ReraGenieLog inGet a buyer report

Home / Browse projects / Mumbai Suburban, Maharashtra / Infra - Azura Height

Registered No litigation declared Mixed project

Infra - Azura Height

By SALIM MOHAMMED AMIN BEHLIM

RG-MH-69496 · RERA PM1180002500596 · Last updated on MahaRERA portal: 10 Sep 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 4 months
  • 1 extension taken
  • Allotment letter deviates from the model form

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Apr 2031Possession promisedmoved 4 months from the original
2 of 9Construction stages donefurthest along: Slabs of Super Structure, 55%
0Complaints at MahaRERAon this registration
Jump to the 25 documents Report an error

Infra - Azura Height is a Mixed project by SALIM MOHAMMED AMIN BEHLIM in Mumbai Suburban, Maharashtra, registered with MahaRERA as PM1180002500596 on 18 Aug 2025. Possession is promised by 30 Apr 2031. The completion date has moved by 4 months from the original filing.

At a glance

Project

  • NameInfra - Azura Height
  • TypeMixed
  • Location
    • PATEL ESTATE ROAD
    • Jogeshwari West
    • Oshiwara
    • Andheri
    • Mumbai Suburban
    • 400102
  • Pincode400102
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PM1180002500596
  • ReraGenie IDRG-MH-69496

Builder

  • NameSALIM MOHAMMED AMIN BEHLIM
  • Entity typeProprietor
  • GSTIN27ACRPB4780F1ZG

Key dates

this monthRegisteredAug 2025First promiseDec 2030Revised toApr 2031

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on18 Aug 2025
  • Promised completion30 Apr 2031
  • Revised completionRevised to 30 Apr 2031 (originally 30 Dec 2030)
  • Buildings1 building record
  • Documents filed25 files

Current status

9.3%Work done, per cost certificate

Figures as on 10 Sep 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
INFRA-AZURA HEIGHTNA00000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 10 Sep 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

2 of 9 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 55%.

INFRA-AZURA HEIGHT: 33% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)Not applicable
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure55%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks40%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 10 Sep 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyNo0%
Sewerage (Chamber, Lines, Septic Tank , STP)No0%
Storm Water DrainsNo0%
Landscaping & Tree PlantingNo0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNo0%
Water conservation /Rain water harvestingNo0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNo0%
Electrical meter room, sub-station, receiving stationNo0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed65

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots65
Podiums / Upper Parking Floor65

Land and ownership1

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area682 sq m
Land owned byNot the promoter
Named landowners1
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on9 Jul 2025
LandownerVillageDistrict
RAMKRISHNA NARSU PUNJAOshiwaraMumbai Suburban

Approvals and building plan

Sanctioning authorityMCGM
Permissible FSI682.3
Proposed, not sanctioned682 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchMTNL BUILDING, GROUND FLOOR, S.V. ROAD, MUMBAI
Estimated costRs 16.27 cr
Cost incurredRs 1.51 cr
Work done9.29%
BuildingWingEstimatedIncurred
INFRA-AZURA HEIGHTNARs 16.27 crRs 1.51 cr
-NA-Rs 9

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectHingoo Architects
EngineerDinesh H Mehta
Chartered AccountantR S L & CO.
PartnerRole in project
S.B.CONSTRUCTION-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

PM1180002500596/WarDec 2030 → Apr 2031

Reason as filed by the promoterNA

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportNot on the file

    A lawyer's report on who owns the land and what is registered against it.

  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 8 Jul 2025
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 8 Sep 2026
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 8 Sep 2026Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 Apr 2031

Documents filed25

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 2A (FY 2025-2026)File: FORM2A.pdf10 Sep 2026
Building plan approvalFile: 150925 Drg 1-7mb.pdf8 Sep 2026
Commencement certificateFile: 101025 FCC upto 8th floor.pdf8 Sep 2026
Building plan approvalFile: new amemndment drawing 150526.pdf8 Sep 2026
Commencement certificateFile: 260526 FurtherCC_03.pdf8 Sep 2026
Withdrawal Update Form 1File: 041025 Architect.pdf8 Sep 2026
Withdrawal Update Form 1File: 040126 Architect.pdf8 Sep 2026
Withdrawal Update Form 1File: 060426 Architect.pdf8 Sep 2026
Withdrawal Update Form 1File: 041025 Architect.pdf8 Sep 2026
Withdrawal Update Form 2File: 041025 Engineer.pdf8 Sep 2026
Withdrawal Update Form 2File: 040126 Engineer.pdf8 Sep 2026
Withdrawal Update Form 2File: 060426 Engineer.pdf8 Sep 2026
Withdrawal Update Form 2File: 041025 Engineer.pdf8 Sep 2026
Withdrawal Update Form 3File: 041025 CA.pdf8 Sep 2026
Withdrawal Update Form 3File: 040126 CA.pdf8 Sep 2026
Withdrawal Update Form 3File: 060426 CA.pdf8 Sep 2026
Withdrawal Update Form 3File: 041025 CA 01.pdf8 Sep 2026
Withdrawal Update Form 1File: 060826 Architects Certificate.pdf7 Sep 2026
Withdrawal Update Form 1File: 060826 Architects Certificate.pdf7 Sep 2026
Withdrawal Update Form 2File: 08082026 Engineers Certificate.pdf7 Sep 2026
Withdrawal Update Form 2File: 08082026 Engineers Certificate.pdf7 Sep 2026
Withdrawal Update Form 3File: 110826 CAs Certificate.pdf7 Sep 2026
Withdrawal Update Form 3File: 110826 CAs Certificate.pdf7 Sep 2026
Layout approvalFile: Drawing Flat.pdf8 Jul 2025
Declaration and undertaking (Annexure A)File: Annexure A - OP OR.pdf8 Jul 2025

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one moved by 4 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is on the register

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Infra - Azura Height on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Jogeshwari West6,700+ in Mumbai Suburban

2 kmInfra - Azura HeightCompleted 110Lapsed / revoked 58Abeyance 1Other 129Dot size: filed unitsN

Filed coordinates, straight-line distance. 298 registered projects within 2 km.

Builder: SALIM MOHAMMED AMIN BEHLIM

SALIM MOHAMMED AMIN BEHLIM has 1 registration on MahaRERA, including Infra - Azura Height. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if Infra - Azura Height is delayed beyond 30 Apr 2031?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Infra - Azura Height?

The registered promoter entity is SALIM MOHAMMED AMIN BEHLIM, a proprietor as per the filing. Its GSTIN 27ACRPB4780F1ZG can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Infra - Azura Height?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Infra - Azura Height?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Infra - Azura Height?

The professionals named in the filing: Architect: Hingoo Architects; Engineer: Dinesh H Mehta; Chartered Accountant: R S L & CO.. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Infra - Azura Height?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Infra - Azura Height. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Infra - Azura Height to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.