Indraprashth
RG-MH-09238 · RERA P52000005562 · Last updated on MahaRERA portal: 28 Apr 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Completion date moved by 90 months
- 3 extensions taken
Clear
- No litigation declared
- No complaints on record
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Indraprashth is a Residential / Group Housing project by Suresh LILADHAR Toprani in Raigarh, Maharashtra, registered with MahaRERA as P52000005562 on 11 Aug 2017. Possession is promised by 31 Dec 2026. The completion date has moved by 90 months from the original filing. 9 of the 58 units on this registration are recorded sold or booked, and 5 of 22 construction stages are filed complete.
At a glance
Project
- NameIndraprashth
- TypeResidential / Group Housing
- Location
- Raigarh Road
- Dasturi Naka
- Mahad
- Raigarh
- 402301
- Pincode402301
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52000005562
- ReraGenie IDRG-MH-09238
Builder
- NameSuresh LILADHAR Toprani
- Entity typeIndividual
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on11 Aug 2017
- Promised completion31 Dec 2026
- Revised completionRevised to 31 Dec 2026 (originally 30 Jun 2019)
- Buildings2 building records
- Documents filed76 files
Current status
Figures as on 28 Apr 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Indraprashth Building 1 | NA | 8 | 8 | 44 | 0 | 44 |
| Indraprashth Building 2 | NA | 8 | 0 | 14 | 0 | 14 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building2
As on 28 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
5 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Internal walls, at 97%.
Indraprashth Building 169%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 97% |
| Sanitary Fittings within the flats / premises | 70% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 95% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Indraprashth Building 20%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 28 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 80% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | No | Not applicable |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 80% |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | No | Not applicable |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 80% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | Yes | 0% |
Parking filed3
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership4
MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
| Landowner | Village | District |
|---|---|---|
| HANSABEN HANSRAJ PATEL | Bhingaloli | Ratnagiri |
| VIMLABEN SHANTILAL PATEL | Bhingaloli | Ratnagiri |
| PREMJI DAYABHAI PATEL | Bhingaloli | Ratnagiri |
| AMRUTLAL DEVJI PATEL | Mahad | Raigarh |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| Indraprashth Building 1 | NA | Rs 5.96 cr | Rs 5.87 cr |
| Indraprashth Building 2 | NA | Rs 2.98 cr | - |
| - | NA | Rs 65.00 lakh | Rs 55.25 lakh |
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Agharkar Consulting Engineers Pvt Ltd VILAS AGHARKAR |
| Engineer | Agharkar Consulting Engineers Pvt Ltd VILAS AGHARKAR |
| Chartered Accountant | MS BUTALA MS BUTALA |
| Chartered Accountant | BUTALA TRIVEDI AND ASSO LLP |
| Partner | Role in project |
|---|---|
| Suresh LILADHAR Toprani | - |
Extensions applied for3
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterImpact and delay due to COVID Pandemic. Unavailability of material and workforce. Pending 5th and 6th floor CC for Building No. 1.
Reason as filed by the promoterTHE PROJECT DATE IS EXTENDED TILL 29/05/2020 THE REASON BEHIND THAT IS THERE WAS SHORTAGE OF MATERIAL AND HENCE EXTENSION OF THE PROJECT TO BE GRANTED.
Reason as filed by the promoterthe construction is about to complete just some minor work is pending
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 26 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 30 Jul 2022 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 30 Jul 2022 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 23 Mar 2018Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Dec 2026
Documents filed76
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: FORM 1.pdf | 28 Apr 2026 |
| Withdrawal Update Form 2File: FORM 2.pdf | 28 Apr 2026 |
| Withdrawal Update Form 3File: FORM 3.pdf | 28 Apr 2026 |
| Form 1File: FORM 1.pdf | 11 Feb 2026 |
| Form 2File: FORM 2.pdf | 11 Feb 2026 |
| Form 3File: FORM 3.pdf | 11 Feb 2026 |
| Disclosure of Sold and Booked InventoryFile: SOLD AND UNSOLD INVENTORY.pdf | 11 Feb 2026 |
| Other - TechnicalFile: WORK COMPLETION.pdf | 2 Dec 2024 |
| Certificates of CA (Form 3)File: CA CERTIFICATE - converted.pdf | 12 Oct 2024 |
| Certificates of CA (Form 3)File: CA CERTIFICATE - converted.pdf | 12 Oct 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A (22-23).pdf | 17 Jul 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A (23-24).pdf | 17 Jul 2024 |
| Details of encumbrances concerned to FinanceFile: DECLARATION REGARDING EMCUMBRANCES.pdf | 25 Jun 2024 |
| Details of encumbrances concerned to LegalFile: DECLARATION REGARDING EMCUMBRANCES.pdf | 25 Jun 2024 |
| Declaration about Commencement CertificateFile: DECLARATION REGARDING COMMENCEMENT.pdf | 25 Jun 2024 |
| Declaration in FORM BFile: FORM B.pdf | 25 Jun 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1.pdf | 25 Jun 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2.pdf | 25 Jun 2024 |
| Disclosure of sold/ booked inventoryFile: DETAILS REGARDING SOLD AND UNSOLD.pdf | 25 Jun 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: ANNEXURE A.pdf | 25 Jun 2024 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: DECLARATION REGARDING SEPERATE BANK ACCOUNT.pdf | 25 Jun 2024 |
| Foreclosure of the ProjectFile: ONE PLOT ONE REGISTRATION.pdf | 25 Jun 2024 |
| Deviation Report with respect to Allotment letterFile: DECLARATION REGARDING DEVIATION.pdf | 25 Jun 2024 |
| Deviation Report with respect to model copy of AgreementFile: DECLARATION REGARDING DEVIATION.pdf | 25 Jun 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM 5 2021-2022.pdf | 4 Feb 2023 |
| Building plan approvalFile: COPY OF LAYOUT PLAN.pdf | 30 Jul 2022 |
| Layout approvalFile: COPY OF LAYOUT PLAN.pdf | 30 Jul 2022 |
| Copy of Layout Approval (in case of layout)File: COPY OF LAYOUT PLAN.pdf | 30 Jul 2022 |
| Building Plan Approval (IOD)File: COPY OF LAYOUT PLAN.pdf | 30 Jul 2022 |
| Layout approvalFile: TOPRANI APPROVED DRAWING 2.pdf | 19 Jul 2022 |
| Building plan approvalFile: TOPRANI APPROVED DRAWING 2.pdf | 19 Jul 2022 |
| Copy of Layout Approval (in case of layout)File: TOPRANI APPROVED DRAWING 2.pdf | 19 Jul 2022 |
| Building Plan Approval (IOD)File: TOPRANI APPROVED DRAWING 2.pdf | 19 Jul 2022 |
| Layout approvalFile: COPY OF APPROVED DRAWING.pdf | 8 Jul 2022 |
| Copy of Layout Approval (in case of layout)File: COPY OF APPROVED DRAWING.pdf | 8 Jul 2022 |
| CERSAI detailsFile: CERSAI_Search_Report_indraprashth.pdf | 1 Jul 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: 2A ENGINEER CERTIFICATE 2019-2020 (1).pdf | 16 Sep 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: 2A ENGINEER CERTIFICATE 2020-2021.pdf | 16 Sep 2021 |
| Declaration about Commencement CertificateFile: DECLARATION REGARDING CC.pdf | 13 Sep 2021 |
