ReraGenieLog inGet a buyer report

Home / Browse projects / Mumbai Suburban, Maharashtra / Integrated Ramicon A

Registered No litigation declared Residential / Group Housing project

Integrated Ramicon A

By Integrated Affordable Home Private Limited

RG-MH-17661 · RERA P51800056120 · Last updated on MahaRERA portal: 18 May 2026

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 1 other registration.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Dec 2027Possession promisedno revision filed
4 of 11Construction stages donefurthest along: Slabs of Super Structure, 41%
41 of 105Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 85 documents Report an error

Integrated Ramicon A is a Residential / Group Housing project by Integrated Affordable Home Private Limited in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800056120 on 11 May 2024. Possession is promised by 31 Dec 2027. 64 of the 105 units on this registration are recorded sold or booked, and 4 of 11 construction stages are filed complete.

At a glance

Project

  • NameIntegrated Ramicon A
  • TypeResidential / Group Housing
  • Location
    • GOREGAON
    • Borivali
    • Mumbai Suburban
    • 400104
  • Pincode400104
  • RERA no.P51800056120
  • ReraGenie IDRG-MH-17661

Builder

  • NameIntegrated Affordable Home Private Limited
  • Entity typeCompany
  • DirectorsKANTILAL SAVLA, SAGAR SATRA, NAYNESH SATRA, NISHIT SAVLA
  • Other registrations1 more →

Key dates

this monthRegisteredMay 2024PromisedDec 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on11 May 2024
  • Promised completion31 Dec 2027
  • Revised completionNone
  • Buildings1 building record
  • Documents filed85 files

Current status

61%64 of 105 units booked
37.0%Work done, per cost certificate

Figures as on 18 May 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
INTEGRATED RAMICON ANA1701050105

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 18 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 41%.

INTEGRATED RAMICON A: 40% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor0%
Slabs of Super Structure41%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 18 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed52

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots52
Closed/Covered52

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area7,269 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on6 Aug 2025

Approvals and building plan

Sanctioning authorityMMRDA
Permissible FSI6200.0
Proposed, not sanctioned2,708 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchKOTAK MAHINDRA BANK LTD 5 C/ LI, MITTAL COURT, 224, NARIMAN POINT, MUMBAI 400021
Estimated costRs 48.40 cr
Cost incurredRs 17.93 cr
Work done37.04%
BuildingWingEstimatedIncurred
INTEGRATED RAMICON ANARs 43.56 crRs 16.13 cr
-NARs 4.84 crRs 1.79 cr

Certifying professionals and partners8

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSNEHAL S SHAH
ArchitectM/s. Techno Arch
ArchitectSNEHAL SHAH
EngineerMilind Gangaram Gavalwad
EngineerDAYANAND SALUNKE
EngineerJIGAR GHEDIA
Chartered AccountantNEHALI & CO
Chartered Accountantanil Rohira
PartnerRole in project
Integrated Affordable Home Private Limited-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 3 Feb 2024
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 12 Feb 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 3 Feb 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 3 Feb 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2027

