf | 12 Dec 2024 |
| Copy of Layout Approval (in case of layout)File: 1 OF 10.pdf | 12 Dec 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: 1 -3_merged.pdf | 12 Dec 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: 4-6_merged.pdf | 12 Dec 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: 7 -8_merged.pdf | 12 Dec 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: 9-10_merged.pdf | 12 Dec 2024 |
| Commencement Certificates / NA Order for plotted developmentFile: COMMINCEMENT CERT.pdf | 11 Dec 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5 23-24.pdf | 11 Dec 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 ARCHITECTS CERTIFICATE 30092024 IH.pdf | 19 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3 Ivory Height 30092024 Final-compressed.pdf | 19 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 IH 30092024.pdf | 19 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECTS CERTIFICATE_IH.pdf | 10 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER'S CERTIFICATE_IH.pdf | 10 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 _ ENGINEERING CERTIFICATE.pdf | 10 Jul 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A_IH.pdf | 10 Jul 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 of IH 30062024.pdf | 10 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 ARCHITECTS CERTIFICATE 310324 IH.pdf | 11 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 ENGINEER'S CERTIFCATE IH 2 310324.pdf | 11 Apr 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 IH FY 23 24 signed Copy_compressed.pdf | 11 Apr 2024 |
| Home Buyer /Allottee Grievance Redressal CellFile: Grievance contact details_IVORY HEIGHTS.pdf | 1 Apr 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form -1 Architect Certificate 311223.pdf | 12 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGG CERTIFICATE 311223.pdf | 12 Jan 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_Signed_Uploaded.pdf | 12 Jan 2024 |
| Layout approvalFile: Layout Plan-1_compressed.pdf | 6 Oct 2023 |
| Layout approvalFile: Layout Plan-2_compressed.pdf | 6 Oct 2023 |
| Building plan approvalFile: Building Plan-1_compressed.pdf | 6 Oct 2023 |
| Building plan approvalFile: Building Plan-2_compressed.pdf | 6 Oct 2023 |
| Building plan approvalFile: Building Plan-3_compressed.pdf | 6 Oct 2023 |
| Building plan approvalFile: Building Plan-4.pdf | 6 Oct 2023 |
| Building plan approvalFile: Building Plan-5_compressed.pdf | 6 Oct 2023 |
| Building plan approvalFile: Building Plan-6_compressed.pdf | 6 Oct 2023 |
| Building plan approvalFile: Building Plan-7.pdf | 6 Oct 2023 |
| Building plan approvalFile: Building Plan-8.pdf | 6 Oct 2023 |
| Building plan approvalFile: Building Plan-9.pdf | 6 Oct 2023 |
| Building plan approvalFile: Building Plan-10.pdf | 6 Oct 2023 |
| PAN CardFile: CV PAN CARD WITH SELF SINGNATURE.pdf | 6 Oct 2023 |
| Details of encumbrances concerned to FinanceFile: SELF DECLARATION CONCERN TO FINANCE AND LEGAL.pdf | 6 Oct 2023 |
| Details of encumbrances concerned to LegalFile: SELF DECLARATION CONCERN TO FINANCE AND LEGAL.pdf | 6 Oct 2023 |
| Copy of Layout Approval (in case of layout)File: Layout Plan-1_compressed.pdf | 6 Oct 2023 |
| Copy of Layout Approval (in case of layout)File: Layout Plan-2_compressed.pdf | 6 Oct 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: Building Plan-1_compressed.pdf | 6 Oct 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: Building Plan-2_compressed.pdf | 6 Oct 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: Building Plan-3_compressed.pdf | 6 Oct 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: Building Plan-4.pdf | 6 Oct 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: Building Plan-5_compressed.pdf | 6 Oct 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: Building Plan-6_compressed.pdf | 6 Oct 2023 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- Red flags and clear checks, the possession story, sanctions and sales, land and title, who you are dealing with
- Joined against the promoter's 2 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 98 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep IVORY HEIGHTS on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near CHINCHAWAD13,700+ in Pune
Filed coordinates, straight-line distance. 70 registered projects within 2 km.
TANISH PARK
TANISH DEVELOPERS
Ajinkya Towers
APAK Bussiness Innovation Pvt Ltd
SILVER GARDENIA
SILVER PROMOTERS AND DEVELOPERS
Mangalam Life Park
Mangalam Buildcorp
SingaPune Ph 3
Xrbia Mirth Properties LLP
SingaPune Ph 2
Xrbia Mirth Properties LLP
Builder: CHAURANG VENTURES
CHAURANG VENTURES has 3 registrations on MahaRERA, including SAPPHIRE TOWERS and SAPPHIRE TOWERS 2. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What are my rights if IVORY HEIGHTS is delayed beyond 31 Dec 2027?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of IVORY HEIGHTS?
The registered promoter entity is CHAURANG VENTURES, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in IVORY HEIGHTS?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for IVORY HEIGHTS?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at IVORY HEIGHTS?
The professionals named in the filing: Architect: Amit R Ekambe; Engineer: MaheshKumar Thombare; Engineer: Sushilkumar Dhande; Chartered Accountant: SHASHANK R JAIN AND ASSOCIATES; Chartered Accountant: A C V K and Associates LLP; Chartered Accountant: Paras Thakkar Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in IVORY HEIGHTS?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback