ReraGenieLog inGet a buyer report

Home / Browse projects / Nanded, Maharashtra / INFINATE ONE

Completed No litigation declared Residential / Group Housing project

INFINATE ONE

By MAYURESH GOVIND BODKE

RG-MH-14757 · RERA P51100049246 · Last updated on MahaRERA portal: 11 Mar 2025

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

Nothing adverse is on this record. The buyer report still reads the filed documents themselves.

See what the report covers Free either way: or have every new Nanded registration emailed to you, free during the pilot beta.
Dec 2025Possession promisedregistration recorded completed
11 of 11Construction stages doneevery applicable stage filed complete
0Complaints at MahaRERAon this registration
Jump to the 48 documents Report an error

INFINATE ONE is a Residential / Group Housing project by MAYURESH GOVIND BODKE in Nanded, Maharashtra, registered with MahaRERA as P51100049246 on 3 Feb 2023. The registration is recorded completed; possession was promised by 31 Dec 2025.

At a glance

Project

  • NameINFINATE ONE
  • TypeResidential / Group Housing
  • Location
    • CTS NO. 10010
    • PLOT NO. 6&7
    • SHARDA NAGAR
    • MAUJE ASADULLABAD
    • NANDED
    • NANDED
    • Nanded Waghala (M Corp.)
    • 431602
  • Pincode431602
  • RERA no.P51100049246
  • ReraGenie IDRG-MH-14757

Builder

  • NameMAYURESH GOVIND BODKE
  • Entity typeIndividual

Key dates

this monthRegisteredFeb 2023PromisedDec 2025Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on3 Feb 2023
  • Promised completion31 Dec 2025
  • Revised completionNone
  • Buildings1 building record
  • Documents filed48 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
INFINATE ONENA50000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 11 Mar 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

11 of 11 construction stages are filed complete.

INFINATE ONE: 100% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 11 Mar 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes50%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes50%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed26

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots26
Open Space26

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area465 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI1014.64
Proposed, not sanctioned1,015 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSHOP NO 16/17, SIDDHANCHAL PHASE IV, VASANT VIHARPOKHRAN ROAD 2, THANE

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSHAIKH TAJJUDIN
EngineerER A M ADIL
Chartered AccountantCA MAYUR P AGRAWAL
PartnerRole in project
MAYURESH GOVIND BODKE-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 20 Jan 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 23 Dec 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 23 Dec 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 23 Dec 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 4 Mar 2025

Documents filed48

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A Infinate One.pdf11 Mar 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 Infinate One.pdf11 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 June compressed.pdf10 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Sep_compressed.pdf10 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Dec_compressed.pdf10 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Mar_compressed.pdf10 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: From 2 June_compressed.pdf10 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Sep_compressed.pdf10 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 March new.pdf7 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 June new.pdf7 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Sep new.pdf7 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Dec new.pdf7 Mar 2025
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Occupancy Certificate.pdf4 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: declaration[1].pdf16 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: declaration[1].pdf16 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: declaration[1].pdf16 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: declaration[1].pdf16 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Self Declaration by Promoters to Bank Sept 23.pdf11 Dec 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Self Declaration by Promoters to Bank Sept 23.pdf11 Dec 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Self Declaration by Promoters to Bank Sept 23.pdf11 Dec 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5- March 23.pdf14 Oct 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A- Quality Assurance_11zon.pdf9 Oct 2023
Disclosure of sold/ booked inventoryFile: disclosure of booking .pdf8 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: declaration march.pdf22 Sep 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: declaration june.pdf22 Sep 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: declaration march.pdf22 Sep 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: declaration june.pdf22 Sep 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: declaration march.pdf22 Sep 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: declaration june.pdf22 Sep 2023
Declaration in FORM BFile: Form B Revised.pdf25 Jan 2023
Declaration about Commencement CertificateFile: Format D declaration of commencement certificate.pdf24 Jan 2023
Copy of the legal title reportFile: Title Report Infinateone New.pdf20 Jan 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest in other Real Estate Organisation.pdf17 Jan 2023
Proforma of Agreement for saleFile: Final Agreement to sale.pdf17 Jan 2023
Proforma of Allotment letterFile: Infinate One RERA Allotment Letter Final.pdf17 Jan 2023
Layout approvalFile: Shardanagar Layout Report compressed.pdf23 Dec 2022
Building plan approvalFile: Shardanagar Layout Report compressed.pdf23 Dec 2022
PAN CardFile: Mayuresh Bodke PAN Card Resize.pdf23 Dec 2022
Details of encumbrances concerned to FinanceFile: Non encumbrances_compressed.pdf23 Dec 2022
Details of encumbrances concerned to LegalFile: Non encumbrances_compressed.pdf23 Dec 2022
Copy of Layout Approval (in case of layout)File: Shardanagar Layout Report compressed.pdf23 Dec 2022
Building Plan Approval / NA Order for plotted developmentFile: Shardanagar Layout Report compressed.pdf23 Dec 2022
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf23 Dec 2022
CERSAI detailsFile: CERSAI_Search_Report_200254983918_For_Asset_Based_Search_16_12_2022_14_00_15_467.pdf23 Dec 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3- CA Certificate_11zon.pdf23 Dec 2022
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Separate bank account including non - encumbrance_11zon.pdf23 Dec 2022
Deviation Report with respect to Allotment letterFile: Deviation Letter_11zon.pdf23 Dec 2022
Deviation Report with respect to model copy of AgreementFile: Deviation Letter_11zon.pdf23 Dec 2022

How this compares with Nanded

3%of Nanded projects moved their completion datethis one has not
25%of Nanded registrations have lapsed or been cancelledthis one is completed

Computed across the 100+ Nanded projects on ReraGenie, from their own filings.

Keep INFINATE ONE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near NANDED100+ in Nanded

Builder: MAYURESH GOVIND BODKE

MAYURESH GOVIND BODKE has 1 registration on MahaRERA, including INFINATE ONE. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Nanded district page.

Frequently asked questions

What are my rights if INFINATE ONE is delayed beyond 31 Dec 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of INFINATE ONE?

The registered promoter entity is MAYURESH GOVIND BODKE, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in INFINATE ONE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for INFINATE ONE?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at INFINATE ONE?

The professionals named in the filing: Architect: SHAIKH TAJJUDIN; Engineer: ER A M ADIL; Chartered Accountant: CA MAYUR P AGRAWAL. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in INFINATE ONE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About INFINATE ONE. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save INFINATE ONE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.