Red flags

  • Possession 1 months past the filed date
  • Completion date moved by 24 months
  • 2 extensions taken
  • Rs 1.99 crore secured on the land, in favour of Lala Urban Co-op Bank
  • The declared charge does not appear in the CERSAI report on the filing

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Sep 2026Possession promised1 month past this date
14 of 22Construction stages doneacross 2 buildings; furthest along: Sanitary Fittings within the flats /..., 95%
38 of 154Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 211 documents Report an error

IDEAL AVENUE is a Residential / Group Housing project by IDEAL BUILDERS in Pune, Maharashtra, registered with MahaRERA as P52100027916 on 15 Jan 2021. Possession was promised by 28 Sep 2026 and is now 1 months past that date. The completion date has moved by 24 months from the original filing. 116 of the 154 units on this registration are recorded sold or booked, and 14 of 22 construction stages are filed complete.

At a glance

Project

  • NameIDEAL AVENUE
  • TypeResidential / Group Housing
  • Location
    • MOSHI
    • BORADEWADI
    • Pimpri Chinchawad (M Corp.)
    • Haveli
    • Pune
    • 412105
  • Pincode412105
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100027916
  • ReraGenie IDRG-MH-17091

Builder

  • NameIDEAL BUILDERS
  • Entity typePartnership
  • PartnersPRASHANT BHIVSEN BAGAL, Balkrishna Mahadu Sawant

Key dates

1 months past promisethis monthRegisteredJan 2021First promiseSep 2024Revised toSep 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on15 Jan 2021
  • Promised completion28 Sep 2026
  • Revised completionRevised to 28 Sep 2026 (originally 30 Sep 2024)
  • Buildings2 building records
  • Documents filed211 files

Current status

75%116 of 154 units booked
98.0%Work done, per cost certificate

Figures as on 23 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BNA141271071
ANA1312582583

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 23 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

14 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Sanitary Fittings within the flats / premises, at 95%.

B82%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
A78%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises95%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks95%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.95%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.75%

Progress on shared amenities15

As on 23 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes90%
Water SupplyYes90%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes90%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes90%
Street LightingYes85%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes80%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes90%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes90%
Electrical meter room, sub-station, receiving stationYes90%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed269

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots269
Closed/Covered85
Open Space184
BuildingClosed/CoveredOpen SpaceTotal
B3672108
A49112161

Land and ownership3

MahaRERA does not publish landowner contact details. A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area2,754 sq m
Land owned byThe promoter, with other names on the file
Named landowners3
Encumbrance on the landDeclared present
Charge in favour ofLala Urban Co-op Bank
Secured amountRs 1.99 crore
Declared on1 Oct 2024
LandownerVillageDistrict
RAMCHANDRA SASTEPimpri Chinchawad (M Corp.)Pune
DATTU BHIKU SASTEPimpri Chinchawad (M Corp.)Pune
SHARAD TUKARAM JADHAVPune (M Corp.)Pune

Approvals and building plan

Sanctioning authorityPimpri Chinchwad Municipal Corporation
Permissible FSI2802.05
Proposed, not sanctioned2,802 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchAUNDH, PUNE-411007
Estimated costRs 40.85 cr
Cost incurredRs 40.03 cr
Work done98.0%
BuildingWingEstimatedIncurred
ANARs 19.10 crRs 18.72 cr
BNARs 17.90 crRs 17.54 cr
-NARs 3.85 crRs 3.78 cr

Certifying professionals and partners7

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMR SACHIN LADKAT
EngineerRATHIS'S GROUP
EngineerRAJNIKANT SHIVARAY KATTIMANI
Chartered AccountantCA VAIBHAV MODI
Chartered AccountantA S JANGADA & ASSOCIATES
Chartered AccountantNITISH VAIDYA & ASSOCIATES
Chartered AccountantB.D.PAWAR & ASSOCIATES
PartnerRole in project
IDEAL BUILDERS-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100024581Sep 2024 → Sep 2025

Reason as filed by the promoterDue to the non-availability of labor and other resources

EA12082502359Sep 2024 → Sep 2026

Reason as filed by the promoterThe progress of our project was unavoidably delayed due to prolonged timelines in securing critical approvals - particularly the Transfer of Development Rights (TDR) and the subsequent sanction of building plans by the municipal authorities. Despite our continuous follow-up and timely submissions, the process took longer than anticipated, which affected our execution schedule. Therefore, we are requesting an extension.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 23 Dec 2020
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 11 Mar 2025
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 11 Mar 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 11 Mar 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed211

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 211 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1 Q1 FY 2026-27.pdf23 Jul 2026
Withdrawal Update Form 2File: Form 2 Q1 2026-27.pdf23 Jul 2026
Withdrawal Update Form 3File: Form 3 Q1 FY 2026-27.pdf23 Jul 2026
Withdrawal Update Form 1File: Form 1.pdf20 Apr 2026
Withdrawal Update Form 2File: Form 2.pdf20 Apr 2026
Withdrawal Update Form 3File: Form 3.pdf20 Apr 2026
Withdrawal Update Form 1File: Form 1.pdf14 Jan 2026
Withdrawal Update Form 2File: Form 2.pdf14 Jan 2026
Withdrawal Update Form 3File: Form 3.pdf14 Jan 2026
Withdrawal Update Form 1File: Form 1 Final.pdf17 Oct 2025
Withdrawal Update Form 2File: Form 2 Final.pdf17 Oct 2025
Withdrawal Update Form 3File: Form 3 Final_compressed.pdf17 Oct 2025
Withdrawal Update Form 1File: Form 1 Final.pdf22 Sep 2025
Withdrawal Update Form 2File: Form 2 Final.pdf22 Sep 2025
Withdrawal Update Form 3File: Form 3 Final.pdf22 Sep 2025
Withdrawal Update Form 1File: Form 1 Final.pdf1 Sep 2025
Withdrawal Update Form 2File: Form 2 Final.pdf1 Sep 2025
Withdrawal Update Form 3File: Form 3 Final.pdf1 Sep 2025
Form 2A (FY 2023-2024)File: Form 2A Final.pdf1 Sep 2025
Form 2A (FY 2024-2025)File: Form 2A Final.pdf1 Sep 2025
Form 5 (FY 2024-2025)File: Form 5 Final.pdf26 Aug 2025
Form 1File: Form 1 Final.pdf12 Jul 2025
Form 2File: Form 2 Final.pdf12 Jul 2025
Form 3File: Form 3 Final.pdf12 Jul 2025
Disclosure of Sold and Booked InventoryFile: Sold Circular.pdf12 Jul 2025
Form 1File: Form 1.pdf12 Jul 2025
Form 2File: Form 2 Final.pdf12 Jul 2025
Form 3File: Form 3 Final.pdf12 Jul 2025
Disclosure of Sold and Booked InventoryFile: Sold Circular.pdf12 Jul 2025
Form 1File: Form 1 Final.pdf12 Jul 2025
Form 2File: Form 2 Final.pdf12 Jul 2025
Form 3File: Form 3 Final.pdf12 Jul 2025
Disclosure of Sold and Booked InventoryFile: Sold Circular Final.pdf12 Jul 2025
Form 1File: Final Form 1.pdf8 Jul 2025
Form 2File: Final Form 2.pdf8 Jul 2025
Form 3File: Final Form 3 (Q1 24-25).pdf8 Jul 2025
Disclosure of Sold and Booked InventoryFile: Sold Circular.pdf8 Jul 2025
Layout approvalFile: Sanction plan.pdf11 Mar 2025
Layout approvalFile: Sanction Plan.pdf11 Mar 2025
Building plan approvalFile: Building Plan 1.pdf11 Mar 2025
Building plan approvalFile: Building Plan 2.pdf11 Mar 2025
Building plan approvalFile: Building Plan 3.pdf11 Mar 2025
Building plan approvalFile: Building Plan 4.pdf11 Mar 2025
Building plan approvalFile: Building Plan 5.pdf11 Mar 2025
Building plan approvalFile: Building plan 6.pdf11 Mar 2025
Building plan approvalFile: Building Plan 7.pdf11 Mar 2025
Building plan approvalFile: Building Plan 8.pdf11 Mar 2025
Building plan approvalFile: Building Plan 9.pdf11 Mar 2025
Building plan approvalFile: Building Plan 10.pdf11 Mar 2025
Building plan approvalFile: Building Plan 11.pdf11 Mar 2025
Building plan approvalFile: Building Plan 12.pdf11 Mar 2025
Building plan approvalFile: Building Plan 2.pdf11 Mar 2025
Building plan approvalFile: Building Plan 3.pdf11 Mar 2025
Building plan approvalFile: Building Plan 4.pdf11 Mar 2025
Building plan approvalFile: Building Plan 5.pdf11 Mar 2025
Building plan approvalFile: Building Plan 6.pdf11 Mar 2025
Building plan approvalFile: Building Plan 7.pdf11 Mar 2025
Building plan approvalFile: Building Plan 8.pdf11 Mar 2025
Building plan approvalFile: Building Plan 9.pdf11 Mar 2025
Building plan approvalFile: Building Plan 10.pdf11 Mar 2025
Building plan approvalFile: Building Plan 11.pdf11 Mar 2025
Building plan approvalFile: Building Plan 12.pdf11 Mar 2025
Building plan approvalFile: Building Plan 13.pdf11 Mar 2025
Copy of Layout Approval (in case of layout)File: Sanction Plan.pdf11 Mar 2025
Copy of Layout Approval (in case of layout)File: Sanction plan.pdf11 Mar 2025
Commencement Certificates / NA Order for plotted developmentFile: commencement.pdf11 Mar 2025
Commencement Certificates / NA Order for plotted developmentFile: Commencement.pdf11 Mar 2025
Building Plan Approval / NA Order for plotted developmentFile: Building Plan 13.pdf11 Mar 2025
Building Plan Approval / NA Order for plotted developmentFile: Building Plan 12.pdf11 Mar 2025
Building Plan Approval / NA Order for plotted developmentFile: Building Plan 11.pdf11 Mar 2025
Building Plan Approval / NA Order for plotted developmentFile: Building Plan 10.pdf11 Mar 2025
Building Plan Approval / NA Order for plotted developmentFile: Building Plan 9.pdf11 Mar 2025
Building Plan Approval / NA Order for plotted developmentFile: Building Plan 8.pdf11 Mar 2025
Building Plan Approval / NA Order for plotted developmentFile: Building Plan 7.pdf11 Mar 2025
Building Plan Approval / NA Order for plotted developmentFile: Building Plan 6.pdf11 Mar 2025
Building Plan Approval / NA Order for plotted developmentFile: Building Plan 5.pdf11 Mar 2025
Building Plan Approval / NA Order for plotted developmentFile: Building Plan 4.pdf11 Mar 2025
Building Plan Approval / NA Order for plotted developmentFile: Building Plan 3.pdf11 Mar 2025
Building Plan Approval / NA Order for plotted developmentFile: Building Plan 2.pdf11 Mar 2025
Building Plan Approval / NA Order for plotted developmentFile: Building Plan 12.pdf11 Mar 2025

How this compares with Pune

75%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 24 months
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep IDEAL AVENUE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near BORADEWADI13,700+ in Pune

2 kmIDEAL AVENUECompleted 84Lapsed / revoked 50Other 89Dot size: filed unitsN

Filed coordinates, straight-line distance. 223 registered projects within 2 km.

Builder: IDEAL BUILDERS

IDEAL BUILDERS has 1 registration on MahaRERA, including IDEAL AVENUE. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if IDEAL AVENUE is delayed beyond 28 Sep 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of IDEAL AVENUE?

The registered promoter entity is IDEAL BUILDERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in IDEAL AVENUE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for IDEAL AVENUE?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at IDEAL AVENUE?

The professionals named in the filing: Architect: MR SACHIN LADKAT; Engineer: RATHIS'S GROUP; Engineer: RAJNIKANT SHIVARAY KATTIMANI; Chartered Accountant: CA VAIBHAV MODI; Chartered Accountant: A S JANGADA & ASSOCIATES; Chartered Accountant: NITISH VAIDYA & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in IDEAL AVENUE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About IDEAL AVENUE. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save IDEAL AVENUE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.