| Disclosure of sold/ booked inventoryFile: DETAILS OF SOLD AND UNSOLD.pdf | 13 Sep 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: RERA 2020.pdf | 13 Sep 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: RERA 2021.pdf | 13 Sep 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: FINAL CA SIGN 1718 RERA AUDIT.pdf | 5 Dec 2019 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: FINAL CA SIGN 1819 RERA AUDIT.pdf | 5 Dec 2019 |
| OtherFile: order.pdf | 12 Jun 2019 |
| OtherFile: MFSMAA018619.pdf | 12 Jun 2019 |
| Commencement Certificates / NA Order for plotted developmentFile: SLT permissions.pdf | 23 Mar 2018 |
| Layout approvalFile: slt layout.pdf | 29 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: slt layout.pdf | 29 Jul 2017 |
| Declaration in FORM BFile: SLT Form B Notarised.pdf | 29 Jul 2017 |
| Certificates of CA (Form 3)File: SLT Form 3 CA.pdf | 29 Jul 2017 |
| Proforma of Allotment letterFile: Sale agreement Part 1.pdf | 29 Jul 2017 |
| Proforma of Allotment letterFile: Sale agreement Part 2.pdf | 29 Jul 2017 |
| Proforma of Allotment letterFile: Sale agreement Part 3.pdf | 29 Jul 2017 |
| OtherFile: DevAgreePart1.pdf | 29 Jul 2017 |
| OtherFile: DevAgreePart2.pdf | 29 Jul 2017 |
| OtherFile: DevAgreePart3.pdf | 29 Jul 2017 |
| OtherFile: DevAgreePart4.pdf | 29 Jul 2017 |
| OtherFile: DevAgreePart5.pdf | 29 Jul 2017 |
| OtherFile: DevAgreePart6.pdf | 29 Jul 2017 |
| OtherFile: DevAgreePart7.pdf | 29 Jul 2017 |
| OtherFile: DevAgreePart8.pdf | 29 Jul 2017 |
| OtherFile: DevAgreePart9.pdf | 29 Jul 2017 |
| OtherFile: DevAgreePart10.pdf | 29 Jul 2017 |
| OtherFile: DevAgreePart11.pdf | 29 Jul 2017 |
| OtherFile: SLT POA Part 1.pdf | 29 Jul 2017 |
| OtherFile: SLT POA Part 2.pdf | 29 Jul 2017 |
| OtherFile: SLT POA Part 3.pdf | 29 Jul 2017 |
| Building plan approvalFile: SLT permissions.pdf | 27 Jul 2017 |
| Details of encumbrancesFile: SLT Encumbrance.pdf | 27 Jul 2017 |
| Building Plan Approval (IOD)File: SLT permissions.pdf | 27 Jul 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: SLT Form 1 Architect.pdf | 27 Jul 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: SLT Form 2 Engg.pdf | 27 Jul 2017 |
| Proforma of Allotment letterFile: SLT allotment letter.pdf | 27 Jul 2017 |
| PAN CardFile: SLT PAN.pdf | 26 Jul 2017 |
| Copy of the legal title reportFile: SLT Title certificate.pdf | 26 Jul 2017 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Raigarh
Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.
Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 76 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep Indraprashth on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Dasturi Naka5,900+ in Raigarh
Filed coordinates, straight-line distance. 50 registered projects within 2 km.
NEXA PRIME
NEXAFUTURITY LLP
CKC HUB
UDAY CHANDRAKANT PAYELKAR
CLOUD 9
NEELKANTH ENTERPRISES
LUCKY HOUSE
LUCKY GROUP
NITYA NIRGUN ENCLAVE
PRIYANKA PRASANT GUJAR
SAI SHRUSTHI
SKYLINE DEVELOPERS
See every Raigarh project, with the district possession charts
Builder: Suresh LILADHAR Toprani
Suresh LILADHAR Toprani has 1 registration on MahaRERA, including Indraprashth. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Raigarh district page.
Frequently asked questions
What are my rights if Indraprashth is delayed beyond 31 Dec 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Indraprashth?
The registered promoter entity is Suresh LILADHAR Toprani, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Indraprashth?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Indraprashth?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Indraprashth?
The professionals named in the filing: Architect: Agharkar Consulting Engineers Pvt Ltd VILAS AGHARKAR; Engineer: Agharkar Consulting Engineers Pvt Ltd VILAS AGHARKAR; Chartered Accountant: MS BUTALA MS BUTALA; Chartered Accountant: BUTALA TRIVEDI AND ASSO LLP. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Indraprashth?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback