ReraGenieLog inGet a buyer report

Home / Browse projects / Mumbai Suburban, Maharashtra / IQRA

Registration lapsed No litigation declared Residential / Group Housing project

IQRA

By SHUBHAM DEVELOPERS

RG-MH-26393 · RERA P51800008498 · Last updated on MahaRERA portal: 13 Jun 2023

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 16 months past the filed date
  • 7 complaints at MahaRERA
  • Completion date moved by 78 months
  • 2 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Jun 2025Possession promised16 months past this date
1 of 11Construction stages donefurthest along: Internal walls, 95%
7Complaints at MahaRERAon this registration
Jump to the 42 documents Report an error

IQRA is a Residential / Group Housing project by SHUBHAM DEVELOPERS in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800008498 on 19 Aug 2017. Possession was promised by 30 Jun 2025 and is now 16 months past that date. The completion date has moved by 78 months from the original filing. 7 complaints are on record with the regulator.

At a glance

Project

  • NameIQRA
  • TypeResidential / Group Housing
  • Location
    • Masjid Road
    • Santacruz East
    • Kolekalyan
    • Andheri
    • Mumbai Suburban
    • 400055
  • Pincode400055
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800008498
  • ReraGenie IDRG-MH-26393

Builder

  • NameSHUBHAM DEVELOPERS
  • Entity typePartnership
  • PartnerSHAHEZAD QAYYUM KHAN
  • Other registrations5 more →
  • Completed1 of 6
  • No longer live3 lapsed, de-registered or revoked
  • Declared earlier projects2 →

Key dates

16 months past promisethis monthRegisteredAug 2017First promiseDec 2018Revised toJun 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on19 Aug 2017
  • Promised completion30 Jun 2025
  • Revised completionRevised to 30 Jun 2025 (originally 31 Dec 2018)
  • Buildings1 building record
  • Documents filed42 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
IQRA HEIGHTSNA230000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 13 Jun 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

1 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 95%.

IQRA HEIGHTS: 66% average across the applicable activities

ActivityProgress
Excavation90%
Basement (if any)80%
Podiums (if any)0%
Plinth80%
Stilt Floor20%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises95%
Sanitary Fittings within the flats / premises70%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%

Progress on shared amenities15

As on 13 Jun 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed13

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots13
Closed/Covered10
Open Space3

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area887 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI2218.0
Proposed, not sanctioned2,218 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchJUHU ROAD OPP POLICE STATION SANTACRUZ WEST MUMBAI

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectKETAN BELSARE ELLORA PROJECT CONSULTANTS PRIVAT LIMITED
EngineerMr Nitin Kumar Jain of Sihavat Consultancy Services
Chartered AccountantA R Sodha & Co
PartnerRole in project
SHUBHAM DEVELOPERS-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800005759Dec 2018 → Apr 2020

Reason as filed by the promoter1. Financial issue due to slow down in the real Estate industry 2. non-payment of the flat consideration from the buyers 3. Now work has been started smoothly 4. more than 85% work has been completed 5. extension is required for completing the project and obtaining the occupation certificate

EXT51800016769Dec 2018 → Jun 2025

Reason as filed by the promoter1. Due to Covid Pandemic, the Project could not completed on time. 2. The Fund flow of the project got disturb due to the Covid Pandemic 3. There is no sale in last 2-3 years which caused shortage of fund flow 4. We have overall 75-80% work has complete and balance finishing work are in the process of completion. 5. We have arranged project fund to complete the project.

Complaints filed with MahaRERA7

Case no.ComplainantRespondentFiled
CC006000000199293Pinky SharmaM/S Shubham Developers07/12/2021
CC006000000210452Iqra Heights Welfare AssociationShubham Developers22/03/2022
CC006000000210494Vikas SoodM/s Shubham Developers23/03/2022
CC006000000210491Mr. Jabbar A. TanwarM/s Shubham Developers23/03/2022
CC006000000210492Javed B TanwarShubham Developers23/03/2022
CC006000000397932Mudassir Rashid KhanShubham Developers21/10/2023
CC006000000408593Abdul kayum Tambolim/s shubham Developers22/12/2023

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 28 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 28 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 28 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 28 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed42

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf13 Jun 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf13 Jun 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A March 2020.pdf13 Jun 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A March 2021.pdf13 Jun 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A March 2022.pdf13 Jun 2023
Certificates of CA (Form 3)File: Form 3 iqra.pdf10 Jun 2023
Proforma of Agreement for saleFile: AFS Final Draft Iqra.pdf10 Jun 2023
Proforma of Allotment letterFile: ALLOTMENT LETTER.pdf10 Jun 2023
Deviation Report with respect to Allotment letterFile: Deviation Report allotment letter.pdf10 Jun 2023
Deviation Report with respect to model copy of AgreementFile: Deviation Report Agreement for Sale.pdf10 Jun 2023
Details of encumbrances concerned to FinanceFile: No encumbrance Legal.PDF7 Jun 2023
Details of encumbrances concerned to FinanceFile: encumbrance Finance.PDF7 Jun 2023
Details of encumbrances concerned to LegalFile: No encumbrance Legal.PDF7 Jun 2023
Details of encumbrances concerned to LegalFile: encumbrance Finance.PDF7 Jun 2023
Declaration about Commencement CertificateFile: Declaration CC.PDF7 Jun 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A_MARCH 2020 Iqra Heights.pdf7 Jun 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A_MARCH 2021 Iqra Heights.pdf7 Jun 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A_MARCH 2022 Iqra Heights.pdf7 Jun 2023
Disclosure of sold/ booked inventoryFile: Disclosure Sold unsold.PDF7 Jun 2023
CERSAI detailsFile: CERSAI_Search_Report_200270728381_For_Debtor_Based_Search_06_06_2023_17_46_09_298.pdf7 Jun 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure SK.PDF7 Jun 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure AS.PDF7 Jun 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: Form 5 2017-18.PDF7 Jun 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5 2018-19.PDF7 Jun 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 2019-20.PDF7 Jun 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 2020-21.PDF7 Jun 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 2021-22.PDF7 Jun 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Decalration bankAccount.PDF7 Jun 2023
Declaration in FORM BFile: FORM B IQRA.pdf31 Jul 2017
Certificates of CA (Form 3)File: IQRA FORM 3.pdf31 Jul 2017
Proforma of Allotment letterFile: UNDERTAKING.pdf31 Jul 2017
Details of encumbrancesFile: ENCURBENCES IQRA FINAL.pdf29 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHIECT CERTIFICATE IQRA FINAL.pdf29 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEERS CERTIFICATE IQRA FINAL.pdf29 Jul 2017
Building plan approvalFile: Pages from IOD shubham.pdf28 Jul 2017
Layout approvalFile: layout plan shubham.pdf28 Jul 2017
PAN CardFile: PAN SHUBHAM.pdf28 Jul 2017
Copy of the legal title reportFile: LEGAL TITLE SHUBHAM.pdf28 Jul 2017
Copy of Layout Approval (in case of layout)File: layout plan shubham.pdf28 Jul 2017
Building Plan Approval (IOD)File: Pages from IOD shubham.pdf28 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: CC.pdf28 Jul 2017
OtherFile: LOI IQRA shubham.pdf28 Jul 2017

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered late
ProjectLocationFlatsStatusPromisedDelivered
SHUBHAM HEIGHTS0FF OLD NAGARDES ROAD NICOLAS WADI ANDHERI EAST MUMBAI59CompletedDec 2010Late, May 2011

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one moved by 78 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is among them

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep IQRA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Santacruz East6,700+ in Mumbai Suburban

2 kmIQRACompleted 130Lapsed / revoked 73Other 138Dot size: filed unitsN

Filed coordinates, straight-line distance. 341 registered projects within 2 km.

Builder: SHUBHAM DEVELOPERS

SHUBHAM DEVELOPERS has 6 registrations on MahaRERA, including OSCAR PLAZZA and R N GOLI SUNDARBAN PHASE 1 2. Its filings disclose 2 earlier MahaRERA projects: declares 0 of 2 past projects completed on time. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What does it mean that IQRA shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if IQRA is delayed beyond 30 Jun 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of IQRA?

The registered promoter entity is SHUBHAM DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in IQRA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against IQRA?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for IQRA?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at IQRA?

The professionals named in the filing: Architect: KETAN BELSARE ELLORA PROJECT CONSULTANTS PRIVAT LIMITED; Engineer: Mr Nitin Kumar Jain of Sihavat Consultancy Services; Chartered Accountant: A R Sodha & Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in IQRA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About IQRA. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save IQRA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.