ISHAAN GHARKUL A

By Ishaan Buildcon

RG-MH-87702 · RERA P52100018238 · Last updated on MahaRERA portal: 28 Jan 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 36 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2025Possession promisedregistration recorded completed
4 of 11Construction stages doneacross 2 buildings; furthest along: Internal walls, 75%
30 of 143Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 289 documents Report an error

ISHAAN GHARKUL A is a Residential / Group Housing project by Ishaan Buildcon in Pune, Maharashtra, registered with MahaRERA as P52100018238 on 16 Oct 2018. The registration is recorded completed; possession was promised by 31 Dec 2025. The completion date has moved by 36 months from the original filing. 113 of the 143 units on this registration are recorded sold or booked, and 4 of 11 construction stages are filed complete.

At a glance

Project

  • NameISHAAN GHARKUL A
  • TypeResidential / Group Housing
  • Location
    • VELHA ROAD
    • NASRAPUR
    • Bhor
    • Pune
    • 412213
  • Pincode412213
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100018238
  • ReraGenie IDRG-MH-87702

Builder

  • NameIshaan Buildcon
  • Entity typePartnership
  • PartnersNASIR ABDUL KARIM SHAIKH, AJMALKHAN KAYAMKHAN PATHAN, VIJAY GHEVERCHAND OSWAL

Key dates

this monthRegisteredOct 2018First promiseDec 2022Revised toDec 2025Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on16 Oct 2018
  • Promised completion31 Dec 2025
  • Revised completionRevised to 31 Dec 2025 (originally 30 Dec 2022)
  • Buildings2 building records
  • Documents filed289 files

Current status

79%113 of 143 units booked
100.0%Work done, per cost certificate

Figures as on 28 Jan 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
ISHAAN GHARKUL ANA651070107
B 1 WingNA4436036

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 28 Jan 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 11 construction stages are filed complete across 2 buildings. The stage furthest along is Internal walls, at 75%.

ISHAAN GHARKUL A55%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises75%
Sanitary Fittings within the flats / premises30%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks30%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.30%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.35%
B 1 WingNot stated
ActivityProgress
ExcavationNot applicable
Basement (if any)Not applicable
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/PremisesNot applicable
Sanitary Fittings within the flats / premisesNot applicable
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water TanksNot applicable
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.Not applicable
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.Not applicable

Progress on shared amenities15

As on 28 Jan 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes10%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed135

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots135
Closed/Covered108
Open Space27

Land and ownership9

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area2,624 sq m
Land owned byThe promoter, with other names on the file
Named landowners9
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on13 Dec 2025
LandownerVillageDistrict
AMOL DATTATRAYA DALVINasrapurPune
VAISHALI VIKAS BANDALNigadePune
PUSHPA BHARAT DALVINasrapurPune
POOJA SANTOSH CHORGHERahatwadePune
ASHWINI YUVRAJ ZHANJEDhankawadiPune
KANCHAN BHARAT DALVINasrapurPune
MANDA SURESH WADKARKatrajPune
SURESH GANPAT WADKARKatrajPune
DATTATRAY MARUTI DALVINasrapurPune

Approvals and building plan

Sanctioning authorityPune Metropolitan Regional Development Authority Pune
Permissible FSI4622.41
Proposed, not sanctioned4,622 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branch2416, GEN THIMAYYA ROAD CAMP PUNE
Estimated costRs 10.60 cr
Cost incurredRs 10.60 cr
Work done100.0%
BuildingWingEstimatedIncurred
ISHAAN GHARKUL ANARs 6.50 crRs 6.50 cr
B 1 WingNARs 3.50 crRs 3.50 cr
-NARs 60.00 lakhRs 60.00 lakh

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectPESHAVE AND ASSOCIATES
EngineerAjmalkhan Pathan
EngineerRohinee Badgujar
Chartered AccountantAbhijit Mundada
Chartered AccountantSupriya Mundada
PartnerRole in project
Ishaan Buildcon-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100012845Dec 2022 → Dec 2025

Reason as filed by the promoterWe appreciate your concern that you have by default extended the date but we would like to inform you that We are in Rural Area and all labors have gone to their villages due to the pandemic Covid 19 and will return only after Diwali and as it is there are heavy rains too. We request you that looking at the overall pandemic situation of Covid 19 we request you to extend the date till 31.12.2022 and issue us certificate of extention to that effect

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 13 Oct 2018
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 25 May 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 13 Oct 2018
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 25 May 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed289