Documents filed85

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 85 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1 Certi Wing A 13 05 2026.pdf18 May 2026
Withdrawal Update Form 2File: Form 2 Ramicon A.pdf18 May 2026
Withdrawal Update Form 3File: Signed CA Certificate_Ramicon A wing Mar 26 (1).pdf18 May 2026
Withdrawal Update Form 1File: Form 1_Ramicon Wing A_Dec25.pdf27 Jan 2026
Withdrawal Update Form 2File: Form 2 Ramicon A Dec 25.pdf27 Jan 2026
Withdrawal Update Form 3File: Form 3 Ramicon A Dec 25.pdf27 Jan 2026
Withdrawal Update Form 1File: INTEGRATED RAMICON A WING SEPT 25.pdf28 Oct 2025
Withdrawal Update Form 2File: Form 2 Ramicon A.pdf28 Oct 2025
Withdrawal Update Form 3File: Form 3 Ramicon A.pdf28 Oct 2025
Form 5 (FY 2024-2025)File: integrated ramicon a.pdf7 Oct 2025
Withdrawal Update Form 1File: Form 1 - Ramicon A - Jun 25.pdf3 Oct 2025
Withdrawal Update Form 2File: Form 2 - Ramicon A - Jun 25.pdf3 Oct 2025
Withdrawal Update Form 3File: Form 3 - Ramicon A - Jun 25.pdf3 Oct 2025
Form 2A (FY 2024-2025)File: Form 2A Ramicon A (2).pdf3 Oct 2025
Withdrawal Update Form 1File: Form 1 - Ramicon A - Jun 25.pdf12 Sep 2025
Withdrawal Update Form 2File: Form 2 - Ramicon A - Jun 25.pdf12 Sep 2025
Withdrawal Update Form 3File: Form 3 - Ramicon A - Jun 25.pdf12 Sep 2025
Withdrawal Update Form 1File: Form 1 - Ramicon A - Jun 25.pdf10 Sep 2025
Withdrawal Update Form 2File: Form 2 - Ramicon A - Jun 25.pdf10 Sep 2025
Withdrawal Update Form 3File: Form 3 - Ramicon A - Jun 25.pdf10 Sep 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Ramicon A.pdf16 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Ramiocn A.pdf16 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 05_form 1 (wing a - ramicon).pdf22 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Ramicon A.pdf3 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_IAHPL A Wing_Oct-Dec 2024.pdf3 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1- Ramicon A.pdf24 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3.pdf5 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2.pdf5 Dec 2024
Disclosure of sold/ booked inventoryFile: Ramiocn A Inventory.pdf5 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Ramicon A.pdf9 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Remicon A wing Apr-June 2024.pdf13 Aug 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate-Ramicon A wing June 24.pdf13 Aug 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect's Certificate for Wing A.pdf25 Jul 2024
CERSAI detailsFile: IAHPL Cersai Ramicon A.pdf1 Apr 2024
Other - TechnicalFile: Ramicon A - Specimen format of Declaration - layout.pdf19 Feb 2024
Layout approvalFile: 10.pdf12 Feb 2024
Layout approvalFile: 11.pdf12 Feb 2024
Layout approvalFile: 12.pdf12 Feb 2024
Layout approvalFile: 13.pdf12 Feb 2024
Layout approvalFile: 14.pdf12 Feb 2024
Layout approvalFile: 15.pdf12 Feb 2024
Layout approvalFile: 16.pdf12 Feb 2024
Layout approvalFile: 9.pdf12 Feb 2024
Layout approvalFile: 3.pdf12 Feb 2024
Layout approvalFile: 4.pdf12 Feb 2024
Layout approvalFile: 5.pdf12 Feb 2024
Layout approvalFile: 6.pdf12 Feb 2024
Layout approvalFile: 7 (1).pdf12 Feb 2024
Layout approvalFile: 8.pdf12 Feb 2024
Copy of Layout Approval (in case of layout)File: 3.pdf12 Feb 2024
Copy of Layout Approval (in case of layout)File: 4.pdf12 Feb 2024
Copy of Layout Approval (in case of layout)File: 5.pdf12 Feb 2024
Copy of Layout Approval (in case of layout)File: 6.pdf12 Feb 2024
Copy of Layout Approval (in case of layout)File: 7 (1).pdf12 Feb 2024
Copy of Layout Approval (in case of layout)File: 8.pdf12 Feb 2024
Copy of Layout Approval (in case of layout)File: 9.pdf12 Feb 2024
Copy of Layout Approval (in case of layout)File: 10.pdf12 Feb 2024
Copy of Layout Approval (in case of layout)File: 11.pdf12 Feb 2024
Copy of Layout Approval (in case of layout)File: 12.pdf12 Feb 2024
Copy of Layout Approval (in case of layout)File: 13.pdf12 Feb 2024
Copy of Layout Approval (in case of layout)File: 14.pdf12 Feb 2024
Copy of Layout Approval (in case of layout)File: 15.pdf12 Feb 2024
Copy of Layout Approval (in case of layout)File: 16.pdf12 Feb 2024
Proforma of Agreement for saleFile: 1 Proforma of Agreement for sale (1) (1).pdf10 Feb 2024
Deviation Report with respect to model copy of AgreementFile: Deviation to Agreement.pdf10 Feb 2024
Details of encumbrances concerned to FinanceFile: Encumrance Legal.pdf9 Feb 2024
Details of encumbrances concerned to LegalFile: Encumrance Legal.pdf9 Feb 2024
Deviation Report with respect to Allotment letterFile: Deviation - Allotment Letter (1).pdf9 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA Certificate_Ramicon A wing_Reg.pdf5 Feb 2024
Layout approvalFile: plans (1).pdf3 Feb 2024
Layout approvalFile: 2.pdf3 Feb 2024
Building plan approvalFile: 05_amended cc_010722.pdf3 Feb 2024
PAN CardFile: company PAN card.pdf3 Feb 2024
Copy of the legal title reportFile: Title Report 01 04 24.pdf3 Feb 2024
Details of encumbrances concerned to FinanceFile: Fin Encumbrance (1).pdf3 Feb 2024
Details of encumbrances concerned to LegalFile: Fin Encumbrance (1).pdf3 Feb 2024
Copy of Layout Approval (in case of layout)File: plans (1).pdf3 Feb 2024
Copy of Layout Approval (in case of layout)File: 2.pdf3 Feb 2024
Building Plan Approval / NA Order for plotted developmentFile: 05_amended cc_010722.pdf3 Feb 2024
Commencement Certificates / NA Order for plotted developmentFile: 01_revalidated cc upto plinth_010722.pdf3 Feb 2024

How this compares with Mumbai Suburban

61%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one has not
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is on the register

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Integrated Ramicon A on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near GOREGAON6,700+ in Mumbai Suburban

Builder: Integrated Affordable Home Private Limited

Integrated Affordable Home Private Limited has 2 registrations on MahaRERA, including Integrated Ramicon and Integrated Ramicon A. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if Integrated Ramicon A is delayed beyond 31 Dec 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Integrated Ramicon A?

The registered promoter entity is Integrated Affordable Home Private Limited, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Integrated Ramicon A?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Integrated Ramicon A?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Integrated Ramicon A?

The professionals named in the filing: Architect: SNEHAL S SHAH; Architect: M/s. Techno Arch; Architect: SNEHAL SHAH; Engineer: Milind Gangaram Gavalwad; Engineer: DAYANAND SALUNKE; Engineer: JIGAR GHEDIA. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Integrated Ramicon A?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Integrated Ramicon A. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Integrated Ramicon A to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.