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 289 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 2A (FY 2025-2026)File: 2A 25-26.pdf28 Jan 2026
Form 2A (FY 2023-2024)File: 23-24 2A.pdf28 Jan 2026
Form 5 (FY 2023-2024)File: Form 5 2023-24 Ishaan.pdf28 Jan 2026
Form 5 (FY 2024-2025)File: 24-25 form 5 ishaan.pdf28 Jan 2026
Occupational CertificateFile: Completion Declaration.pdf28 Jan 2026
Withdrawal Update Form 1File: Ishaan Form 1 26_6_2025.pdf22 Jan 2026
Withdrawal Update Form 1File: Ishaan Form 1 26_6_2025.pdf22 Jan 2026
Withdrawal Update Form 2File: Ishaan Form 2 26_6.pdf22 Jan 2026
Withdrawal Update Form 2File: Ishaan Form 2 26_6.pdf22 Jan 2026
Withdrawal Update Form 3File: Ishaan form 3 8_8_25.pdf22 Jan 2026
Withdrawal Update Form 3File: Ishaan form 3 8_8_25.pdf22 Jan 2026
Occupational CertificateFile: Completion Certificate.pdf22 Jan 2026
Occupational CertificateFile: OC Verification.pdf22 Jan 2026
Form 5 (FY 2023-2024)File: Form 5 2023-24.pdf8 Dec 2025
Form 5 (FY 2024-2025)File: Form 5 2024-25_organized.pdf8 Dec 2025
Form 2A (FY 2018-2019)File: Ishaan Buildcon sep 18-19 (1).pdf15 Nov 2025
Form 2A (FY 2019-2020)File: Ishaan Buildcon sep 19-20 (1).pdf15 Nov 2025
Form 2A (FY 2020-2021)File: Ishaan Buildcon sep 20-21 (1).pdf15 Nov 2025
Form 2A (FY 2021-2022)File: Ishaan Buildcon sep 21-22 (1).pdf15 Nov 2025
Form 2A (FY 2022-2023)File: Ishaan Buildcon sep 22-23 (1).pdf15 Nov 2025
Form 2A (FY 2023-2024)File: Ishaan Buildcon sep 23-24 (1).pdf15 Nov 2025
Form 2A (FY 2024-2025)File: Ishaan Buildcon sep 24-25 (1).pdf15 Nov 2025
Form 2A (FY 2025-2026)File: Ishaan buildcon sep 25 (1).pdf15 Nov 2025
Form 5 (FY 2019-2020)File: Form 5 2019-20.pdf15 Nov 2025
Form 5 (FY 2018-2019)File: Ishaan Buildcon 2018 form 5.pdf14 Nov 2025
Form 5 (FY 2020-2021)File: Ishaan Buildcon 2020 form 5.pdf14 Nov 2025
Form 5 (FY 2021-2022)File: Ishaan Buildcon 2021 form 5.pdf14 Nov 2025
Form 5 (FY 2022-2023)File: Form 5 2022.pdf14 Nov 2025
Form 1File: Form 1 Ishaan Gharkul.pdf8 Oct 2025
Form 2File: ISHAAN GHARKUL A june 25.pdf8 Oct 2025
Form 3File: Jun 2025 Form 3.pdf8 Oct 2025
Disclosure of Sold and Booked InventoryFile: Sold Unsold Ishan Gharkul Jun 2025.pdf8 Oct 2025
Form 1File: Ishaan Buildcon march 2023 Form 1 Signed.pdf31 May 2025
Form 2File: Ishaan Buildcon march 2023 Form 2.pdf31 May 2025
Form 3File: Ishaan Buildcon March 2023 Form 3.pdf31 May 2025
Disclosure of Sold and Booked InventoryFile: Ishaan Buildcon march 2023.pdf31 May 2025
Form 1File: Ishaan Buildcon june 2023 Form 1 Signed.pdf31 May 2025
Form 2File: Ishaan Buildcon jun 2023 Form 2.pdf31 May 2025
Form 3File: Ishaan Buildcon jun 2023 Form 3.pdf31 May 2025
Disclosure of Sold and Booked InventoryFile: Ishaan Buildcon june 2023.pdf31 May 2025
Form 1File: Ishaan Buildcon Sep 2023 Form 1 Signed.pdf31 May 2025
Form 2File: Ishaan Buildcon Sep 2023 Form 2.pdf31 May 2025
Form 3File: Ishaan Buildcon sep 2023 Form 3.pdf31 May 2025
Disclosure of Sold and Booked InventoryFile: Ishaan Buildcon sep2023.pdf31 May 2025
Form 1File: Ishaan Buildcon Dec 2023 Form 1 Signed.pdf31 May 2025
Form 2File: Ishaan Buildcon Dec 2023 Form 2.pdf31 May 2025
Form 3File: Ishaan Buildcon Dec 2023 Form 3.pdf31 May 2025
Disclosure of Sold and Booked InventoryFile: Ishaan Buildcon Dec 2023.pdf31 May 2025
Form 1File: Ishaan Buildcon march 2024 Form 1 Signed.pdf31 May 2025
Form 2File: Ishaan Buildcon march 2024 Form 2.pdf31 May 2025
Form 3File: Ishaan Buildcon march 2024 Form 3.pdf31 May 2025
Disclosure of Sold and Booked InventoryFile: Ishaan Buildcon march 2024.pdf31 May 2025
Form 1File: Ishaan Buildcon june 2024 Form 1 Signed.pdf31 May 2025
Form 2File: Ishaan Buildcon june 2024 Form 2.pdf31 May 2025
Form 3File: Ishaan Buildcon jun 2024 Form 3.pdf31 May 2025
Disclosure of Sold and Booked InventoryFile: Ishaan Buildcon june 2024.pdf31 May 2025
Form 1File: Ishaan Buildcon sep 2024 Form 1 Signed.pdf31 May 2025
Form 2File: Ishaan Buildcon Sep 2024 Form 2.pdf31 May 2025
Form 3File: Ishaan Buildcon sep 2024 Form 3.pdf31 May 2025
Disclosure of Sold and Booked InventoryFile: Ishaan Buildcon Sep 2024.pdf31 May 2025
Form 1File: Ishaan Buildcon Dec 2024 Form 1 Signed.pdf31 May 2025
Form 3File: Ishaan Buildcon Dec 2024 Form 3.pdf31 May 2025
Disclosure of Sold and Booked InventoryFile: Ishaan Buildcon Sold unsold dec 2024.pdf31 May 2025
Form 2File: Dec 2024 ishaan form 2 (1).pdf31 May 2025
Form 1File: Ishaan Buildcon march 2025 Form 1 Signed.pdf31 May 2025
Form 2File: Ishaan Buildcon march 2025 Form 2.pdf31 May 2025
Form 3File: Ishaan Buildcon march 2025 Form 3.pdf31 May 2025
Disclosure of Sold and Booked InventoryFile: Ishaab Buildcon March 2025 sold unsold.pdf31 May 2025
Form 2A (FY 2024-2025)File: 2 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24) (1).pdf31 May 2025
Form 1File: Ishaan Buildcon Dec 2018 Form 1 Signed.pdf23 May 2025
Form 2File: Ishaan Buildcon Dec 2018 Form 2.pdf23 May 2025
Form 3File: Ishaan Buildcon Dec 2018 Form 3.pdf23 May 2025
Disclosure of Sold and Booked InventoryFile: Ishaan Buildcon Dec 2018.pdf23 May 2025
Form 1File: Ishaan Buildcon march 2019 Form 1 Signed.pdf23 May 2025
Form 2File: Ishaan Buildcon march 2019 Form 2.pdf23 May 2025
Form 3File: Ishaan Buildcon March 2019 Form 3.pdf23 May 2025
Disclosure of Sold and Booked InventoryFile: Ishaan Buildcon march 2019.pdf23 May 2025
Form 1File: Ishaan Buildcon june 2019 Form 1 Signed.pdf23 May 2025
Form 2File: Ishaan Buildcon june 2019 Form 2.pdf23 May 2025
Form 3File: Ishaan Buildcon june 2019 Form 3.pdf23 May 2025

How this compares with Pune

79%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 36 months
26%of Pune registrations have lapsed or been cancelledthis one is completed

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep ISHAAN GHARKUL A on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near NASRAPUR13,700+ in Pune

2 kmISHAAN GHARKUL ALapsed / revoked 4Other 2Dot size: filed unitsN

Filed coordinates, straight-line distance. 6 registered projects within 2 km.

Builder: Ishaan Buildcon

Ishaan Buildcon has 1 registration on MahaRERA, including ISHAAN GHARKUL A. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if ISHAAN GHARKUL A is delayed beyond 31 Dec 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of ISHAAN GHARKUL A?

The registered promoter entity is Ishaan Buildcon, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in ISHAAN GHARKUL A?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for ISHAAN GHARKUL A?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at ISHAAN GHARKUL A?

The professionals named in the filing: Architect: PESHAVE AND ASSOCIATES; Engineer: Ajmalkhan Pathan; Engineer: Rohinee Badgujar; Chartered Accountant: Abhijit Mundada; Chartered Accountant: Supriya Mundada. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in ISHAAN GHARKUL A?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About ISHAAN GHARKUL A. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save ISHAAN GHARKUL A to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.